[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales Court of Appeal (Civil Division) Decisions |
||
You are here: BAILII >> Databases >> England and Wales Court of Appeal (Civil Division) Decisions >> Thomas-Fredric's (Construction) Ltd v Wilson [2003] EWCA Civ 1494 (21 October 2003) URL: http://www.bailii.org/ew/cases/EWCA/Civ/2003/1494.html Cite as: [2004] BLR 23, [2003] EWCA Civ 1494 |
[New search] [Printable RTF version] [Help]
IN THE COURT OF APPEAL (CIVIL DIVISION)
ON APPEAL FROM THE HIGH COURT OF JUSTICE
QUEEN'S BENCH DIVISION
LIVERPOOL DISTRICT REGISTRY
(HIS HONOUR JUDGE MACKAY
(sitting as a deputy High Court judge))
Strand London, WC2 |
||
B e f o r e :
LORD JUSTICE JUDGE
LORD JUSTICE JONATHAN PARKER
____________________
THOMAS-FREDRIC'S (CONSTRUCTION) LIMITED | Claimant/Respondent | |
-v- | ||
KEITH WILSON | Defendant/Appellant |
____________________
Smith Bernal Wordwave Limited
190 Fleet Street, London EC4A 2AG
Tel No: 020 7404 1400 Fax No: 020 7831 8838
Official Shorthand Writers to the Court)
MR A SINGER (instructed by Messrs Knowles Solicitors, Liverpool L1 6EN) appeared on behalf of the Respondent
____________________
Crown Copyright ©
"... on the condition that the work is carried out diligently and that the value of the works is considered correct to that amount."
The letter referred to the appellant, Mr Wilson, in its heading. Beneath the surveyor's signature at the foot, however, the appellant himself had signed the letter "on behalf of Gowersand Ltd".
"1.8 By a letter of 2nd January 2003 the Respondent alleges that he, Mr Keith Wilson, is not the developer in the contract for the construction of the two dwellings at Pear Tree farm. It is alleged that the correct name of the developer is Gowersand Limited, a company for which Mr Wilson is said to be the Company Secretary. As a consequence of this allegation the Respondent further alleges that there can be no referral to an adjudication on the ground that the wrong party has been named in the Notice of Adjudication and the Referral Notice. Following consideration of submissions made by the Claimant on 6th January 2003 the allegation was rejected and the parties informed that the adjudication would continue.
The Respondent provided further documentation in support of the allegation that Gowersand Limited is the developer in the contract by providing copies of letters from the solicitors, accountants and bankers of Gowersand on 6th and 8th January 2003. During a telephone conference the parties were invited to attempt to reach an agreement on this issue. The parties were unable to do so and therefore the Claimant was asked for further submissions on this issue. After consideration of the submissions by the Claimant on 10th January 2003 the parties were again informed that the inquiries as to the identity of the contracting parties were those named in the Notice of Adjudication and the Referral Notice. That being the case the parties were informed that the adjudication would continue.
The investigation of these allegations led the Respondent to request an extension of time for submission of the Response which the Claimant agreed to and revised directions were issued for the submission of the Response and the date for making the decision in this matter.
1.9 It has not been necessary to hold a meeting in connection with this adjudication. This decision has been made solely on the basis of the documentation received.
...
5.2 Throughout the contract the parties were in dispute as to progress, valuation of the works and payment. The parties agree that these disputes led to the formation of a further agreement thereby compromising their differences and disputes under the original agreement and bringing it to a conclusion. The new agreement was made by the parties at a meeting on or about 5th August 2002 and was confirmed by way of a letter from Oldale Owen Associates on 6th August 2002 (the Agreement). The parties agree that the Agreement is a construction contract within the meaning of the Act requiring the Claimant to complete the construction of the two dwellings and associated works for a lump sum payment of £35,000.00 payable over four weeks in instalments of £8,750.00.
...
The Respondent alleges that the Claimant is mistaken as to the identity of the Respondent. The Respondent maintains that the developer is Gowersand Limited whose Company Secretary is Mr Keith Wilson and that Gowersand Limited was the developer in both the original contract and the 6th August 2002 Agreement. It is clear that the developer in the original agreement is Mr Wilson. The quotations and subsequent correspondence from the Claimant are all addressed to Mr Wilson in person. Indeed there has never been shown to me any correspondence from either Mr Wilson or Gowersand Limited. The only reference to Gowersand Limited, on any documentation, appears to have been the 6th August 2002 Agreement which was signed by Mr Wilson on behalf of Gowersand Limited. However that letter merely confirms the agreement made at an earlier meeting when the parties to the contract were clearly Thomas Fredric Construction Limited and Mr Keith Wilson, the parties to the original agreement."
"... the parties are wrongly named in the Referral Notice and we do not believe that you have the jurisdiction to decide the case.
...
The final [agreement] in the 'chain' of contracts was the Agreement of 6 August 2002 noted in the Referral at 2.44. This agreement, we submit, supersedes all other agreements. It is a construction contract within the meaning of Section 104 of the HGCRA (1996) and it is evidenced in writing by the document signed by the Parties, Thomas Fredric Construction Ltd [they did not in fact sign] and Gowersand Ltd.
...
The Adjudicator can have no jurisdiction to decide matters when the Referral does not include a qualifying contract and does not request a decision on the identity of the parties."
"The adjudicator was asked to make a decision on this point [the identity of the contracting party]. Unlike many cases relating to jurisdiction, the adjudicator was asked to, and did, make a decision on this point. To the extent that the adjudicator was entitled to receive the application for adjudication and was entitled to rule on it, and the Act provides that this entitlement entitles the applicant (the claimant) to come to court, that is an important matter because the adjudicator has himself ruled on his jurisdiction."
"11. The statement from Mr Wilson indicates that in fact the adjudicator's decision was wrong and there is still an issue. But in fact, the adjudicator having made his decision, I consider that this Court should follow it and it is not part of the issues between the parties which are relevant for the determination of this Court. In any event, if I am wrong about that, or if I were to hold against the claimant (which I have not done) on that issue, I consider the claimants are quite correct when they say that the evidence all pointed one way.
12. On the basis of a summary judgment application, I would say that the evidence does point, almost entirely substantially, with the result that the parties considered at the time that they were entering into a contract. One party was the claimant and the other party was Mr Wilson. Therefore, I find against the defendant on that crucial issue."
Mr Singer seeks to uphold the judgment on both grounds.
"... for an agreement to be in writing within section 107(2)(c) of the 1996 Act the whole contract had to be evidenced in writing, not merely part of it, and it was not sufficient to confer jurisdiction to entertain an adjudication under section 108 that there was evidence in writing capable of supporting merely the existence or substance of an agreement, the parties to it, the nature of the work and the price; that, since the documents relied on by the defendant contained no evidence of the terms of the oral agreement made between the parties or of those terms on which the defendant sought to rely in the adjudication, there was no 'agreement in writing' within the meaning of section 107; ..."
"The contract shall provide that the decision of the adjudicator is binding until the dispute is finally determined by legal proceedings, by arbitration (if the contract provides for arbitration or the parties otherwise agree to arbitration) or by agreement.
The parties may agree to accept the decision of the adjudicator as finally determining the dispute."
"If the contract does not comply with the requirements of subsections (1) to (4), the adjudication provisions of the Scheme for Construction Contracts apply."
"The decision of the adjudicator shall be binding on the parties, and they shall comply with it until the dispute is finally determined by legal proceedings, by arbitration (if the contract provides for arbitration or the parties otherwise agree to arbitration) or by agreement between the parties."
In short, unless the parties agree to accept the adjudicator's decision as finally determining the dispute -- and that certainly has never been suggested here -- the decision has to be complied with only in the short term, i.e. until the dispute is finally determined by some other means. As Ward LJ explained in the opening paragraph of his leading judgment in RJT Consulting:
"[The Act] gave the important and practical right to refer disputes to adjudication so as to provide a quick enforceable interim decision under the rubric of 'pay now, argue later'."
