![]() |
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | |
England and Wales Court of Appeal (Civil Division) Decisions |
||
You are here: BAILII >> Databases >> England and Wales Court of Appeal (Civil Division) Decisions >> Petroleo Brasileiro SA (Petrobras) v Petromec Inc [2013] EWCA Civ 150 (05 March 2013) URL: http://www.bailii.org/ew/cases/EWCA/Civ/2013/150.html Cite as: [2013] EWCA Civ 150 |
[New search] [Printable RTF version] [Help]
ON APPEAL FROM THE QUEEN'S BENCH DIVISION, COMMERCIAL COURT
MR JUSTICE FIELD
2002 FOLIO 4
Strand, London, WC2A 2LL |
||
B e f o r e :
LORD JUSTICE MOORE-BICK
and
LORD JUSTICE LEWISON
____________________
PETROLEO BRASILEIRO SA ("PETROBRAS") |
Appellant |
|
- and - |
||
PETROMEC INC |
Respondent |
____________________
Mr Nicholas Vineall QC (instructed by Wikborg Rein LLP) for the Respondent
Hearing dates : Wednesday 3rd October 2012
Thursday 4th October 2012
____________________
Crown Copyright ©
Lord Justice Rix :
"36. The negotiation of the charter hire rate was a commercial negotiation. There was no in-put from the Petrobras and [Petromec] technical people as to the new compression specification and no-one on the Petrobras Negotiating Committee was consulted about this change."
The reference to the "new compression specification" will become clearer below. It plays a significant role in this appeal. However, this was only one technical item (albeit an important item) among others which were being negotiated by reference to Annex X.
"12.1 In consideration of Petromec's agreement to upgrade the Vessel in accordance with the Amended Specification Brasoil agrees to pay to Petromec an amount equal to the reasonable extra cost (if any) to Petromec of Upgrading the Vessel in accordance with the Amended Specification over and above the cost that Petromec might reasonably have incurred in Upgrading the Vessel in accordance with the Original Specification."
The compressors
"P3.1.2 – Design Parameters
Gas Compression Capacity: 6000000 m3/d (20oC and 101.3 kpa abs)
…
GAS COMPRESSION
Gas from Safety Gas K.O. Drum is sent to 3 x 50% three stage compressors (3 x 2000000 m3/d). Each compressor stage shall be provided with a cooler, scrubber and compressor. A cooler shall be installed at third stage discharge.
The gas production facilities and utilities shall be design to attend total gas compression capacity (6000000 m3/d)
The compressor performance shall be guaranteed to the flow of 2000000 m³/day at package inlet (at 20oC and 101.3 kPa abs) with gas molecular weight of 18.5…"
The operational capacity of 4 million m³ per day was inherent in the language of "3 x 50%...compressors (3 x 2000000 m3/d)", where 50% was necessarily half of 4,000,000 m/3 per day.
"20. As gas is compressed its temperature rises and it is necessary to cool it at certain stages in the compression process. During the cooling process, liquid droplets are formed which are removed from the gas stream by separation equipment known as a "scrubber" or "knock out drum" prior to entry into the next compression stage. The whole package of equipment that compresses the gas, including a gas turbine that generates pressure through a drive shaft, and the scrubbers, is known as a "compression train"."
"PETROBRAS re-confirmed the compression requirements as stated in the specification. [Petromec] prefers to use compressors based on LM 1600 gas turbines. PETROBRAS stated that their studies indicated:
• 3 x 50% units driven by LM2500's or
or 2 x 100% units driven by LM 5000's
[Petromec] will study the options further and submit to PETROBRAS approval."
"BRASOIL re-confirmed the compression requirements as stated in the specification. BRASOIL stated that their preliminary studies indicated:
- 3 x 50% units driven by LM 2500's or
- 2 x 100% units driven by LM 5000's
CONTRACTOR will study the options further and submit to BRASOIL approval. Both alternatives may be accepted."
"P.3.1.2: BRASOIL re-confirmed the compression requirements as stated in the specification.
