![]() |
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | |
England and Wales Court of Appeal (Civil Division) Decisions |
||
You are here: BAILII >> Databases >> England and Wales Court of Appeal (Civil Division) Decisions >> Carillion Construction Limited (t/a Crown House Engineering) v Ballast Plc [2001] EWCA Civ 1098 (12 July 2001) URL: http://www.bailii.org/ew/cases/EWCA/Civ/2001/1098.html Cite as: [2001] EWCA Civ 1098 |
[New search] [Printable RTF version] [Help]
COURT OF APPEAL (CIVIL DIVISION)
ON APPEAL FROM QUEEN'S BENCH DIVISION
HIS HONOUR JUDGE FAULKS QC (SITTING AS A
DEPUTY JUDGE OF THE QUEEN'S BENCH DIVISION)
Strand, London, WC2A 2LL Thursday 12th July 2001 |
||
B e f o r e :
LORD JUSTICE WALLER
and
LADY JUSTICE HALE
____________________
Carillion Construction Limited (trading as Crown House Engineering) |
Respondent/Claimant | |
- v - | ||
Ballast Plc (Formerly Ballast Wiltshier Plc) |
Appellant/Defendant |
____________________
Smith Bernal Reporting Limited, 190 Fleet Street
London EC4A 2AG
Telephone 020 7421 4040 Fax 020 7831 8838
(Official Shorthand Writers to the Court)
Crown Copyright ©
ALDOUS LJ:
"1. When was the Sub-contract made? In particular, was it:
1.1. when the Defendant wrote to the Claimant on 22nd October 1996 accepting the offer made by the Claimant in its letter dated 19th July 1996; or
1.2. at the meeting on 8th November 1996; or
1.3. at some other time, and if so, when.
2. To what extent (if at all) was the Claimant obliged to comply with the Employer's Requirements?
3. Were the Main Contract Terms incorporated into the Sub-contract?"
"If we accept your quotation, it will be accepted only to the extent that it is not contrary to, or inconsistent with our obligations under the main contract and our terms and conditions. A copy of the standard form of sub-contract and the main contract (except detailed prices) may be inspected at our office during normal business hours."
"Further to your recent enquiry we now confirm our tender for the Mechanical & Electrical Services to the above mentioned project for the lump sum total of £2,233,500.00 (Two million two hundred and thirty three thousand five hundred pounds).
Our bid is inclusive of 2½% discount for cash payment made within the terms of the contract or for payment received within 30 days of the date of our application for payment.
As the Main Contract is to be let under the ICE form we have based our tender upon entering into a domestic sub contract on the FCEC form suitably amended to agree with the Main Contract amendments where applicable.
In the event of us being required to carry out work on a daywork basis these would be charged under the definition of prime cost of daywork as laid down in the agreement between the RICS and the HVCA/ECA with the following percentage additions:
a) Labour plus 120%
b) Material plus 20%
c) Plant plus 20%
Enclosed for your perusal is a copy of our Tender Summary and Schedule of Exclusions and our Standard Tender Conditions ref: STC/9/JUN/95/GW upon which our tender is based.
This bid is fixed price until April 1997 and will remain open for acceptance for a period of 30 days during which time we look forward to your further instructions."
Attached to that letter was the tender summary, a schedule of exclusions and their standard tender conditions.
"Further to our meeting in your office on 1 May '96, when you gave us your briefing on the proposal now being developed, together with copies of your provisional drawings, we are keen to get schemes firmed up and thus develop the design to allow scheduling for procurement of plant and equipment together with associated builders work which you will require as early as possible.
We would like to brief our designers on the proposal and hope to do this week commencing 13 May '96 with enough firm information from your goodselves to produce some meaningful outlines and layouts sufficient to produce plant requirements, plant room layouts, routing and builders work detail in line with your programme requirements.
All of the above is in hand and progressing. We hope to meet with your goodselves next week, in order to turn up the architectural layout requirements. In the meantime we would be pleased to receive something from you in the form of a Letter of Intent, Instruction or Order. However, we are happy to proceed on the basis of an informal agreement.
We understand that the cost for the project will be developed between us to meet the new proposal being developed, based upon the original employer's requirements, the new layouts and the various tender period cost options provided.
We are not sure exactly which cost options were eventually decided upon in the final negotiation and summarise as follows the costings we provided in the tender and post tender pre contract negotiation period.
We hope the foregoing meets with your approval and look forward to meeting you next week."
"The impression I got was that the guidance I was given was to be clear in what we were actually pricing, and make sure that any grey areas needed to highlighted to Ballast, and where we actually tried to accommodate that was to come up with a fairly comprehensive set of proposals as the basis of our tender, and scope of works."
