[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Administrative Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Administrative Court) Decisions >> Lensbury Ltd & Anor, R (on the application of) v Richmond-Upon-Thames London Borough Council & Ors [2016] EWHC 980 (Admin) (29 April 2016) URL: http://www.bailii.org/ew/cases/EWHC/Admin/2016/980.html Cite as: [2016] EWHC 980 (Admin) |
[New search] [Printable RTF version] [Help]
& (1) CO/5231/2015 |
QUEEN'S BENCH DIVISION
PLANNING COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
THE QUEEN ON THE APPLICATION OF (1) LENSBURY LTD (2) PINENORTH PROPERTIES LTD |
Claimants |
|
- and - |
||
RICHMOND-UPON-THAMES LONDON BOROUGH COUNCIL |
Defendant |
|
- and - |
||
TEDDINGTON & HAM HYDRO CO-OPERATIVE LTD THE ENVIRONMENT AGENCY |
Interested Parties |
____________________
(instructed by Howes Percival LLP) for the First Claimant
Richard Turney (instructed by Dentons UKMEA LLP) for the Second Claimant
Daniel Kolinsky QC (instructed by South London Legal Partnership) for the Defendant
The Interested Parties were not represented
Hearing dates: 13 and 14 April 2016
____________________
Crown Copyright ©
Mr Justice Supperstone :
Introduction
"Demolition of section of weir; installation of 3 reverse engineered archimedean screw turbines to generate hydroelectricity. New Fish and Eel passes, sluice gate, cable routes to substation. Adapt maintenance access to that section of weir; plant room to be constructed on walkway."
Factual Background
"The proposal has been considered in the light of the Development Plan, comments from statutory consultees and third parties. It has been concluded that, subject to conditions to protect environmental (including biodiversity) and local concerns, including wider heritage assets and noise and disturbance, there is not sufficient or significant harm to interests of acknowledged importance caused by the development that justifies withholding planning permission.
The proposal has not been found to cause an increase in flood risk irrespective of whether or not proposed strategic flood risk schemes go ahead.
RECOMMENDATION: PERMISSION."
"… Members considered a range of matters during their deliberations including the location and ecology of the application site. The committee was not minded to approve the application based on the officer's report and recommendation. The appearance of the proposed installation was considered and this was deemed to be an insufficient reason for refusing the application. Concerns about future flooding were also considered and dismissed as a reason for refusal by the committee, particularly as the Environment Agency had stated that the proposed hydroelectric installation would not increase the flood risk in the area.
The committee considered whether there was enough information being provided about the proposed noise mitigation scheme. It was noted that this application affected a sensitive area where there was already a relatively noisy industrial installation (weir). This, in the committee's opinion, made judging whether the proposed turbines would add to the noise in the area, when measured at various distances and positions, more difficult. It was ultimately decided that there was not enough information to approve or reject the application on noise grounds at this stage.
RESOLVED that further consideration of this item be deferred to a future meeting of the committee for the following reason:
'The committee did not feel that enough information was presented in the proposed noise mitigation scheme, as alluded to in proposed condition NSO2'."
"The original report is set out in appendix 'A'.
The application was considered by the planning committee at its meeting on the 15th April where it was RESOLVED that consideration of this item be deferred to a future meeting of the committee for the following reason:
'The committee did not feel that enough information was presented in the proposed noise mitigation scheme, as alluded to in the proposed condition NSO2.'
Further information has been submitted for consideration. This is considered to reinforce the original recommendation.
There has been no other material change in circumstances or substantive new issue raised since the meeting of 15th April.
RECOMMENDATION: PERMISSION."
"…The committee discussed the acceptability of the application in terms of noise, as other matters had been decided upon during the meeting held on 15 April 2015, with there being no new planning issues of any significance having subsequently arisen. It was generally considered that noise could not be used as a reason for refusal as it could not be sustained on appeal of the committee's decision. The committee felt that the proposed conditions safeguarded residents and other nearby establishments, although a concern was raised over how feasible it would be for the applicant to comply with them. It was also felt by many of the members who attended the site visits to Teddington and Romney that, in practice, the level of additional noise caused by such turbines was negligible and not audible a short distance away from the installation.
RESOLVED that the application be approved, subject to the conditions and informatives in the officer's report."
Grounds of Challenge
i) The Council failed to comply with the duty under s.38(6) of the Planning and Compulsory Purchase Act 2004 ("the 2004 Act") (Ground 1).ii) The Council failed properly to consider the impacts of the proposed development on heritage assets (Ground 2).
iii) The Council failed to screen the planning application under the Town and Country Planning (Environmental Impact Assessment) Regulations 2011 ("the 2011 Regulations") (Ground 3).
i) The grant of planning permission was unlawful in that it was granted in breach of the requirements of the 2011 Regulations. The Council failed to screen the application to decide whether or not the proposal was for EIA development.This is the same ground as Mr Lockhart-Mummery's third ground.
ii) The determination of the application was procedurally unfair and the Council failed to have regard to material considerations because it limited its consideration to matters relating to noise (Ground 4).
iii) Condition NSO1 imposed on the grant of planning permission in relation to noise is unlawful and members were misled as to its effect (Ground 5).
In addition Mr Turney associated himself with the submissions made by Mr Lockhart-Mummery on Grounds 1 and 2.
Ground 1: failure to comply with s.38(6) of the Planning and Compulsory Purchase Act 2004
The Legal Framework
The 2004 Act, s.38(6)
"If regard is to be had to the development plan for the purpose of any determination to be made under the planning Acts the determination must be made in accordance with the plan unless material considerations indicate otherwise."
"In the practical application of section 18A it will obviously be necessary for the decision maker to consider the development plan, identify any provisions in it which are relevant to the question before him and make a proper interpretation of them. His decision will be open to challenge if he fails to have regard to a policy in the development plan which is relevant to the application or fails properly to interpret it. He will also have to consider whether the development proposed in the application before him does or does not accord with the development plan. There may be some points in the plan which support the proposal but there may be some considerations pointing in the opposite direction. He will require to assess all of these and then decide whether in light of the whole plan the proposal does or does not accord with it…
… in my view it is undesirable to devise any universal prescription for the method to be adopted by the decision maker, provided always of course that he does not act outwith his powers. Different cases will invite different methods in the detail of the approach to be taken and it should be left to the good sense of the decision maker, acting within his powers, to decide how to go about the task before him in the particular circumstances of each case. … The precise procedure followed by any decision maker is so much a matter of personal preference or inclination in light of the nature and detail of the particular case that neither universal prescription nor even general guidance are useful or appropriate."
"Where it is concluded that the proposal is not in accordance with the development plan, it is necessary to understand the nature and extent of the departure from the plan which the grant of consent would involve in order to consider on a proper basis whether such a departure is justified by other material considerations."
(See also R (Hampton Bishop Parish Council) v Herefordshire Council [2015] 1 WLR 2367 at para 33, per Richards LJ).
"It is axiomatic that the decision maker does not have to deal with each and every policy that has been raised by the parties during an appeal. That is not the Claimant's case. Rather, it is submitted a finding of compliance or conflict with the development plan and the basis for it needs to be made so that the decision maker can proceed to undertake the planning balance in an informed way. I agree. Such a step is not just form. Rather, it is an essential part of the decision-making process, so that not only the decision maker but also the reader of the Decision Letter is aware and can understand that the duty imposed under section 38(6) has been discharged properly by the decision maker."
"That does not mean a mechanistic approach of judging the proposals against each and every policy that may be prayed in aid of a development or against it, but an evaluation of main policy areas within the development plan that are relevant to the proposal to be determined and an assessment of how the proposal [fares] against them. That can be shortly stated and the process to be followed is for the individual decision maker. But it needs to be clear at the culmination of the decision-taking process what the eventual judgment is against the development plan as a whole. Only by carrying out that exercise can the next step of evaluating the planning balance be properly undertaken."
Development Plan Policies
The London Plan
"B Buildings, streets and open spaces should provide a high-quality design response that:
…
(b) contributes to a positive relationship between the urban structure and natural landscape features, including the underlying land form and topography of an area."
"C Development should identify, value, conserve, restore, re-use and incorporate heritage assets, where appropriate.
D Development affecting heritage assets and their settings should conserve their significance, by being sympathetic to their form, scale, materials and architectural detail."
"B The strongest protection should be given to London's Metropolitan Open Land and inappropriate development refused, except in very special circumstances, giving the same level of protection as in the Green Belt. Essential ancillary facilities for appropriate uses will only be acceptable where they maintain the openness of MOL."
The Defendant's Core Strategy
The Council's Development Management Plan 2011
"New development (or re-development) or other proposals should conserve and enhance the character and appearance of the area."
"It is particularly important that any scheme not only preserves but positively enhances the Conservation Area."
"The borough's Metropolitan Open Land will be protected and retained in predominantly open use. Appropriate uses include public and private open spaces and playing fields, open recreation and sport, biodiversity including rivers and bodies of water and open community uses including allotments and cemeteries.
It will be recognised that there may be exceptional cases where appropriate development such as small-scale structures is acceptable, but only if it:
1. Does not harm the character and openness of the metropolitan open land; and
2. Is linked to the functional use of the Metropolitan Open Land or supports outdoor open space uses; or
3. Is for essential utility infrastructure and facilities, for which it needs to be demonstrated that no alternative locations are available and that they do not have any adverse impacts on the character and openness of the metropolitan open land.
Improvement and enhancement of the openness and character of the Metropolitan Open Land and measures to reduce visual impacts will be encouraged where appropriate."
The First Report for the meeting on 15 April 2015
"42. The River Thames is designated Metropolitan Open Land (MOL) and as such Core Strategy policy CP 10, DMP policy DM OS 2 apply. In addition, the site is within the Teddington Lock Conservation Area, designated as Other Site of Nature Importance and falls within the Thames Policy Area as well as high risk flood zone (flood zone 3).
43. Teddington Weir is a prominent structure within the River Thames and the existing landscape, recognised within the Thames Landscape Strategy along with the lock and footbridge as the main focus of activity and interest in this reach. The section of the weir to be used for the hydro power scheme was constructed in 1991-92. The proposal is to construct a hydropower installation (three Archimedean screw turbines) within the existing Teddington weir to generate electricity. This requires the demolition of this section of the weir (consisting of two fixed crest weirs, two radial gates and two fish passes).
44. From a MOL perspective, this proposal is considered to be a replacement structure, whereby one engineering solution is replaced by another one. The overall scale of the structure is comparable with the adjoining large roller sluice gates. The screws will be mainly below the top of the river wall, whilst the shafts will extend up to a higher level (above the projected maximum flood level), where the generator platform and walkway will be situated.
45. In line with MOL policies, there is a presumption against inappropriate development, and building development is generally unacceptable. MOL policies however recognise that there may be exceptional cases where appropriate development, such as 'small scale structures', is acceptable. Whilst not in itself a small structure, this proposal is for a replacement structure of an existing engineering component within the wider context of the weir, it does not involve a change of use as such and is functionally linked to the river, it is considered that this proposal is in line with MOL policies.
46. The proposals clearly have a visual impact on a sensitive section of the riverside, with views from and to listed structures, particularly the footbridge.
47. The overall scale is within that of the lock structures generally and the arches incorporated into the design and general indication of materials relate it visually to the existing main structure. As such it is not considered that the visual impact is generally negative. In the key view from the footbridge the turbines would add an element of visual interest and its overall design again is seen to be in character with the operational infrastructure which itself forms a key characteristic of the riverside conservation area. As a consequence it is not considered to compromise heritage assets, registered or otherwise, within their immediate or wider context, as has been suggested or the objectives set out in the Thames Landscape Strategy.
48. The need for an acceptable exposition of balancing benefits in order to balance such highly adverse impact would only arise if the premise that there was such a highly adverse impact was accepted. The proposal is seen as acceptable in its own right and not dependent on a required level of 'green' measures or alternative benefits."
Discussion
i) The relevant provisions of the London Plan, the Core Strategy and the Development Management Plan were identified (although I think, he accepted, there was no express reference to CP11 in the Core Strategy).ii) The site was identified as within the Teddington Lock Conservation Area, and it was noted that "the local character of the area is clearly formed by the river and its extensive riverside infrastructure, including the weir and lock".
iii) Visual representations of the proposed development (comparing before and after) from Ham Bank and Teddington Bridge were produced.
iv) Consultation responses received in respect of the application were set out in some detail. On the one hand, the general consensus from representations in support was that "this is a highly sustainable form of development which will benefit the local community without causing harm to the local character or local amenity"; on the other, representations opposed raised concerns "in particular to the visual impact of the proposal and impacts and on noise pollution". It was noted that the nature and form of the proposal would have a significant adverse impact on heritage assets including the conservation area, the two listed foot bridges and the club itself as a non-designated heritage asset.
- "The applicant has failed to assess properly the significance and heritage values of the conservation area and the designated and non-designated heritage assets within it.
- The development proposal has not been informed by an understanding of the significance of heritage assets: their evidential, historical, aesthetic and communal value.
- The proposal causes 'less than substantial harm' to the character and settings of heritage assets, both designated and non-designated.
- The proposal causes 'less than substantial harm' by the demolition of part of the existing weir structure, which has not been properly assessed as to its contribution to the appearance and character of the Conservation Area.
- The new hydro structure does not make a positive contribution to the character and local distinctiveness; there is no demonstration that the proposal preserves or enhances the Conservation Area or the setting of the designated and undesignated heritage assets.
- The proposal will have a detrimental impact on the enjoyment, use and interpretation of the significance of the Lensbury and its grounds.
- The proposal involves the demolition of non-designated heritage assets within the conservation area that is part of the existing sluice but also obscures from key views the existing distinctive arched structure to the roller sluices. The views from the grounds and setting of the Lensbury Club, itself a non-designated heritage asset, are detrimentally affected by the new structure.
…
- … The new structure prevents the appreciation of the nature of the heritage assets, which include views across the Thames to the leafy expanse on the opposite bank, which is expressive of the spatial qualities and topographical character of the river.
…
- There is no acceptable exposition of balancing benefits that have been provided by the applicants in order to balance such highly adverse impact."
Ground 2: failure lawfully to consider the impacts of the proposed development on heritage assets
The Statutory and Policy Framework
"(1) In considering whether to grant planning permission for development which affects a listed building or its setting, the local planning authority or, as the case may be, the Secretary of State shall have special regard to the desirability of preserving the building or its setting or any features of special architectural or historic interest which it possesses."
"(1) In the exercise, with respect to any buildings or other land in a conservation area, of any of the provisions mentioned in sub-section (2), special attention shall be paid to the desirability of preserving or enhancing the character or appearance of that area.
(2) The provisions referred to in sub-section (1) are the planning Acts …"
"128. In determining applications, local planning authorities should require an applicant to describe the significance of any heritage assets affected, including any contribution made by their setting. The level of detail should be proportionate to the assets' importance and no more than is sufficient to understand the potential impact of the proposal on their significance…
129. Local planning authorities should identify and assess the particular significance of any heritage asset that may be affected by a proposal (including by development affecting the setting of a heritage asset) taking account of the available evidence and any necessary expertise…
…
131. In determining planning applications, local planning authorities should take account of:
- the desirability of sustaining and enhancing the significance of heritage assets and putting them to viable uses consistent with their conservation; …
132. When considering the impact of a proposed development on the significance of a designated heritage asset, great weight should be given to the asset's conservation. The more important the asset, the greater the weight should be. …
133. Where a proposed development will lead to substantial harm to or total loss of significance of a designated heritage asset, local planning authorities should refuse consent, unless it can be demonstrated that the substantial harm or loss is necessary to achieve substantial public benefits that outweigh that harm or loss, or all of the following apply: …
134. Where a development proposal will lead to less than substantial harm to the significance of a designated heritage asset, this harm should be weighed against the public benefits of the proposal, including securing its optimum viable use.
