[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Administrative Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Administrative Court) Decisions >> Foster, R (on the application of) v Oldham MBC & Pugmanor Properties Ltd [1999] EWHC Admin 774 (30 July 1999) URL: http://www.bailii.org/ew/cases/EWHC/Admin/1999/774.html Cite as: [1999] EWHC Admin 774, [2000] Env LR 395 |
[New search] [Help]
1.
Just east of Rochdale Road at Royton within the borough of Oldham, there is
a site of just under 9 acres which was at one time used for the extraction of
sand, clay and gravel. That seems to have been happening in the 1940s, but in
any event on 19th February 1953 an express planning permission was granted for
the getting of those minerals from this land. At that time there was some
housing in the locality, but this was not as extensive as it has since become.
The applicant in these proceedings for judicial review is one of the local
residents. The minerals were worked in the 1950s, and perhaps thereafter, but
it is agreed that none have been worked for a long time.
2.
The Environment Act 1995 sought to deal with such old mineral permissions
granted before 22nd February 1982, apart from those cases where permission had
been deemed to be granted under an interim development order between 1943 and
1948. That latter category of even older permissions had already been covered
by the Planning and Compensation Act, 1991. But both statutory regimes
endeavoured to achieve a record of what permissions existed and to bring about
an updating of the conditions on them, so as to reflect more modern
environmental concerns and practices.
3.
Section 96 of the Environment Act 1995 ("the Act") brought into effect two
schedules relating to this topic. For present purposes only Schedule 13 is
relevant. In broad terms, it requires the preparation by mineral planning
authorities ("MPAs") of a "first list" of mineral sites in their areas. This
is to be done by 31st January 1996. Such sites are to be categorised as active
or dormant sites, and the list is to divide active sites into Phase I and Phase
II sites. The division into those two phases relates to the date of planning
permission or the predominant planning permission for the mineral extraction on
the site. It is unnecessary to go into further detail on that aspect, since it
is agreed that the site with which this court is concerned is a dormant site.
4.
The schedule makes provision for the first list to be advertised, to the
extent that notice must be given in local newspapers by the MPA of the
existence of the list and of the places where it may be inspected: paragraph 5.
It must also serve notice on the apparent owner of any land of interest in any
mineral included within a listed site: paragraph 8. An owner of land or of any
interest in a mineral not included in the first list may apply to the MPA for
that land or interest to be so included, but such an application has to be made
within three months of the advertisement of the list: paragraph 6.
5.
If a site is not included on the list, any relevant planning permission
ceases to have effect on the day following the three-month period for
applications for inclusion, unless such an application has by then been made:
paragraph 12(4). If a site is included, then the landowner or person with an
interest in a mineral may apply to the MPA to determine the conditions to which
the relevant planning permissions relating to that site are to be subject:
paragraph 9(1). In the case of an active Phase I site, that application must
be made within the period specified in the first list: paragraph 3(4). If it
is not, any relevant permission ceases to have effect: paragraph 12(1). In the
case of a dormant site, there is no period of time within which an application
has to be made for a determination of conditions. Instead, it is provided that
no relevant permission has the effect of authorising the carrying out of
minerals development unless an application for a determination of conditions
has been made: paragraph 12(3).
6.
What happened in the present case was that the site east of Rochdale Road
was included by the MPA in its first list as a dormant site. That list was
published in about January 1996. The second respondent, Pugmanor Properties
Ltd ("Pugmanor"), bought the site, and on 17th November 1997 made an
application for a determination of conditions. In that application Pugmanor
specified as a relevant planning permission the permission dated 19th February
1953. It also set out its proposed conditions, as is required by Schedule 13
of the Act.
7.
This application was duly reported to the relevant Sub-Committee by the
officers. The report indicated not only that there was heavy local opposition
to the revival of mineral working on the site, but also that the Council's own
planning department shared what it called "the very real environmental
concerns" arising from the site's proximity to a large number of residential
properties. Indeed the planning officer said in terms that if this had been a
new planning application, he would almost certainly have recommended refusal.
Significantly, as will be seen, he also expressed the view that if this had
been a new planning application, a full Environmental Statement would almost
certainly have been required under the Town and Country Planning (Assessment of
Environmental Effects) Regulations 1988 ("the 1988 Regulations").
8.
The Sub-Committee did consider whether the permission dated 19th February
1953 was still in force but accepted the advice of its officers that it was.
It proceeded, therefore, on 18th March 1998 to determine the conditions to
which that permission was to be subject in accordance with Schedule 13,
paragraph 9(6). The conditions so determined were numerous and undoubtedly
placed considerable restraints on the working of the site. A number of them
were in the form of "Grampian" conditions, so-called, requiring certain matters
to be dealt with before the working of minerals could commence. Nonetheless,
considerable local concern seems to have been aroused by this decision to
determine the conditions.
9.
The applicant now seeks to quash that decision of the Council, dated 18th
March 1998. By a proposed amendment to Form 86A, she also seeks a declaration
that there is no subsisting planning permission in respect of the site capable
of being made subject to conditions pursuant to Schedule 13 of the Act. That
proposed amendment was not opposed by the Council, but was opposed by Mr
Gilbart QC on behalf of Pugmanor. I reserved my ruling on that application to
amend, because the arguments raised were inextricably linked with those being
raised on the substantive application and were thus best dealt with in this
judgment. I shall return to that proposed amendment in due course.
10.
Two main arguments are advanced by Mr George QC on behalf of the
applicant. First, it is said that the 1953 permission was no longer subsisting
and valid at the time when the first list was published by the MPA or when it
made its determination about conditions on 18th March 1998. Consequently the
authority was not entitled to determine conditions in respect of it. Secondly,
it is argued that the authority acted unlawfully in failing to require an
environmental assessment in accordance with the EC Directive 85/337/EEC before
it made its determination on conditions. I shall take those two main arguments
in turn.
11.
Reliance is placed by the applicant on the statutory provisions under which
a planning permission lapses if development to which it relates has not be
begun by a certain date. Section 65(1) of the Town and Country Planning Act
1968 provided that:
12.
In the case of mineral operations, the period of ten years was substituted
for that of five years by the Town and Country Planning (Minerals) Regulations
1971, regulation 6. Since the commencement date of section 65 was 1st April
1969, the effect of these provisions was that a pre-1968 minerals permission
lapsed on 1st April 1979 if development has not begun by that date. That much
is not in issue. Regulation 7 of those Minerals Regulations 1971 provided that:
13.
It is the applicant's case that no such mining operations to which the 1953
permission related had begun to be carried out by 1st April 1979, with the
result that that permission had lapsed long before the Oldham MBC as MPA came
to draw up its list of minerals sites and to consider Pugmanor's application
for a determination of conditions.
14.
There is, however, a preliminary objection raised on behalf of Pugmanor.
Mr Gilbart contends that, at the stage when the MPA is considering an
application for a determination of conditions, it is no longer open to it to
decide whether or not a planning permission relating to the site is still
valid. It is submitted that, once the site has been included in the first
list, the MPA is under a duty to determine conditions when an application for
such a determination is made. Mr Gilbart points to paragraph 9(6) of Schedule
13, which begins by stating:
15.
With certain exceptions, irrelevant for present purposes, "relevant
planning permission" means any planning permission granted after 30th June 1948
for minerals development: see paragraph 1(1) of the Schedule. It is accepted
by Pugmanor that in drawing up the first list of mineral sites, the MPA is
entitled and bound to consider whether a relevant planning permission exists,
because that is a crucial part of the definition of a mineral site. "Mineral
site", according to paragraph 1(1) means "the land to which a relevant planning
permission relates". Mr Gilbart also accepts that at the stage of drawing up
the first list, the MPA must consider whether a planning permission still
subsists. If it does not, then it is not a "relevant planning permission".
But he argues that, once the first list has been drawn up and advertised and
the period of three months for land owners to challenge the omission of a site
has expired, the MPA has no power to determine that a site was wrongly included
in the list. Reliance is placed on the decision of Lightman J in R v North
Lincolnshire Council ex parte Horticultural and Garden Products Ltd (1998) 3
PLR 1, when it was held that there was no implied provision in Schedule 13
whereby an MPA could entertain an application to add a site to the list once
the three months had expired. The court there emphasised the purpose of this
legislation of achieving certainty and finality as to the sites enjoying
mineral planning permission (see page 8).
16.
If that is so, submits Mr Gilbart, then it would be wrong to allow judicial
review proceedings, well outside three months from the advertising of the list,
to challenge the inclusion of a site in the list. That essentially is what
this challenge is, a form of collateral challenge to the inclusion of
Pugmanor's site on the list. The list should be seen as definitive of the
relevant planning permissions.
17.
This argument seems to me to misunderstand the role of the first list. It
is a list of mineral
sites,
not a definitive list of relevant planning permissions. It is right that, at
the stage of compiling the first list, the MPA has to consider whether a
relevant planning permission or permissions exist in respect of a given site,
but it need not identify those permissions in the list, merely whether the site
is an active Phase I site, an active Phase II site or a dormant site, together
with the date by which any paragraph 9 application is to be made in relation to
an active Phase I site: paragraph 3. When an owner subsequently makes an
application for a determination of conditions under paragraph 9, he is required
at that stage to identify "
any
relevant planning permissions" relating to the site: paragraph 9(2)(c) -- my
emphasis.
18.
It is in that context that the undoubted duty of the MPA under paragraph
9(6) to determine conditions has to be seen. It is a duty to determine the
conditions to which "each relevant planning permission relating to the site is
to be subject." It has to be remembered that there may be more than one
permission relating to the site. The MPA may not have identified them all when
compiling the list. If an owner applies under paragraph 9 in respect of a site
on the list, he can identify a permission or permissions additional to whatever
the MPA had in mind when it included the site in the list. If this situation
arises, the MPA must be entitled to consider whether such additional
permissions are still valid or not. That continuing validity is part of the
concept of a "relevant planning permission", since it would be absurd to
require a site to be included on the list merely because of a lapsed
permission. But in the same way, it would be absurd to require the MPA to
determine conditions for a lapsed permission. The MPA is entitled to consider
the validity of any permission alleged in a paragraph 9 application to be a
"relevant planning permission" and to do so at that stage when it is dealing
with that application.
19.
I appreciate that, in a case such as the present where there is only one
permission alleged to be relevant, a decision that that permission is no longer
valid amounts to saying that the site should not have been included in the list
in the first place. But that is not, in fact, the same thing as amending the
list or taking the site out of it. The site would remain in the list, until
the list is eventually reviewed. However strange that might seem, it is a more
sensible result than depriving the MPA of the power to consider the validity of
planning permissions identified in a paragraph 9 application. The MPA cannot
be bound to accept the applicant's assertion that A, B and C are "relevant
planning permissions" relating to the site. It has to exercise its own judgment
on the matter and in so doing, it must consider any issue concerning the
continued validity of any of those permissions. I therefore reject the
preliminary objection raised by the second respondent.
20.
I revert, therefore, to the issue itself of the validity of the 1953
permission, which turns upon whether any mining operation to which that
permission related began to be carried out before 1st April 1979. This is not
simply a question of whether any mining operating began physically to be
carried out after the grant of that permission on 19th February 1953. A series
of authorities has established the legal proposition that, for development to
have been development to which a permission related, it must have been
development authorised by that permission and consequently must not have been
in breach of a condition on the permission. I reviewed the authorities in a
recent judgment in Leisure Great Britain Plc v Isle of Wight Council
(1997-L-1499; judgment 28th June 1999) and I do not propose to take time doing
so again. It is enough to set out the familiar passage from the judgment of
Woolf LJ (as he then was) in Whitley and Sons v Secretary of State for Wales
(1992) 64P and CR 296, at 302:
21.
Mr George QC on behalf of the applicant relies on those principles, and
draws attention to condition 1 on the 1953 permission. That needs to be set
out in full:
22.
This 1953 permission was, in fact, an amended re-issue of a permission
granted the previous year. The relevant committee had resolved in May 1952 to
grant permission for the getting of sand, clay and gravel on the site, with a
condition requiring a detailed plan and scheme to be submitted by 31st December
1952. However, due it seems to confusion arising from the division of planning
responsibilities between the County Council and the then Royton UDC, no
planning permission was actually issued until 6th December 1952. The
authorities recognised that this left an unreasonably short period for the
submission of a scheme of working, and so the fresh permission dated 19th
February 1953 was issued bearing the date in condition 1 of 31st March 1953.
23.
On 30th March 1953 agents for the landowner wrote to the UDC, enclosing a
tracing. The tracing is no longer to be found, but the letter stated that it
showed the two areas from which it was proposed to excavate sand and gravel,
the area upon which it was proposed to tip waste materials and the approximate
boundaries of the existing sand pits. The letter continued:
25.
One notes that there was no suggestion in that reply that the further
submission being indicated would be too late to meet the terms of condition 1.
26.
Nothing further seems to have taken place by way of scheme details for
about one year. There was then a meeting between representatives of the
landowners and council officers "to discuss the drawing up of the scheme of
working". The outcome of that meeting seems to have been that the officers
would prepare a draft scheme for the landowners to submit if they agreed with
it. Certainly a number of internal memoranda show the officers drawing up a
scheme dealing with the level of working, areas of tipping, removal and
spreading of top soil to a particular depth, and tree planting. This was duly
sent to the landowners and a further meeting was held on 19th May 1954. The
correspondence after that meeting makes it clear that the planning authority
was expecting the landowners or their agents to frame their scheme of working
as they thought fit and to submit it for consideration: see letter 20th May
1954.
27.
Nothing had been received by 7th July 1954, when the Divisional Planning
Officer wrote again to the agents, drawing attention to condition 1 on the 1953
permission and asking for the necessary scheme to be submitted. In their
reply, the agents referred to the letter of 30th March 1953 and the enclosed
tracing, saying that "we do not appear to have received any reply to this draft
scheme." The letter ended by saying that they were working on an amended
scheme, which they hoped to let the officer have in the near future.
28.
No further proposals were received and by October 1954 the officers of the
two authorities were discussing possible enforcement action. What apparently
was contemplated was a notice under which the sanction would be the authority
preparing the scheme and recovering the cost. It seems that an enforcement
notice was duly served on 10th November 1955, but a copy of the notice itself
can no longer be found. It seems from the UDC records that it required
compliance with the conditions on the permission. Not long afterwards, on 24th
January 1956 the agents wrote to the UDC, referring to their original "draft
scheme" and proposing a meeting to discuss a proposed scheme. A further letter
from them, dated 16th February 1956, stated that they were not in full
agreement with the scheme as drawn up by the planning officers but they would
submit an amended version.
29.
In fact, there was then a further meeting between the owner, his agent and
Council Officers on 24th May 1956. A Council file note records that the
discussion was about the details which should be submitted to meet condition 1,
and that it was pointed out to the owner and his agent that what was in effect
needed was the position when the excavation and tipping had been carried out.
The owner promised to submit the necessary details within 14 days. The
correspondence indicates he did not do so, but on 22nd June the agent brought
plans and proposals based on the Council's draft scheme to a further meeting
and these were discussed at length. It seems that the full detailed scheme was
expected to be submitted very soon. However, it had not been received by 24th
July 1956.
30.
There is then a gap in the available records for over 14 years. The next
letter on file is one from the agent dated 15th January 1971, asking the
Divisional Planning Office whether or not the 1953 permission was still valid.
The letter went on to say that "the workings
would
be executed in accordance with the plan prepared by your department" (emphasis
added). A file note from the planning department's files records that a
planning officer "persuaded" the agent that the permission was not valid
because a scheme had not been submitted within time.
31.
None of the parties to these proceedings have been able to discover
anything further to indicate that a full scheme under condition 1 was ever
submitted, beyond those documents to which I have already referred, nor any
approval by the planning authority of such a scheme, beyond the degree to which
those documents and events can be construed so as to amount to an approval. It
is right that, at a much later planning inquiry in 1986 into a residential
proposal for the site, the Oldham MBC, by then the planning authority, accepted
that the 1953 permission was still valid, but it is unclear on what basis they
did so and it is not suggested that that acceptance creates any kind of
conclusive finding to that effect.
32.
On the basis of this history, Mr George submits that any mineral operations
carried out after the date of the 1953 permission were in breach of condition
1. In the light of the planning authority's willingness to see a scheme
submitted after the specified date of 31st March 1953, he does not argue that
condition 1 could not have been met by an approval of a scheme after that date.
But he relies on that part of the condition which states:
33.
It is contended on behalf of the applicant that there never was an approved
scheme under condition 1, and in consequence any mineral operations on site
were no more authorised by the permission than those operations which had
preceded it.
34.
On behalf of the planning authority, Mr Sauvain QC emphasises that this
permission was one for the continuation of mineral workings as condition 1
indicates, so that the then planning authority knew that work was going on at
this site. There is no condition saying that working must stop until a
detailed scheme is approved. The condition is not drafted in such terms as "No
development shall be carried out until a scheme has been approved". The
authority merely set a date in the future for the submission of such a scheme.
Consequently, he submits, work could take place and did take place under this
1953 permission until a scheme had been approved. Only then would all workings
have to accord with the approved scheme.
35.
Secondly he contends that the landowner did comply with the first part of
condition 1 by submitting the letter and tracing of 30th March 1953. That
complied with some of the requirements set out in paragraphs (a) to (d) of the
condition, and in particular dealt with the method of working, even if there is
nothing about the finished contours or about topsoil. The draft scheme
produced by the officers had only limited extra detail. By the time one gets
to July 1956, it seems that a scheme had broadly been agreed and all that was
lacking was the formal submission of it by the owner. Reliance is placed by Mr
Sauvain on the decision in R v Flintshire County Council, ex parte Somerfield
Stores Ltd (1998) P and CR 336, where it was held by Carnwath J that a
condition had in substance been complied with where the relevant traffic report
had been submitted by the applicant and approved by officers but the written
notice of approval had not been issued by the time work began on site.
36.
Both he and Mr Gilbart make the point that it is dangerous to make firm
conclusions about what happened some forty-five years or so later, especially
when the records indicate some confusion as between the County and District
authorities. Mr Gilbart largely adopts Mr Sauvain's submissions on this topic,
but he also emphasises that by the time of the meeting on 24th May 1956 all
that seems to have been still outstanding were the details concerning the
steps to be taken once the excavation had finished. There was no disagreement
therefore about the details of the workings themselves, which were continuing
and which were a start to development under the permission. Moreover, it is
submitted on behalf of Pugmanor that there is a need for some flexibility to be
allowed to a planning authority in the way in which it deals with the
implementation of a condition: see Agecrest v Gwynedd County Council (1998) JPL
325.
37.
Although Mr George argued that one could not conclude that workings were
actually going on on this site during the brief period between the grant of
this permission on 19th February 1953 and 31st March 1953, it seems to me that,
on the balance of probabilities, some mineral operations would have taken place
then, even if only to a limited degree. This was a working pit, albeit a
slowly working one. In any event, his acceptance that a scheme could be
lawfully submitted and approved after 31st March 1953 robs that date of any
real significance. If a scheme could thereafter be submitted and be approved,
the operations could take place after that date and still be authorised by the
permission. There could be a start to development after that date.
38.
Condition 1 is not expressed in a negative form, prohibiting operations
under the permission until a scheme has been approved. Such a negative form is
often used when development is not authorised until such an event, and in a
number of the cases on this topic, such as Flintshire and Agecrest (ante), the
court was dealing with such conditions. Indeed, if one goes back to the
decision of Forbes J in Clwyd County Council v Secretary of State for Wales
(1982) JPL 696, one finds some emphasis being placed by the court on such a
formulation. The learned judge there approached the issue in terms of whether
the breach of conditions rendered the mining operations "unlawful", because
that was how the argument was being advanced by counsel. The court found that,
because the conditions in question did not use expressions such as "No
development shall be carried out until ..." they were not conditions precedent,
and consequently failure to observe them did not make the development unlawful
(page 699).
39.
It will be seen from the passage cited from Whitley earlier in this
judgment that the law has moved on since 1982. In Whitley, Woolf LJ, with whom
the other two Court of Appeal judges agreed, rejected the approach of asking
whether the conditions could be classified as conditions precedent. That, said
the court, is neither necessary nor helpful. The true test is whether the
operations are permitted by the planning permission read together with the
conditions. "If the operations contravene the conditions, they cannot be
properly described as commencing the development authorised by the permission"
(page 302). I note that one of the conditions under consideration in Whitley
was not expressed in the form of a condition precedent, but was somewhat
similar to that part of condition 1 in the present case on which the applicant
relies. Condition 2 in Whitley was that:
40.
That is negative in form, but it is difficult to distinguish it from the
wording of condition 1 here, namely:
41.
The approach in Whitley has been followed in a number of subsequent
decisions, including several in the Court of Appeal. In Handoll and Suddick v
Warner Goodman and Street (1995) 1 PLR 40, the Court of Appeal relied on
Whitley as supporting the proposition, which it accepted, that:
42.
In Daniel Platt Ltd v Secretary of State for the Environment (1997) 1 PLR
73, the Court of Appeal again endorsed the principle spelt out in Whitley.
43.
One turns, therefore, to look at the 1953 permission and its conditions, in
particular condition 1. Mr Sauvain is right in asserting that the permission,
read as a whole, does not seek to stop the mining operations which had been
going on from before the grant of this permission. But I find his argument
that the permission was, therefore, authorising those operations in some
untrammelled way, until such time as a scheme was approved unpersuasive. It was
inevitable for practical reasons that the permission would allow some time for
a detailed scheme to be submitted. But the wording of condition 1 is quite
clear. It requires
all
operations (my emphasis) to be carried out in accordance with the scheme as
approved or modified. It does not say that, once a scheme has been approved,
then the operations must accord with it, implying that there is some exempt
period prior to that date, of approval during which the permission allowed any
method of working to take place. It is significant that the final sentence of
condition 1 demonstrates how much importance was being attached to complying
with an approved scheme: even if the applicants seek to amend the approved
scheme at some future date, it must be complied with until the amendments have
been approved.
44.
One quite accepts that the planning authority, in practice, allowed
operations to continue, just as they had been continuing during the 1940s and
up to the grant of this permission. But I conclude that Mr George is right
when he submits that this was tolerated, unauthorised working, rather than
authorised working. It did not mean that the permission authorised working
outside the confines of a scheme until such a scheme had been approved or even
until 31st March 1953, by when a scheme was to be submitted. There was no
halfway house here. On the wording of condition 1, works done in accordance
with an approved scheme were authorised by the permission; works done other
than in such accordance were not done under the authority of this permission.
I therefore reject Mr Sauvain's first submission on this issue.
45.
I do accept, however, that, given the wording of condition 1, there could
be retrospective authorisation of works carried out after the grant of this
permission. That accords with the actual outcome of Whitley. In the present
case, all operations have to comply with the approved scheme, but nothing in
the wording of this permission and its conditions, requires the scheme to be
approved first. If a scheme was eventually approved and operations had been
carried out which could be seen to have been in accordance with that scheme,
then that would suffice to render those operations authorised ones. That
seems, to me, to be the significance of the fact that condition 1 does not, in
terms, prevent operations being carried out
until
a
scheme has been approved, but merely requires them to be in accordance with the
approved scheme.
46.
That gives rise to the vital question: was there an approved scheme in this
case? The scheme, such as it was, submitted on 30th March 1953, was never
approved. Mr George criticises that submission for its deficiencies when
measured against the details required by condition 1, but the fact is that the
authority allowed further and subsequent discussions, about a scheme, to take
place. One is having to look, therefore, at the period after 31st March 1953,
to see if a scheme was ever approved.
47.
In so doing, I bear in mind the dangers inherent in interpreting documents
and events so long afterwards. I also accept the approach adopted in
Flintshire that, if an authority or its officers with delegated powers,
approve a scheme or report required under a condition, the mere absence of
formal notices will not prevent the condition from having been complied with.
48.
In the present case, it is right that the local authority officers drew up
a draft scheme to assist the landowner and repeatedly suggested that he submit
it. On the evidence before me, he never did so. On the other hand, it seems
that in due course, a considerable measure of informal agreement was reached,
in the course of discussions, about what ought to go into a detailed scheme,
certainly on the details of the method of working. That appears to be the
implication of the file note dealing with the meeting on 24th May 1956. A lot
of progress towards a detailed scheme had been made, even though at times the
officers seem to have thought that the landowner was using delaying tactics.
49.
Does all this amount to compliance with condition 1? I have concluded that
it does not. A degree of informal agreement on what ought to go into a detailed
submission falls short of such compliance, especially given the history of this
site where there were repeated meetings and apparent progress and yet no
submission of details then resulting. The matter can be tested by asking what
would have happened if, after 1956, operations had been carried out which did
not accord with the method of working discussed between the officers and the
owner or his agents. Could the planning authority have brought enforcement
action on the basis that there was an approved scheme under condition 1, from
which scheme there had been a departure? In my judgment, they could not. They
could not have successfully asserted that there was ever an approved scheme,
even to the extent of the excavating operations themselves. Not merely was
there no approval issued by the planning authority, but the matter never went
before the relevant committee for decision. Indeed, it is difficult to see
that things ever advanced to the stage of a submission by the landowner for
approval, as opposed to a series of discussions about the possible content of a
scheme. In saying that, I recognise that there was the earlier submission of
30th March 1953, but that clearly was never approved and the landowner took no
steps to challenge the lack of approval.
50.
I conclude, therefore, that none of the mining operations carried out on
this site after the grant of the 1953 permission complied with condition 1 of
that permission and for that reason those operations were not authorised by the
permission. It follows that there never was a start to operations under that
permission and that in consequence, the permission lapsed in 1979. It is no
longer valid.
51.