"8. Ms Rawley also submits that, if a defendant can resist enforcement proceedings on the grounds that the adjudicator has no jurisdiction to make the award, the plain intention of Parliament that adjudicators' awards should be honoured pending final resolution of disputes will be frustrated. It will, she suggests, be easy enough for an imaginative defendant cynically to invent an argument that there was no contract, or that any contract made was concluded before 1 May 1998. In, my view, these fears are exaggerated. It will only be in comparatively few cases that such argument will even be possible. Where they are advanced, the adjudicator and the court will be vigilant to examine the arguments critically.
9. I concluded, therefore, that it is open to a defendant in enforcement proceedings to challenge the decision of an adjudicator on the grounds that he was not empowered by the Act to make the decision."
Then, a little later:
"14. Ms Rawley submits that, by putting forward their case to the adjudicator that the contract was made before 1 May 1998, and that for that reason he had no jurisdiction, the defendants were submitting the question of jurisdiction to the adjudicator for his decision, and agreeing to be bound by it. She relies on the principles enunciated by Devlin J in Westminster Chemicals & Produce Ltd v Eicholz & Loeser [1954] 1 LLR 99, 105-6. Although that case concerned an arbitration, I agree that what Devlin J said was equally applicable to an adjudication. He said that if two people agree to submit a dispute to a third person, then the parties agree to accept the award of that person, or, putting it another way, they confer jurisdiction on that person to determine the dispute. If one of the parties thinks that the dispute is outside the agreement that they have made, then he can protest against the jurisdiction of the arbitrator.
'If he protests against the jurisdiction of the arbitrator, which is merely an elaborate way of saying: "I have not agreed to abide by your award," if he protests in that form it is held that he can take part in the arbitration without losing his rights, and what he is doing, in effect, is that he is merely saying: I will come before you, but I am not by my conduct in coming before you and arguing the case, to be taken as agreeing to accept your award, because I am not going to do so". In those circumstances he may or may not be allowed to take part in the arbitration. Customarily I think he is, but whether that be so or not, if he protests it is well settled that he enters into no agreement to abide by the award.'
15. In my view, the defendants' solicitors' letter of 9 March 1999 stated in the clearest terms that the defendants protested the adjudicator's jurisdiction, and that they would not recognise and comply with any decision to award money to the claimant. The letter also made it clear that, if the adjudication proceeded, they reserved their right to participate, but without prejudice to their contention that there was no jurisdiction. ... It is a question of fact whether a party submits to the jurisdiction of a third person. ..."
"The possibilities of challenging the jurisdiction of an adjudicator are broad if not infinite. This decision confirms that any arguable challenge to the jurisdiction of the adjudicator will secure that the decision of the adjudicator is summarily unenforceable. If the decision is not enforceable immediately, the underlying dispute going to the jurisdiction of the adjudicator has to be resolved either by the court or in appropriate cases by the arbitrator. Accordingly one of the principal objects of the 1996 Act, namely the prompt resolution of disputes, is necessarily but effectively undermined."
I shall return to that later.
"... the sensible way is for whoever objects to raise the objection and to make clear that they are not going to be bound by the adjudicator's decision on that point if it goes against them. Obviously if it goes in their favour that is the end of the matter subject to an application, perhaps by the other side, to the court.
The question I have to decide in this case is not so much whether it is incompetent for the parties to confer jurisdiction because, in my judgment, they can. That is supported by what Mr Justice Dyson said, but whether, on the facts of this case, one can properly say there has been a submission to the jurisdiction of the adjudicator [which] depends on the fair reading and interpretation of the correspondence which passed between the parties ..."
"It seems to me to be clear that if the adjudicator decides a question, then that decision remains decided."
ORDER: Appeal allowed with costs here and below.