![]() |
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | |
England and Wales Court of Appeal (Civil Division) Decisions |
||
You are here: BAILII >> Databases >> England and Wales Court of Appeal (Civil Division) Decisions >> Royal Brompton Hospital National Health Service Trust v Hammond & Ors [2001] EWCA Civ 206 (9 February 2001) URL: http://www.bailii.org/ew/cases/EWCA/Civ/2001/206.html Cite as: [2001] EWCA Civ 206, 76 Con LR 148 |
[New search] [Printable RTF version] [Help]
COURT OF APPEAL (CIVIL DIVISION)
ON APPEAL FROM THE TECHNOLOGY AND CONSTRUCTION COURT
(HIS HONOUR JUDGE RICHARD SEYMOUR QC)
Strand London WC2 Friday, 9th February 2001 |
||
B e f o r e :
____________________
THE ROYAL BROMPTON HOSPITAL NATIONAL | ||
HEALTH SERVICE TRUST | Claimant | |
- v - | ||
FREDERICK ALEXANDER HAMMOND AND OTHERS | Defendants |
____________________
Smith Bernal Reporting Limited
190 Fleet Street, London EC4A 2AG
Telephone No: 020 7421 4040
Fax No: 020 7831 8838
Official Shorthand Writers to the Court)
MR M TAVERNER QC and MR R EDWARDS (instructed by Fishburn Morgan Cole) appeared on behalf of the 8th, 14th and 15th Defendants
____________________
Crown Copyright ©
Friday, 9th February 2001
1. The judge formed a clear and comprehensive view of the progress of the works and of the history of each of the disputed certificates.
2. It was necessary for the architects and for him to consider not just the period by which progress was delayed by a relevant event but also the consequences for the final date in real time. Before actual completion, the final date could only be estimated.
3. The overlap of delays caused by up to four separate relevant events means that an overall appreciation has to be made on a number of different hypotheses before concluding what delay in final completion each of the events has caused or is likely to cause.
4. The inquiry made necessary even by the limited proposed grounds of appeal would make it necessary to examine the whole of the judge's perspective and to question the validity of his conclusions overall.
5. I do not consider that the claimants have any realistic chance of persuading the Court of Appeal that the judge's finding as to the total periods of extension which could non-negligently be granted were wrong or unsupported by the evidence.
6. Similarly, I do not consider that the architects have any realistic chance of satisfying the Court of Appeal that the judge's conclusion were wrong, or should be adjusted by reference to the suggested overlap of commissioning and Hydrotite delays. The consequences of both events and their relationship with each other was carefully considered and taken into account by him.
7. Further and in any event, the specific issues raised by these applications it appears cannot be decided without re-opening much of the evidence and revisiting the judge's conclusions on other issues which are not challenged by either party. I do not believe that this would be a proportionate or correct use of the appeal process in the circumstances of this case.