The gas compression system will consist of the following equipment: 1 off new gas compression train with a capacity of 2,000,000 Nm³/d, at 20ºC/101, 3 kPa abs.; and 1 off existing HP and Export Gas Compressor, as supplied by Delaval Stork driven by an EGT RLM 1600 gas turbine."
The risers
"The central caisson may be used for attachment of the risers and using the [d]raw works for pull in. BRASOIL accepts this concept. It was agreed that CONTRACTOR would contact flexible riser manufacturers and develop a study to maximise the use of the central caisson. The design would be discussed and finalised with BRASOIL."
The compression deviation and issue
"P.3.1.2: BRASOIL re-confirmed the compression requirements as stated in the specification.
The gas compression system will consist of the following equipment: 1 off new gas compression train with a capacity of 2,000,000 Nm³/d, at 20ºC, 3 kPa abs.; and 1 off existing HP and Export Gas Compressor, as supplied by Delaval Stork driven by an EGT RLM 1600 gas turbine."
"In particular:
1.2 Does it mean, as Petrobras contends, that the cost that Petromec might reasonably have incurred in upgrading the Vessel is to be assessed by reference to the cost that Petromec might reasonably have incurred to purchase one new compressor with a capacity of 2 million cubic metres per day together with the costs associated with the retention of the existing compressor; but otherwise those costs are to be assessed by reference to a total compression requirement of 6m cubic metres per day with inter alia three new compressors and three trains of compression; or
1.3 Does it mean, as Petromec contends, that the cost that Petromec might reasonably have incurred in upgrading the Vessel is to be assessed by reference to a gas compression system consisting of one new compression train with a capacity of 2mn³/d (at 20ºC/101, 3KpA abs) and the existing HP and export Gas Compressor, as supplied by Delaval Stork driven by an EGT RLM 1600 gas turbine?"
"52. In a nutshell, Petrobras' case is that the second sentence governs the cost that Petromec might reasonably have incurred to procure the gas compression system described in the second sentence but otherwise (ie apart from the cost of procuring the gas compression system described in the second sentence), the cost that Petromec might reasonably have incurred in upgrading the platform in accordance with the [Original Specification] is to be assessed by reference to the reconfirmed gas compression requirements under the first sentence…
54. Petromec submitted that the first sentence of the deviation makes no sense when the deviation is construed as a whole in the light of its factual matrix and should be ignored. On that basis, the second sentence should be given its ordinary meaning, namely, that Petromec's sole obligation in respect of gas compression equipment was to supply a gas compression system consisting of one new 2 million m³/d gas compression train and the existing gas compressor."
"53…Thus on Petrobras' case, whilst it would be responsible for meeting the cost of the two additional 2 million m³ per day trains it says are necessary to achieve the total compression requirement of 6 million m³ per day, Petromec would be responsible for meeting the whole of the rest of the cost incurred in upgrading the platform in accordance with the [Original Specification], including the cost of (i) extending the deck space; (ii) gas processing equipment (eg TEG Contactor used for dehydration of natural gas); (iii) the cooling system capacity and other associated items.
54. Petromec submitted…If Petrobras wanted any additional gas compression equipment, it would have to instruct a variation to the specification and pay for it separately, including the cost of any additional deck space."
"59. In my judgment, the compression deviation was intended to operate as a cost allocation exercise. One new 2 million m³/d compression system together with the existing system were never going to be sufficient to answer Petrobras' compression requirement of 6 million m³/d and it is common ground that Petrobras was going to have to pay the additional acquisition cost of such compression systems as might be specified to achieve Petrobras' overall compression requirement…
60. The question is whether any further costs that would arise out of Petrobras' compression systems specification, such as additional deck space and gas processing equipment, are allocated by the compression deviation to Petrobras' account rather than to Petromec's account. In my judgment, they are. In my opinion, the meaning and effect of the compression deviation when construed against the relevant background is that, apart from Petromec having to supply the existing compressor and one new 2,000,000 m³/d gas compression train, the whole of the cost of acquiring, installing and accommodating such further compression systems, including additional deck space and processing equipment, as might be specified by Petrobras to meet their compression requirement of 6 million m³/d, was for Petrobras' account."