"21.9 GENERAL
ONLY those systems and services described in the foregoing paragraphs have been included in our tender."
"1.00 CHE are to issue a drawing schedule, including issue dates, w/c 5.8.96 (5
No copies of drawing to be issued to BW, 1 No to TT&H).
2.00 All design and specifications indicated on CHE drawings will be deemed
to be included within the contract price agreed with BW.
3.01 RWG to issue comments regarding CHE design philosophy statement to
CHE and BW.
3.02 BW stated that a revised statement must be issued 6.8.96 (to include
overflow design strategy).
3.03 CHE to issue full details to support any departure from the client's
requirements."
"Further to the correspondence and discussions between yourselves and R W Gregory, please issue your revised outline design statement by Tuesday, 13 August 1996 in order to incorporate, in full detail, relevant items of information which depart from the Employers Requirements."
Crown House complied with that request on 12th August 1996. It took the form of the previous specification with a number of amendments. It contained in paragraph 2.20 the words that had been previously been in paragraph 2.19, which I have set out above. That document was the revised specification. Upon receipt, Ballast passed it on to R.W. Gregory for them to check. Ballast also had a meeting with Drivers Jonas, the employer's representatives, so as to go through the specification. They persistently pointed out that the Crown House specification did not fully comply with the employer's requirements. An example is the comments of Drivers Jonas of 1st October 1996 on the Crown House drawings that were sent by Ballast to Crown House on 22nd October 1996.
"It is our intention to enter into a sub-contract with yourselves for the mechanical and electrical installation on the above project for the lump sum fixed price of £2,320,000.00. (two million, three hundred and twenty thousand pounds)
It may take a short while to prepare the contract documentation but in the interval we should be obliged if you would take such action as may be necessary to avoid delays arising on this project.
The sub-contract, when placed, will be subject to the condition of the main contract which are I.C.E. – DESIGN AND CONSTRUCT approved by the Federation of Civil Engineering Contractors.
Would you please acknowledge that you are proceedings."
That letter, Crown House submitted, was an acceptance of the quotation sent on 12th August with the revised specification. Whatever it was it gave comfort to Crown House who either had just arrived on site or were on site around 22nd October.
"We acknowledge receipt of and thank you for your letter reference
DJW/FC/AD/8084 dated 22nd October 1996 informing us of your intention to enter into a Sub-Contract with ourselves for the Mechanical and Electrical Installation.
We understand that the Sub-Contract will be let under the Form of Sub-Contract as issued by the Federation of Civil Engineering Contractors, and until such time the Sub-Contract is provided, we would be grateful if you could inform us of the 'Specified Dates' for the submission of the monthly value of works completed and materials delivered to site etc, in accordance with Clause 15 of the Sub-Contract.
We feel that it would be in the best interests of both Ballast Wiltshier and ourselves, that a pre sub-contract meeting be convened as quickly as possible, to discuss programme and other matters, and confirm that we are available to attend at your convenience."
"2.00 NOTICE OF COMMENCEMENT OF WORKS
Works started in accordance with the site programme. At present working on site under a Letter of Intent, subject to finalisation of contract documentation.
3.00 EXPLANATION OF CONTRACT & SCOPE OF WORKS
3.01 Aspen tender enquiry.
3.02 Subsequent correspondence.
3.03 Discussion between BW (D Peat) and CHE (C Fox) on 28.6.96. CHE
have agreed that their price complies with the Employer's Requirements and the Fisec report.
3.04 Additional works must be priced and BW will apply for a draft change order.
….
5.00 AVAILABILITY OF INFORMATION (DRAWINGS, SPECIFICATIONS,
WORKING PROCEDURE, ETC)
5.01 CHE are to comply with the Employer's Requirements and if they wish to
depart from these then they must inform BW specifically in writing (note that the client may accept or reject any alternative proposals).
.…
11.00 ATTENDANCES
With reference to CHE's letter dated 19.7.96 referenced GMW/MAK/5152/008/5,
the following items were discussed and commented upon:- ….."
"3.03 Discussion between BW (D Peat) and CHE (C Fox) on 28.6.96. CHE have agreed that their price complied with the Employer's Requirements and the Fisec report.
3.04 Additional works must be priced and BW will apply for a draft change order."
"I preferred the evidence of Mr Fox of the Claimant because having very carefully priced their tender on a specific basis, it seemed to me wholly implausible that experienced and competent businessmen such as those representing the Claimant would already alter the basis of their written tender without any corresponding alterations, or recalculation or price. I was not impressed with the evidence of Mr Peat for the Defendants on this point, which, as I have said, was repetitive on the subject of Employers' Requirements and whose evidence smacked of the benefit of hindsight."
WALLER LJ:
HALE LJ: