England and Wales Court of Appeal (Civil Division) Decisions |
||
You are here: BAILII >> Databases >> England and Wales Court of Appeal (Civil Division) Decisions >> Capita (Banstead 2011) Ltd & Anor v RFIB Group Ltd [2015] EWCA Civ 1310 (21 December 2015) URL: http://www.bailii.org/ew/cases/EWCA/Civ/2015/1310.html Cite as: [2016] 2 WLR 1429, [2016] 2 BCLC 32, [2016] PNLR 17, [2016] WLR(D) 61, [2016] QB 835, [2015] EWCA Civ 1310 |
[New search] [Printable RTF version] [View ICLR summary: [2016] WLR(D) 61] [Buy ICLR report: [2016] 2 WLR 1429] [Buy ICLR report: [2016] QB 835] [Help]
ON APPEAL FROM HIGH COURT OF JUSTICE
QUEEN'S BENCH DIVISION
COMMERCIAL COURT
THE HONOURABLE MR JUSTICE POPPLEWELL
Strand, London, WC2A 2LL |
||
B e f o r e :
THE RIGHT HONOURABLE LADY JUSTICE GLOSTER DBE
and
THE HONOURABLE MR JUSTICE HENDERSON
____________________
CAPITA (BANSTEAD 2011) LIMITED (FORMERLY KNOWN AS FPS GROUP LTD & ANR |
Appellants |
|
- and - |
||
RFIB GROUP LIMITED |
Respondent |
____________________
Mr Neil Kitchener QC & Mr Laurence Emmett (instructed by Nabarro LLP) for the Respondent
Hearing dates: 21st & 22nd October 2015
____________________
Crown Copyright ©
Lord Justice Longmore:
Introduction
Facts
"Core Services
2.1.1 Advice & Guidance on Scheme Design & Legislative Trends
- Guidance and recommendations about the design of the Scheme, benefit structure, eligibility criteria, and the specific needs of the Scheme membership.
- Providing information and recommendations about social and political trends affecting the provision of pensions and employee benefits.
- Supplying information and tailored advice regarding the effect and specification of all relevant legislation, regulations and practice of the Pension Scheme Office of the Inland Revenue, the Occupational Pensions Board and the Department of Social Security.
…
2.1.6 Trusteeship Advice
- Offering advice, as necessary to the Trustees on their main duties and discretionary powers.
- Assisting the Trustees in the conduct of their duties.
2.1.7 The Pension Bill/Act
- Advice, guidance and recommendations on the effects of the Pensions Bill …."
"5.8 The Seller undertakes to indemnify and keep indemnified the Buyer on behalf of itself and the Company … from any liabilities costs claims demands or expenses which any of them may suffer or incur arising directly or indirectly from …
5.8.5 any services or products supplied by the Company … or any advice provided by the Company (or any of its employees or agents) prior to the Transfer Date."
i) The introduction of a cap of the retail price index (with a maximum of 5%) for increases in pension benefits, with effect from 6th April 2000 (announced March 2000);ii) The introduction of the same cap for revaluation of deferred pensions, with effect from 6th April 2000 (announced January 2001);
iii) A reduction of the annual accrual rate from 1/60th to 1/80th, with effect from 1st July 2001;
iv) A reduction of dependants' pensions on a member's death from ? to ½ with effect from 1st April 2004 (announced March 2004); and
v) An increase in the active members' contribution rate from 5% to 7%, with effect from 1st April 2004 (announced March 2004).
The Judgment
"1. A clear intention must appear from the words used before the Court will reach the conclusion that one party has agreed to exempt the other from the consequences of his own negligence or indemnify him against losses so caused. The underlying rationale is that clear words are needed because it is inherently improbable that one party should agree to assume responsibility for the consequences of the other's negligence: Smith at p. 168D-E; Ailsa Craig at p.970; HIH at [11], [63]; Lictor at [36].
