You are here: BAILII >> Databases >> England and Wales High Court (Administrative Court) Decisions >> Colney Heath Parish Council v Secretary of State for Communities & Local Government & Ors [2009] EWHC 787 (Admin) (22 April 2009) URL: http://www.bailii.org/ew/cases/EWHC/Admin/2009/787.html Cite as: [2009] EWHC 787 (Admin) |
[New search] [Printable RTF version] [Help]
Strand, London, WC2A 2LL |
||
B e f o r e :
SITTING AS A DEPUTY JUDGE OF THE HIGH COURT
____________________
Colney Heath Parish Council |
Claimant |
|
-and- The Secretary of State for Communities and Local Government -and- |
First Defendant |
|
St Albans City and District Council -and- Peter Robb |
Second Defendant Third Defendant |
____________________
Alan Masters (instructed by Bramwell Browne Odedra) for the Third Defendant
First and Second Defendant not represented.
Hearing date: 20 March 2009
____________________
Crown Copyright ©
Timothy Corner QC :
INTRODUCTION
"..By allowing the hardcore [already extant on the site] to stay and any building being placed on the site, the natural flow of the floodwater is affected and the houses further down the river will have increased risk of flooding. …"
"… the effect of the development on the openness and function of the Green Belt; the effect on the character of the area; and whether introducing residential accommodation onto the appeal site would result in unacceptable risk to life or place an unacceptable burden on emergency services. The final issue is whether the material considerations advanced in support of the development are sufficient to clearly outweigh the harm by reason of inappropriateness and any other harm."
"…larger, wedge-shaped land holding that runs between Coursers Road and the River Colne."
"The development would thus result in harm to the Green Belt in that it would be inappropriate development, would reduce openness, and would conflict with one of the purposes of including land in the Green Belt. Substantial weight must be given to this harm as it would be contrary to Government advice in PPG2 and to Policy 1 of the Local Plan. It is necessary to consider whether there is any other harm before balancing the identified harm against the other material considerations advanced by the appellant."
"Overall, I consider that due to its layout, scale and siting in relation to the road and footpath, the proposed development would have an urbanising effect on the immediate area and that this would be harmful to the countryside character of the area. This would be contrary to Policy 69 of the Local Plan."
"27. Overall I conclude on this issue that while a large proportion of the site falls within Zone 3a, where PPS 25 advises that development of this type should not be permitted, the level of risk is significantly reduced by the site specific factors set out above. In particular, the maximum depth of a 1:100 (+20%) year flood would only be about 0.5m above ground level and the site occupiers should have at least a 10-hour flood warning in which to vacate the site. As their horses graze the land between the appeal site and the river it seems to me to be highly unlikely that the site occupiers would be taken unawares by rising flood water.
" 28. On the other hand, the level of risk is increased due to the personal circumstances of the appellant's family. Due in part to the health and ages of those who would live on the site I do not consider that the mitigating circumstances are sufficient to completely remove the risk that could arise from potential flooding. I conclude that the development would constitute 'highly vulnerable' development as defined in PPS 25. As there has been no sequential test carried out for this proposal; as the development would be 'highly vulnerable' and in accordance with the advice in paragraph D10 of PPS 25, there is therefore no reason to consider the Exception Test. Overall I conclude that there is clear, if limited, conflict with advice in PPS 25."
"The material considerations advanced by the appellant to be balanced against the identified harm include the need for sites generally; the appellant's personal need for a site and the lack of alternative sites; his health needs and the health needs of his family; the education needs of his grand children; and the failure of policy."
"I consider that the specific needs of the appellant and his family are severe and immediate. From the evidence before me it appears that there is no realistic prospect of the appellant being able to find an alternative site to buy or rent. The lack of a suitable alternative carries weight in favour of the appellant."
"The identified health needs are considerable and carry some weight in favour of the appellant. While there is no evidence to suggest that these needs could only be met from this site, I have no doubt that a settled base would facilitate access to the necessary childcare."
"While the education needs of the children is a factor that weighs in favour of the appellant, I can only give it limited weight as the children do not have any special needs that could only be satisfied at a school close to the appeal site."
"While I am optimistic that the emerging policy guidance will, in time, address this matter, the current position is that there appear to be no sites available locally and no policy advice. This weighs in favour of the appellant."
"There is conflict with the development plan and with advice in PPG 2 and PPS 25."
"..its roadside existence if this appeal fails…"
"I have balanced these material considerations advanced by the appellant against this harm. However, the identified harm is considerable. I have given substantial weight to the harm to the Green Belt. Notwithstanding the mitigating circumstances I do not consider that the clear advice in PPS 25 can be lightly set aside particularly due to the high vulnerability of the appellant's family. For these reasons, I conclude that the material considerations advanced in this case do not clearly outweigh the harm."
"The harm to safety arising from occupation of the appeal site is limited by its location on the very edge of the flood zone."
"Due to the potential flood risk, the number and position of all mobile homes and touring caravans needs to be specified and agreed prior to their siting. The ground level of the site must not be altered. In order to protect residents and others in the event of flood the appellant must subscribe to the EA Floodwatch scheme. For the same reason details of flood proofing, including tethering, of the mobile homes needs to be approved by the Council. In addition, the emergency escape route should include a gateway from the road to the touring caravan and the boundary fencing needs to be approved to ensure that no floating objects can be washed off or onto the site."
"6 The installation details of the caravans/mobile homes shall be approved in writing by the local planning authority before development is commenced. The details shall include the floor levels of the static mobile homes; the means of elevating the floor levels above the 1:1000 year flood level; the means of tethering the mobile homes and the touring caravans; and details of the screens to be provided to prevent storage under the mobile homes.
7 Prior to the first occupation of the site the occupants of the site shall subscribe to the Environment Agency's "Floodwatch" flood warning system. This subscription shall be continuously maintained throughout the residential occupation of this site.
8 Details of the boundary fencing shall be submitted to and approved in writing by the local planning authority. The submitted details shall include details of a pedestrian gate adjacent to the proposed residential touring caravan to ensure its occupants have a dry escape route to Coursers Road in the event of flooding. The approved fencing and gate shall be constructed prior to the first occupation of the site and shall be retained thereafter for the duration of the development.
9 The ground levels of the site shall not be altered without the prior written approval of the local planning authority.
10 No commercial activities shall take place on the land without the prior written permission of the local planning authority."
EVIDENCE ON FLOOD RISK OUTSIDE THE SITE
"8.1 The proposed development would increase the number of people residing within the floodplain and therefore at risk from flooding. The site could not be protected from flood risk without increasing the risk of flooding to other people and property and this would be unacceptable.
8.2 The proposed development will result in a loss of floodplain storage at the site and will also obstruct flood flows and, as a result, will increase the risk of flooding elsewhere. Whilst losses of floodplain storage may be relatively small, the cumulative effect of such losses can be very significant and should be resisted for that reason."
"1. The proposed development will not significantly reduce floodplain storage or obstruct flood flows and therefore will not increase flood risk to others.
2. The proposed development will be safe.
3. The installation of a mesh screen around the perimeter of the static mobile homes between ground level and the underside of the elevated floor will prevent the storage of material beneath the mobile home………
5 The proposed boundary treatment of a robust permeable fence will prevent floating objects within the site being washed off the site.
6. Touring caravans on the site not used for residential accommodation will be securely tethered to prevent them being washed away by floodwaters. However, if they were to be washed away, they would be retained on site by the proposed boundary treatment."
"Condition: The floor level of the static mobile homes shall be approved in writing by the Local Planning Authority before development is commenced.
Reason: To ensure the safety of the mobile homes
Condition: The installation details of the static mobile homes shall be approved in writing by the Local Planning Authority before development is commenced. The details shall include the means of elevating the floor level, the means of tethering the static mobile home and details of the screen to be provided to prevent storage of materials beneath the static mobile home.
Reason: To ensure the proposed development will be safe and will not increase the flood risk to others.
Condition: The occupants of the site will subscribe to the Environment Agency's 'Floodwatch' flood warning system.
Reason: To ensure the safety of the occupants of the site.
Condition: Details of the boundary fence shall be approved in writing by the Local Planning Authority before development is commenced.
Reason: To ensure no floating objects can be washed off the site in times of flood.
Condition: The means of tethering the touring caravans shall be approved in writing by the Local Planning Authority before development is commenced.
Reason: To ensure the touring caravan are prevented from being washed away during times of flood."
"Paragraph 7.3 states that there are no proposals to erect any other permanent structures or to store materials on the site. Even if there was a planning condition to restrict such use on the site, previous experience would suggest that this restriction will not be adhered to and an increased flood risk would result from a reduction in area for floodwater storage and would also have an impact on overland flood flows. Both would lead to an increased risk of flooding on the site and to surrounding property in the vicinity of the site."
THE CHALLENGE
"The Defendant concedes that the Inspector erred in failing to provide an adequately reasoned decision."
"12 My recollection of the Inquiry is that the matters that were in dispute as set out in the Statement of Common Ground were discussed at great length before the Inspector. In particular, I recall that Mr Brawn of the Environment Agency was cross-examined on these very issues for approximately two and a half hours.
13 I further recall that Mr Brawn of the Environment Agency had reluctantly to concede under cross examination that the suggested conditions would adequately mitigate the risk of off-site flooding that might result from the proposed development."
CONCLUSIONS
"I add another warning. The Appellant seeks to rely upon some answers given by Mr Brawn in terms of the degree of risk. We have no problem with that provided the question that was being asked is remembered-at one point e.g. the questions were expressly on the basis of the safety of the mobile home structures themselves. However, that is only one aspect. None of this can deflect from the very obvious risks AND most importantly the clear risk based sequential test in PPS 25 with which these proposals conflict."