In the light of that conclusion, I propose to deal only briefly with the
other main argument advanced by the applicant. There is no doubt that, in the
light of the decision of the House of Lords in R v North Yorkshire County
Council ex parte Brown (1999) 2 WLR 452, the determination of conditions under
Schedule 13 is a "development consent" within the meaning of Directive
85/337/EEC and that the latter is directly effective. The North Yorkshire case
was, it is true, concerned with conditions for "old mining permissions" under
the Planning and Compensation Act 1991, but the regime established for the
latter tranche of mining permissions by Schedule 13 closely follows that
established for permissions under the 1991 Act. The reasoning of the House of
Lords is valid and applicable to determinations under Schedule 13, and all the
parties to the present proceedings accept that.
53.
Article 4 takes one to Annexes I and II to the Directive, the first of
those being a list of the classes of projects where, by virtue of the
Directive, there has to be an environmental assessment. That does not apply
here. But according to Article 4(2), projects of the classes listed in Annex
II shall be made subject to an assessment where Member States consider that
their characteristics so require. One of those classes so listed is the
extraction of minerals such as sand and gravel.
54.
In fact, there is as yet no provision in English law which deals with the
application of the Directive to the determination of conditions under Schedule
13 of the Act. The 1988 Regulations do not apply, nor does the Act itself make
any such provision. Both those Regulations and the Act were passed into law
before the North Yorkshire decision held that the Directive applied to a
determination of conditions. But that does not absolve a local authority,
which is an emanation of the state, from observing a directly applicable
Directive: see Marshall v Southampton Area Health Authority (1986) QB 401;
Foster v British Gas (1991) 2 AC 306. Therefore, where an MPA considers that
a development project is likely to have "significant effects on the
environment" by virtue of such matters as are referred to in Article 2(1), it
is obliged to have an environmental assessment before consent is given.
55.
In the present case, both the MPA and Pugmanor concede that an
environmental assessment was required, and required before consent was given.
None was, in fact, carried out before the determination of conditions on 18th
March 1998. But Mr Sauvain points out that, in the absence of any domestic
implementation of the Directive in this situation, it is open to the MPA to
integrate environmental impact assessment into the existing procedures for
consent: see Article 2(2). This, he argues, is what the MPA did here, because
they imposed numerous conditions requiring more information to be supplied
before mining operations could be resumed. It is contended that this is a
legitimate procedure to adopt in a case such as this, where permission had
already been granted back in 1953, and only the conditions of the permission
are under consideration. It is on this basis that it is sought to distinguish
the decision by Sullivan J in R v Rochdale MBC ex parte Tew (unreported;
CO/3702/98, judgment 7th May 1999). There, the court was dealing with
applications for planning permission for a proposed business park of about
some 170 hectares. The court rejected an argument that some of the information
required for an environmental assessment could be achieved at the later stage
of considering the reserved matters required by conditions on the permission,
saying that by then, it might be too late to reflect any significant adverse
impacts so identified, because permission would already have been granted. The
horse would already have bolted. In contrast, says Mr Sauvain with Mr
Gilbart's support, on a Schedule 13, paragraph 9 determination, the principle
of permission for mineral extraction has already been established. All that is
in issue is what conditions should be applied to the working.
56.
I can see the force of that argument and, in the peculiar circumstances of
a Schedule 13 application in the current state of domestic law, I accept that
it is theoretically open to an MPA to determine conditions which themselves
require all the remaining information for environmental assessment to be
submitted and for detailed schemes to be approved in the light of such
information before the mineral operations can proceed. The issue is whether the
conditions which were determined in this case do that.
57.
The conditions are undoubtedly extensive and far-reaching. There are 56 in
all. Many require further information and further detailed schemes to be
submitted before development begins. Condition 20 requires a comprehensive
site investigation into the hydrogeology of the site and adjacent land before
any mineral extraction begins, so that the effects on the water table and land
stability can be determined. A full working programme has to be approved
covering such matters as the depth of working, the construction of noise baffle
mounds and the means of dealing with surface and groundwater flows, before any
mineral extraction begins.
58.
The reason for this condition (Number 21) is to avoid unacceptable risk of
instability and/or settlement or unacceptable noise disturbance to nearby land
and properties. There are a large number of conditions directed towards
establishing existing noise and vibration levels and towards achieving
acceptable noise levels at residential properties. So far as dust is
concerned, no development is allowed unless and until background dust
monitoring has been undertaken (condition 43) and a dust action plan approved
(condition 44). There is provision for a restoration scheme for the site, and
all these conditions have to be seen in the context of condition 4, which puts
a two-year time limit on the extraction and processing of minerals and the
deposit of materials.
59.
Significantly, a report prepared for the applicant in these proceedings by
environmental consultants, Hyder, acknowledges that a number of issues have
been adequately addressed by these conditions. Those include hydrology,
geology and noise, and the impact of dust on residents. They assert that some
other impacts of dust and pollutants have not been addressed, though I find
that difficult to accept. But the question is whether these conditions
adequately cover the matters to be covered by an environmental assessment.
60.
I remind myself that such an assessment is required to identify, describe
and assess in an appropriate manner the direct and indirect effects of a
project on: human beings, flora and fauna; soil, water, air, climate and the
landscape; the interaction between those factors; and material assets and their
cultural heritage: see Article 3 of the Directive. Mr George submits that in a
number of respects the conditions will not achieve what is required under the
Directive, and in my judgment he is right. There is no provision in them for
any assessment of visual impact of the excavation with its plant and machinery
and vehicles and its associated processes. That would not matter if such an
assessment had already been done, but there is none to be found in any of the
reports to committee or other documents before them. Such an assessment
should cover the effects on residents and others in the locality, including
those using the roads and public footpaths near the site.
61.
Despite the express reference in Article 3, there has been no assessment of
the direct or indirect effects on fauna and flora on site or in the area, nor
is one to be carried out under the conditions determined by the MPA. There has
not even been an assessment of what fauna and flora currently exist on the
site, including in and around the pond or ponds on site. It is perhaps
symptomatic of the present lack of information that it is unclear whether there
are one or two ponds on site.
62.
Inevitably there has been no assessment of the interaction between these
matters and the other factors referred to in Article 3.
63.
Of course, the MPA was not being asked to grant or refuse planning
permission for the mineral operations, but only to determine conditions.
Nonetheless, its powers to impose highly restrictive conditions, including ones
limiting the area to be worked, are in my view clear from paragraph 10(2)(d) of
Schedule 13. While that only applies directly to active sites, it cannot have
been Parliament's intention to allow more restrictive conditions in respect of
active sites than in respect of dormant ones upon their re-awakening.
64.
The MPA can, therefore, use conditions to limit severely the method of
working, the areas to be worked, the timing of excavation and the mitigation
measures to be taken. It should, therefore, ensure that it has all the
appropriate information for an environmental assessment. In this case it did
not, and its conditions would allow operations to begin without an adequate
appraisal of all the necessary impacts. Indeed, one of the officers' reports to
committee in effect recognised this, since it stated that the conditions "deal
with
most
of the matters which an EA would have covered" (emphasis added).
65.
I conclude, therefore, that the MPA acted in breach of the Directive in
determining conditions without either an environmental impact assessment or
provision for one in the conditions themselves. It is contended by the
respondents that, in those circumstances, I should nonetheless as a matter of
discretion refuse relief because nothing of significance would have emerged
from such further assessment. This is, in the light of my decision on the
validity of the 1953 permission, an academic issue, but I have to say that I
would have found it impossible to conclude that a proper assessment would not
have led to different or additional conditions. In those circumstances, I
would have exercised my discretion in favour of the applicant.
66.
Some interesting arguments were advanced about the situation which would
have arisen, had I held the 1953 permission to be valid and subsisting but
quashed it for breach of the Directive. In particular, there would then have
arisen the issue of the effect of quashing on the mechanisms set out in
paragraph 9 of Schedule 13, especially the provisions in paragraph 9(9)
whereby, in the absence of a determination by the MPA within three months, the
conditions proposed by the applicant for a determination take effect. That is
not an issue which now falls to be decided and, that being so, I say no more
about it.
67.
I conclude that the 1953 permission is no longer valid and, both for that
reason and because of the breach of the EEC Directive, the determination by the
MPA dated 18th March 1998 was ultra vires and must be quashed. There remains
simply the question of whether leave should be granted to the applicant to
amend the relief sought, so as to seek a declaration that there is no
subsisting planning permission in respect of the site, capable of being made
subject to conditions pursuant to Schedule 13.
68.
Given that I have dealt with the issue of the validity or invalidity of the
1953 permission in this judgment as a necessary part of the decision as to the
vires of the MPA's determination of conditions, there can be no sustainable
objection to its invalidity being formally declared. Since it is not suggested
that there is any other planning permission relating to this site, a
declaration in the terms sought is appropriate.
69.
I therefore grant leave for the amendment to be made and will make the
declaration in the terms sought.