2. The Canada Steamship principles are not to be applied mechanistically and ought to be considered as no more than guidelines; the task is always to ascertain what the parties intended in their particular commercial context in accordance with the established principles of construction: Smith at p. 177; Ailsa Craig at p. 970; HIH at [11], [61]-[63], [116]; Lictor at [35]. They nevertheless form a useful guide to the approach where the commercial context makes it improbable that in the absence of clear words one party would have agreed to assume responsibility for the relevant negligence of the other.
3. These principles apply with even greater force to dishonest wrongdoing, because of the inherent improbability of one party assuming responsibility for the consequences of dishonest wrongdoing by the other. The law, on public policy grounds, does not permit a party to exclude liability for the consequences of his own fraud; and if the consequences of fraudulent or dishonest misrepresentation or deceit by his agent are to be excluded, such intention must be expressed in clear and unmistakeable terms on the face of the contract. General words will not serve. The language must be such as will alert a commercial party to the extraordinary bargain he is invited to make because in the absence of words which expressly refer to dishonesty the common assumption is that the parties will act honestly: HIH at [16], [68]-[75], [97]."
i) the clause drew a line between wrongful conduct before and after the Transfer Date; it confined the scope of the indemnity to liabilities or losses whose effective cause was wrongful conduct prior to the Transfer Date;
ii) the consequences of employees' conduct after the Transfer Date were for the purchaser's account;
iii) the use of the words "directly or indirectly" required the court to look for the widest link in establishing the causative link between the relevant conduct and the relevant liability or loss incurred by the purchaser such as, for example, loss covered by the second limb of Hadley v Baxendale;
iv) the clause did not however cover conduct by an employee which merely set the background to the loss or could be said to have been causative in the sense of "but for" causation. The conduct must be a real and effective cause of the liability or the loss consequent or the employee's conduct and the claim to which it gave rise;
v) the losses incurred after the Transfer Date had two effective causes in that CHBC was in breach of contract and duty when it failed to make effective amendments to the Scheme rules on or shortly after 6th April 2000, 1st July 2001 and 1st April 2004 and was also in continuing breach of contract and duty after the Transfer Date and liable for later representations founding QEF's claim in deceit. As the judge put it (paragraph 24):-
"immediately after the Transfer Date, CHBC was in continuing breach of duty which gave rise to the continuing losses on a day to day basis."
vi) since the buyer had contractually assumed the risk of negligent or dishonest conduct by the seller's employees after the Transfer Date, it could not rely on conduct prior to the Transfer Date as a concurrent cause because the losses after the Transfer Date would not have occurred if there had not been negligence and dishonesty after the Transfer Date. By this the judge presumably meant that if, immediately after the Transfer Date, Mr Le Cras had complied with his duty of procuring the Trustees' signature to the proposed amendments there would have been no further loss from that time onwards and the previous losses would have been capped; and
vii) it was therefore appropriate to apportion the totality of the loss incurred by Capita/CHBC as a result of the settlement with QEF between losses incurred before the Transfer Date and losses incurred after the Transfer Date; with expert assistance the judge held that the appropriate apportionment was 50/50.
The submissions
i) the entirety of the post-Transfer Date losses was effectively caused by the pre-Transfer Date conduct of Mr Le Cras; the fact that he continued to be negligent and made negligent or deceitful representations was all part of the original breach of contract and duty which occurred before the Transfer Date;
ii) it was inappropriate to talk in terms of "continuing breach of contract or duty" as founding any new liability after the original breach. The concept of a continuing breach occurring "day by day" was artificial and wrong;
iii) if it was appropriate to fasten on any claim for misrepresentation, the relevant representation was made in late 2004 or April 2005 and any apportionment should be recalculated on that basis; and
iv) in any event, any apportionment was wrong because Mr Le Cras's post-Transfer Date was at most a concurrent cause which was not enough to preclude reliance on the indemnity.
(1) Irrelevance of post-Transfer Date conduct?
(2) Continuing Breach of Contract or Duty as a concurrent cause?
"and equally improbable to suppose that if it did exist the obligation would be broken at any time other than when the mistake should have been discovered and put right: namely straightaway."
This also seems to be saying implicitly that Midland Bank was wrongly decided, unless it could be distinguished from Bell on its facts (as to which Mustill LJ presumably agreed with Nicholls LJ, having expressed his entire agreement with Nicholls LJ's judgment "as regards the breach of contract" at page 511F).
(3) The representations
(4) Legal relevance of post-Transfer Date conduct as a concurrent cause
"I consider that the plaintiffs' arguments cannot be accepted. Where there are concurrent causes, each cause is a cause of the consequent event. If the event would have occurred in the absence of a particular fault, that fault is not a cause of the event. Accordingly, it is not correct to say in the present case that the plaintiffs were liable in respect of the death of Mr Quinn because of the breaches of statutory duty; they were liable because of the breaches of statutory duty and the negligence of their servant. It was the concurrent effect of both those causes that gave rise to the death of Mr Quinn and without either of those causes that death would not have occurred and the plaintiffs would not have been liable. Therefore the correct question remains whether the plaintiffs have a right to an indemnity from the defendants in respect of a liability of which a cause was the negligence of one of their servants. It is still necessary to ask whether, as a matter of the construction of the clause, it does cover such liability.
For the purposes of considering the first question I have already quoted from judgments which state the principle to be applied. The principle is that in the absence of clear words the parties to a contract are not to be taken to have intended that an exemption or indemnity clause should apply to the consequences of a party's negligence. Applying that principle and adopting a correct understanding of causation, the parties to a contract such as that with which I am concerned should not be taken to have intended that a party whose servant has been negligent should be entitled to an exemption or an indemnity although there has also been, as a concurrent cause of the relevant loss, a breach of a strict statutory duty."
In this court Steyn LJ (with whom the other members of this court agreed) said that the relevant clause of the contract:-
"…should be construed as providing that the indemnities are not applicable if the event in question has been caused not only by a party's breach of statutory duty but also by his negligence. The short point is that the plaintiffs have contractually assumed the risk of their own negligence and cannot seek to avoid the consequences of that assumption of risk by seeking to rely on a breach of statutory duty."
Conclusion
Lady Justice Gloster:
i) that the judge was wrong to hold that:
"CHBC was also in continuing breach of duty in this respect from day-to-day throughout the period from the Transfer Date to December 2007."
see paragraph 11 of the judge's judgment;
ii) that:
"21. …… despite the existence of a continuing retainer on the part of CHBC, it does not follow that fresh acts of negligence occurred, in respect of each of the amendments, of failing to secure the Trustees' formal adoption of the amendments in a signed document and failing to inform them that the amendments could not be retrospective. These were original acts of negligence which occurred before 30th April 2004 and are accordingly not acts of negligence for which Capita/CHBC are responsible under the indemnity, even though Mr Le Cras made no attempt to repair his omission thereafter.
22. ……
23. But I cannot agree that Mr Le Cras's continuing negligence after 30th April 2004 constituted a fresh cause of action accruing day by day entitling the Trustees and the Foundation to sue CHBC. Nor, therefore, can I agree that that continuing negligence was a cause of the loss suffered by Capita or CHBC, which operated concurrently with the undoubted causative negligence which occurred before the Transfer Date of 30th April 2004. A failure to correct previous acts of negligence is not, to my mind, concurrently causative of losses caused by the original acts of negligence." ;
iii) that there is no distinction of principle between the facts as found by Oliver J (as he then was) in Midland Bank and the facts as found in cases such Bell, Nouri v Marvi and Maharaj v Johnson;
iv) that it is this court's obligation to follow Bell as a decision of this court; and
v) that, accordingly, it is only post 31st December 2004 losses that are irrecoverable under the indemnity (because Mr Le Cras' later representations in late 2004 or 2005 undoubtedly did give rise to new causes of action).
"SECTION 2 - CONSULTANCY SERVICE SPECIFICATION
2.1 Core Services
2.1.1. Advice & Guidance on Scheme Design & Legislative Trends
- Guidance and recommendations about the design of the Scheme, benefit structure, eligibility criteria, and the specific needs of the Scheme membership.
- Providing information and recommendation about social and political trends affecting the provision of pensions and employee benefits.
- Supplying information and tailored advice regarding the effect and specification of all relevant legislation, regulations and practice of the Pension Schemes Office of the Inland Revenue, the Occupational Pensions Board and the Department of Social Security.
2.1.2. Investment Advice
- Advising the Trustees about the attributes and suitability of the Scheme's investments.
- Monitoring and reporting on the investment performance of the scheme's investment manager.
- Providing advice and recommendations about suitable investment vehicles for members' additional voluntary contributions.
2.1.3. Scheme Communications
- Issue of a periodical Newsletter to the Trustees providing information upon benefit trends and pensions practice.
2.1.4. Broking
- Conducting periodic assessments of the competitiveness of the insurance companies with which the Death in Service benefits risks are placed.
- If pensions are to be secured by purchasing annuities, ensuring that competitive rates consistent with security are obtained from the annuity market place.
2.1.5. Meetings
- Attendance at meetings with the Trustees or the Employer as necessary.
- Attending up to four formal Trustees meetings per year.
2.1.6 Trusteeship Advice
- Offering advice, as necessary, to the Trustees on their main duties and discretionary powers.
- Assisting the Trustees in the conduct of their duties.
2.1.7. The Pensions Bill/Act
- Advice, guidance and recommendations on the effects of the Pensions Bill.
2.2 Non-Core Service
2.2.1. Investment Advice
- Assisting the Trustees in the assessment and selection of investment managers.
2.2.2. Scheme Communications
- Drafting, designing and arranging the production of:
a. The Trustees Report and Accounts (to audit stage)
b. A simplified version of the Trustees Report and Accounts for distribution to members.
c. Advising the Trustees about the requirements of the Disclosure of Information Regulations.
2.2.3. Member Communications and Advice
- At the Trustees request, giving presentations to members and prospective members regarding the benefits provided by the Scheme.
- Attending meetings with individual employees in connection with any matters arising from their membership or prospective membership of the scheme.
- Advising individual members on the exercise of any option under the Scheme.
2.2.4. Actuarial Advice
- Advice and recommendation for the development of the most appropriate funding strategy.
- Providing assessments of the cost of individual or bulk augmentations of benefits.
- Advice on scheme solvency.
2.2.5. Pension Bill/Act
- Preparation of a Scheme "audit" to renew the likely effect of forthcoming legislation.
2.2.6. Other Projects
- Non-specified projects that fall outside of the services offered under the core service."
"24. On 6 April 2004 Mr Le Cras instructed Burges Salmon to prepare a deed of amendment in relation to the Scheme to reflect the contribution and benefit changes announced to members in March 2004.
25. On 14 April 2004 Burges Salmon sent a letter to Mr Le Cras advising him, amongst other things, as follows:
"In relation to the effective date for the changes, I should mention at this stage that, in my view, the earliest date these changes can become effective is the date on which the deed of amendment is signed. To give the deed retrospective effect would require the consent of the members under section 67 of the Pensions Act 1995 due to the adverse effect the amendment would have on rights and entitlements accrued in respect of members prior to the date of the amendment..."
26. Thus by 14 April 2004 Mr Le Cras was aware (if he was not so aware before) that (a) intended changes to benefits could not be made by way of announcement to members and (b) the rules could not be amended with retrospective effect so as to adversely affect members' existing rights without raising section 67 issues. Mr Le Cras should have but failed to immediately (on receiving this advice) advise the Trustees of the same and further failed to advise them that the 2000/2001 amendments had not in fact been effected.
27. On 22 April 2004 Mr Le Cras provided Burges Salmon with, amongst other things, copies of the Announcements to Members dated March 2000 and January 2001 together with details of the further changes intended to have been effected in July 2001. He requested that Burges Salmon include such changes in the Deed of Amendment which they were preparing. He further requested that Burges Salmon delete or amend Clause 5 of the then existing draft Deed of Amendment which related to the effective date of the changes.
28. On 10 May 2004 Burges Salmon sent a revised draft deed of amendment to Mr Le Cras for his approval under cover of a letter which stated, amongst other things, as follows:
"...the effective dates for the amendments in the deed are those stipulated in the announcements in accordance with your instructions..,.
...As you know we have expressed reservations about making the amendments retrospective in view of section 67 of the Pensions Act 1995 but you have instructed us to make the amendments retrospective. You have also confirmed that the actuary has said he is prepared to give a certificate. We have drafted the amendments on that basis but express no view as to whether they are legally watertight"
29. Mr Le Cras again failed to forward the above letter to the Foundation and the Trustees and omitted to inform them of the content of the above advice.
30. During June and July 2004 Burges Salmon sent four further drafts of the proposed deed of amendment to Mr Le Cras. On the basis of the documentation provided to the Claimants to date, this correspondence culminated in an email dated 5th July 2004 from Burges Salmon to Mr Le Cras confirming that the changes requested by him had been made and requesting his instructions in relation to two outstanding issues (namely whether there were any Dorincourt members and the potential payment period for childrens' pensions).
31. The Claimants have not to date been provided with any documentation to show that Mr Le Cras responded to the above request for instructions (as he ought to have done). Further the draft Deed was not provided to the Foundation and the Trustees so as to enable the changes to the Scheme to be effected nor were the Foundation and the Trustees provided with any advice in relation to the effect of the failure to execute the Deed. Instead, as set out in paragraphs 32 and 33 below, Mr Le Cras continued to make positive representations to the Foundation, the Trustees and Members that the intended changes had been validly made (when he was expressly aware that this was not the case).
Material Events after 2004
32. At all material times after July 2004 until he left RFBC's employment, Mr Le Cras continued to falsely, alternatively negligently, misrepresent that the changes to the Scheme referred to in paragraph 12 above had been validly made."
"11. CHBC was also in continuing breach of duty in this respect from day to day throughout the period from the Transfer Date to December 2007. The nature of CHBC's retainer, set out in a Services and Fees Agreement dated 1 July 1995, was that it had a continuing role in advising and assisting the trustees and QEF in relation to the Scheme, which included considering the changes previously made, or purportedly made, and considering the implementation of the amendments in the context of subsequent dealings with the trustees. This is apparent from the activity which founded QEF's misrepresentation claim, which involved Mr Le Cras adverting to the previous changes for the purposes of subsequent dealings with the trustees and members of the Scheme. It is also apparent from the activity in the period immediately before and shortly after the Transfer Date. From the end of March 2004 Mr Le Cras had liaised with Burges Salmon who were instructed to include the April 2004 amendments in a draft deed of amendment to the Scheme rules to be executed by the trustees. By 19 April 2004 his instructions included the drafting of amendments to reflect the 2000 and 2001 changes. Discussions with Burges Salmon continued sporadically until July 2004. The last relevant communication appears to have been a letter of 20 September 2004 from Burges Salmon in which the latter notified Mr Le Cras that the partner previously handling the matter had left the firm and asking whether the draft deed of amendment he had sent by email on 5 July was ready to be finalised or whether any further changes were necessary. This is a case which falls on the Midland Bank side of the line (Midland Bank Trust Co Ltd v Hett Stubbs & Kemp [1979] Ch 384) as distinct from one concerned with a retainer to advise on, or carry out, a single transaction such as that in Bell v Peter Browne Co [1990] 2 QB 495 or Nouri v Marvi [2011] PNLR 7. CHBC's retainer included a duty to assist in maintaining a state of affairs, namely that the scheme in force from time to time should reflect the decisions of the Trustees. As such it involved a continuing duty in the sense explained by Dixon J in Larking v Great Western (Nepean) Gravel Ltd [1940] HCA 37; (1940) 64 CLR 221 at 236:
"If a covenantor undertakes that he will do a definite act and omits to do it within the time allowed for the purpose, he has broken his covenant finally and his continued failure to do the act is nothing but a failure to remedy his past breach and not the commission of any further breach of his covenant. His duty is not considered as persisting and, so to speak, being forever renewed until he actually does that which he promised. On the other hand, if his covenant is to maintain a state or condition of affairs, as, for instance, maintaining a building in repair, keeping the insurance of a life on foot, or affording a particular kind of lateral or vertical support to a tenement, then a further breach arises in every successive moment of time during which the state or condition is not as promised, during which, to pursue the examples, the building is out of repair, the life uninsured, or the particular support unprovided. The distinction may be difficult of application in a given case but it must be regarded as one depending upon the meaning of the covenant." (Emphasis supplied.)
"15 But it is necessary to consider the scope of that duty in a little more detail. What does the duty to review the design entail? In what circumstances will an architect be in breach of that duty? I find it convenient to consider an example. Let us suppose that an architect is engaged on the standard RIBA Conditions of Engagement to provide the full service (as PTE were in the present case), including administering a building contract in a standard JCT form of contract. Suppose that he designs the foundations of a building (a large office block), the foundations are constructed in accordance with his design, and several years later, practical completion is achieved. Let us further suppose that the design of the foundations is defective and one which no reasonably competent architect would have produced: in other words, the architect was negligent. There can be no doubt that the architect commits a breach of contract when he completes the design and gives instructions to the contractor to construct the foundations in accordance with it. But in what sense and to what extent is the architect under a duty to review his negligent design once the foundations have been designed and constructed?
16 In my view, in the absence of an express term or express instructions, he is not under a duty specifically to review the design of the foundations, unless something occurs to make it necessary, or at least prudent, for a reasonably competent architect to do so. For example, a specific duty might arise if, before completion, the inadequacy of the foundations causes the building to show signs of distress; or if the architect reads an article which shows that the materials that he has specified for the foundations are not fit for their purpose; or if he learns from some other source that the design is dangerous. In such circumstances, I am in no doubt that the architect would be under a duty to review the design, and, if necessary, issue variation instructions to the contractor to remedy the problem. But in the absence of some reason such as this, I do not think that an architect who has designed and supervised the construction of foundations is thereafter under an obligation to review his design.
17 I do not accept that in every case where an architect has negligently introduced a defective design into a building, he is also by the same token in breach of a continuing breach of a contractual obligation to review his design. In Midland Bank Trust Co. Ltd v. Hett, Stubbs & Kemp [1979] Ch 384, 503C, Oliver J. said:
"It is not seriously arguable that a solicitor who or whose firm has acted negligently comes under a continuing duty to take care to remind himself of the negligence of which, ex hypothesi, he is unaware."
18 In my view, that observation is as apt to apply to an architect as it is to a solicitor. The position is quite different where the architect (or solicitor) knows, or ought to know, of his earlier negligence. When that occurs, then he may well be under a contractual obligation to review his earlier performance, and advise his client honestly and competently of his opinion. Whether he is in fact under such a duty when he has actual or constructive knowledge of his earlier breach of contract will depend on whether the contract is still being performed. If the contract has been discharged (for whatever reason), then the professional person may be under a duty in tort to advise his client of his earlier breach of contract, but it is difficult to see how he can be under any contractual duty to do so.
19 The foundation for the statement in the cases that an architect is under a continuing duty to review his design is the dictum of Sachs L.J. in Brickfield Properties Ltd v Newton [1971] 1 W.L.R. 862, 973F: *522
"The architect is under a continuing duty to check that his design will work in practice and to correct any errors which may emerge. It savours of the ridiculous for the architect to be able to say, as it was here suggested that he could say: 'true, my design was faulty, but, of course, I saw to it that the contractors followed it faithfully' and be enabled on that ground to succeed in the action."
20 But Sachs L.J. was not concerned to explore the scope of an architect's continuing duty to review his design. In my judgment, the duty does not require the architect to review any particular aspect of the design that he has already completed unless he has good reason for so doing. What is a good reason must be determined objectively, and the standard is set by reference to what a reasonably competent architect would do in the circumstances." (Emphasis supplied.)