"61. In my opinion, the first sentence of the compression deviation is not meaningless. Its function is to specify the area in which the cost allocation provided for in the second sentence is to operate and to require Petromec to supply and install the compression systems specified by Petrobras to satisfy its compression requirements, albeit at Petrobras' cost and after the execution of an agreed variation. In my view, the construction which I propose to give to the variation is a commercial one. It recognises that it is for Petrobras to specify what compression configuration it wanted to achieve the overall daily compression requirement and it contemplates Petromec supplying and installing what is specified, with the cost of the supply, installation and accommodation and all associated costs being borne in accordance with the allocation agreed by the parties. I do not think that the first sentence imposes an overarching obligation on Petromec to deliver a rig capable, with modification if necessary, of accommodating the necessary compression systems to answer the requirement of 6 million m³/d. But even if it does, this does not narrow the width of the cost allocation provision so as to make Petromec liable for the cost of additional deck space to accommodate 3 x 50% systems if this be the configuration Petrobras specifies.
62. In my opinion, once it is recognised that the compression deviation is a cost allocation provision, the fact that Petrobras reverted to a 3 x 50% configuration on 10 December 1996 is nothing to the point. The compression deviation was negotiated without reference to what the engineers were saying to each other. And on any view, some system or systems additional to those identified in the compression deviation were going to be required. It was for Petrobras to specify what its requirements were subsequent to the compression deviation being agreed. The original gas compression specification (3 x 50%) in the South Marlim GTS did not spring back into life. The effect of the deviation is that the acquisition cost and all associated costs of such additional systems as might be subsequently specified are to be for Petrobras' account and not Petromec's."
"The intent of this Specification and the accompanying documents of the BASIC DESIGN DOCUMENTS LIST…is to provide all the applicable technical requirements for the delivery of the…platform, ready in all respects for the intended service…Within the contracted scope of work, the CONTRACTOR shall develop the Basic Design and Detailed Engineering Design documents, studies, analysis, workshop drawings and specifications, provide all labor, services, facilities and equipment, handling, storage, fabrication, erection, procurement, installation, commissioning, testing, transportation and pre-operation (on its final location) of all systems, materials, equipment, machinery, fittings etc., or as may be required to complete the Unit, for its new purpose."
The risers, and the caisson deviation
"Risers and control umbilicals arriving at port and starboard sides shall be connected to a riser hanger structure, arranged on top of pontoons, which shall provide the following operational features:
(i) Considering the Unit in pull-in draught, the connecting point shall rise to a minimum air gap of 3.5m, measured from the connecting point to the surface of calm water;
(ii) In addition, the riser hanger structure and accessories shall have a minimum immersion of 9 meters, taking into account the unit at operational draft, in order to avoid supply boats collision…"
"There was therefore to be dry attachment of the risers at locations on the pontoons that would be 3.5 metres above the waterline at pull-in draught and that would be 9 metres below the water when the platform was in operational mode in the South Marlim sea."
"G1.1.3 para 15: The CONTRACTOR shall follow the Basic Design requirements, but changes may be proposed, if they improve operation, decrease weight or simplify construction. Such changes, as any deviation from the technical requirements intended to be performed by the CONTRACTOR, have to be previously submitted to BRASOIL's approval."
"H.13.2: Although pontoons are the connecting positions for all risers on this document, CONTRACTOR may submit to BRASOIL's approval an alternative positioning for risers support."
"The central caisson may be used for attachment of the risers and using the craw [sc draw] works for pull in. BRASOIL accepts this concept. It was agreed that CONTRACTOR would contact flexible riser manufacturers and develop a study to maximise the use of the central caisson. The design would be discussed and finalised with BRASOIL."
"In relation to risers:
3.1 What number of risers would have been required for South Marlim and how were they required to be bundled or grouped? How would that have differed from the number and bundle grouping required for Roncador?
3.2 What is the meaning and effect of [the deviation from Annex X set out in the previous paragraph]…Does it mean, as Petrobras contends, that the result would have been that Petromec could reasonably have had to install a spider deck, the same as or similar to [that] installed for Roncador? Or does it mean, as Petromec contends, that Petromec could reasonably have used the central caisson for the attachment of the risers and in any event would not have had to install a spider deck?"