"It is, of course, true that the solicitor's breach of contract in 1978 did not discharge his obligations. Had the plaintiff learned, a year or two later, of what had happened, he would still have been entitled to go back to his former solicitor and require him to carry out, belatedly, his contractual obligations so far as they could still be performed. For example, lodging a caution. Despite this, it was in 1978 that the breach occurred. Failure thereafter to make good the omission did not constitute a further breach. The position after 1978 was simply that, in breach of contract, the solicitor had failed to do what he ought to have done in 1978 and, year after year, that breach remained unremedied. Nor would the position have been different if in, say, 1980 the plaintiff's solicitor had been asked to remedy his breach of contract and he had failed to do so. His failure to make good his existing breach of contract on request would not have constituted a further breach of contract: it would not have set a new six-year limitation period running. Once again, the position would have been simply that the solicitor remained in breach. Nor, finally, is the position any different because, in respect of lodging a caution, the breach remained remediable until 1986 when the house was sold. A remediable breach is just as much a breach of contract when it occurs as an irremediable breach, although the practical consequences are likely to be less serious if the breach comes to light in time to take remedial action. Were the law otherwise, in any of these instances, the effect would be to frustrate the purpose of the statutes of limitation, for it would mean that breaches of contract would never become statute-barred unless the innocent party chose to accept the defaulting party's conduct as a repudiation or, perhaps, performance ceased to be possible.
For completeness I add that the above observations are directed at the normal case where a contract provides for something to be done, and the defaulting party fails to fulfill his contractual obligation in that regard at the time when performance is due under the contract. In such a case there is a single breach of contract. By way of contrast are the exceptional cases where, on the true construction of the contract, the defaulting party's obligation is a continuing contractual obligation. In such cases the obligation is not breached once and for all, but it is a contractual obligation which arises anew for performance day after day, so that on each successive day there is a fresh breach. A familiar example of this is the usual form of repairing clause in a tenancy agreement. Non-repair for six years does not result in the repairing obligation becoming statute-barred while the tenancy still subsists. The obligation of the tenant or the landlord to keep the property in repair is broken afresh every day the property is out of repair, as Bramwell B. observed in Spoor v. Green (1874) L.R. 9 Ex. 99, 111." (Emphasis supplied.)
To similar effect was Mustill LJ at page 512 F- 513A where he recognised that a solicitor may indeed have a continuing retainer in appropriate circumstances.
"As it seems to me, the passage in Oliver J.'s judgment in Midland Bank v. Hett, Stubbs & Kemp [1979] 1 Ch. 384 at 438 to which we were referred holds that, in a case where there is a continuous contractual obligation, the limitation period does not begin to run until the contract finally becomes impossible of performance. In the case of want of prosecution by a solicitor for example, it would be wholly unsatisfactory to contemplate defining the date of breach for limitation purposes by reference to a solicitor's first failure to take out the summons for directions for the reasons given by Oliver J. Nothing, as I see it, in Bell v. Peter Browne & Co. [1990] 2 Q.B. 495, criticises that aspect of the judgment in a continuing duty case. Indeed as I see it, Nichols L.J. at 501 and Mustill L.J. at 512, seem to recognise that the continuing retainer type of case both exists and will bring a different result from the situation being dealt with in Bell v. Browne. There was, as I see it, clearly a continuing duty on Mr Fulcher up to October 4. His retainer was to make all attempts to preserve the plaintiff's cause of action, including making a section 33 application. That was capable of performance up to the termination of his retainer by the October 4 letter; not before that date should any period of limitation in my view begin to run."
Mr Justice Henderson:
"His failure to make good his existing breach of contract on request would not have constituted a further breach of contract: it would not have set a new six-year limitation period running. Once again, the position would have been simply that the solicitor remained in breach."
Note 1 This case was referred to in Jackson & Powell onProfessional Liability, 7th edition paragraph 5-031, which was cited in the course of argument. [Back]