"[85] The riser deviation derives its contractual effect from the Supervision Agreement. Like the compression deviation, it was part of the basis on which [Petromec] negotiated what was in effect a fixed price for the South Marlim upgrade. In my judgment, construed against this background, Petrobras could only refuse to accept a design for making maximum use of the central caisson for the attachment of the necessary risers if it had reasonable grounds for doing so. As a consequence, in practice, Petrobras were obliged to accept such a design if it were feasible and did not adversely affect to a material extent the safety and operational efficiency of the platform."
"[95] It is clear that Petrobras prefers dry-attachment of risers to wet attachment. However, in the case of P18 (designed in 1996), 71 of the 74 risers were wet-attached with diver assistance when it was discovered that [that] platform's pull-in draft was worse than expected. In addition, 43 out of a total of 65 risers were wet-attached in the case of P52 in 2007 because steel catenary risers were used on account of the depth of the water and such risers need[ed] to be attached low down on the platform. It is also the case that 9 risers out of 70 were wet-attached on P26 to avoid having them run beneath the accommodation sections and on P36 itself, 6 risers were wet-attached to pontoons for similar safety reasons.
[96] Mr Grealish accepted that dry attachment is a simpler option than wet attachment but neither he nor Mr Taggart thought that wet attachment was not feasible.
[97] Mr Pinto stated in his first witness statement that he did not think that Petrobras would have agreed to wet-attachment of risers on P36 at South Marlim unless it was necessary for safety or specific design reasons: Petrobras' preference would have been to install risers on a spider deck. Leaving aside the consideration that he was called as a factual and not an expert witness (this statement is essentially an expression of opinion), it is to be noted that he accepts, as he was bound to given the examples in paragraph 9[5] above, that Petrobras permitted wet attachment if it were necessary for design reasons.
[98] In my judgment, had Petromec proposed a design whereby 52 risers were to be attached to the central caisson and 46 were to be wet-attached to the pontoons, Petrobras could not reasonably have withheld their agreement. Such wet-attachment was feasible, had been done on a considerable scale in the case of P18 and the cost would have been for Petromec's rather than Petrobras' account."
"The meaning and effect of [the central caisson riser deviation in Annex X] is that the result would have been that Petromec could reasonably have had to install a spider deck the same as or similar to that installed for Roncador."
"[PETROMEC] discussed the possibility of using the central caisson for attachment of the risers, and using the [draw] works for pull in.
PETROBRAS expressed possible acceptance of this concept. It was agreed that [PETROMEC] would contact flexible risers manufacturers and develop a study to maximise the use of the central caisson. The design would be discussed and finalized with PETROBRAS."
By August 1996 this had become: "The central caisson may be used for attachment of the risers…BRASOIL accepts this concept". The final sentence however remained the same (other than that "PETROBRAS" had become "BRASOIL"). Mr Vineall emphasises "may be used" and "accepts this concept". He described this as agreement "in principle", but later thought it prudent to abandon the expression "in principle" and talk in terms of commitment.
"The contention of neither party is adopted. However, Petrobras is correct to submit that it was not committed contractually to the adoption of the central caisson for the attachment of the risers. In the circumstances, the contractual requirement of a design permitting dry attachment of the risers remained, but it is recorded as being common ground that the probable outcome would have been the solution of building a spider deck."
If the parties wish to suggest that any different answer should be entered into an order in the light of this judgment, they are at liberty to make submissions accordingly.
Issues 2 and 4
"The upgrade for South Marlim in accordance with the Original Specification would have required two new semi-submersible seawater lift pumps (with a capacity of 1,550 m³/h) together with a total of nine new discharge coolers."
I would so order.
Conclusion
Lord Justice Moore-Bick :
"P.3.1.2: BRASOIL re-confirmed the compression requirements as stated in the specification.
The gas compression system will consist of the following equipment: 1 off new gas compression train with a capacity of 2,000,000 Nm³/d, at 20ºC/101,3 kPa abs.; and 1 off existing HP and Export Gas Compressor, as supplied by Delaval Stork driven by an EGT RLM 1600 gas turbine."
Lord Justice Lewison :