135. The effect of an application on the significance of a non-designated heritage asset should be taken into account in determining the application. In weighing applications that affect directly or indirectly non-designated heritage assets, a balanced judgment will be required having regard to the scale of any harm or loss and the significance of the heritage asset."
"… Paragraph 134 of the NPPF appears as part of a fasciculus of paragraphs … which lay down an approach which corresponds with the duty in section 66(1). Generally a decision maker who works through those paragraphs in accordance with their terms will have complied with the section 66(1) duty. When an expert planning inspector refers to a paragraph within that grouping of provisions… then – absent some positive contra-indication in other parts of the text of his reasons – the appropriate inference is that he has taken properly into account all those provisions, not that he has forgotten about all the other paragraphs apart from the specific one he has mentioned."
The First Report
Discussion
Ground 3: failure to undertake lawful EIA screening
The Legal Framework
"7. Applications which appear to require screening opinion
Where it appears to the relevant planning authority that—
(a) an application which is before them for determination is a… Schedule 2 application; and
(b) the development in question has not been the subject of a screening opinion or screening direction; and
(c) the application is not accompanied by a statement referred to by the applicant as an environmental statement for the purposes of these Regulations,
paragraphs (4) and (5) of Regulation 5 shall apply as if the receipt or lodging of the application were a request made under regulation 5(1)."
"A person who is minded to carry out development may request the relevant planning authority to adopt a screening opinion."
"The installation is designed to produce more than 0.5 megawatts."
Discussion
i) The noise assessment of Peter Brett Associates LLP ("PBA") submitted with the planning application which states under the heading "Proposed Scheme":"It is understood that the anticipated overall power generation is approximately 168kw of power output per turbine, with a total of 500kw estimated from the overall installation" (paragraph 1.3.3).ii) The Applicant's Statement of Consultation dated 1 September 2014, which in the list of consultees at Appendix 1 refers to "LV Transformer Provider/Installer" as the stakeholder with the following interest:
"Required to have a 1.2 MVA transformer to feed onto HV network (the grid)."iii) A letter dated 14 April 2015 from Howes Percival, Lensbury's solicitors, enclosing a technical opinion from Mr Paul Johannsen of Thames Renewables, dated 13 April 2015. Mr Johannsen's conclusion is that:
"The proposed development should have been based on the Total Installed Capacity (TIC) of the proposed hydroelectric development which would have concluded the proposed development has an output of greater than 558kw and up to 630kw. This would also attract the lower tariff rate and confirm that an EIA is required."iv) An email dated 19 February 2015 from Mr Derek Tanner (the Council's planning officer who was the principal author of the reports to Committee in April and September 2015) to Mr Steve Jarvis of the Applicant, which asked him whether he was "able to confirm whether or not the energy output of the current proposal is designed to exceed 0.5MW". The email reply from Mr Jarvis, the following day, was: "No. It's 492kw". (See Addendum Report to Committee of April 2015).
v) The manufacturer's quotation for the proposed plant supplied by the Applicant to the Council.
"6. The letter dated 13.04.15 from Thames Renewables submitted to the Council shortly before the April 2015 committee meeting is in conflict with the information submitted by the planning applicants. This letter consists of two pages with the first page and part of the second dealing with background information regarding tariffs and various general technical points. In the second paragraph on the second page, under the heading '4. Assessment of the Proposed Development', it is stated that the Declared Net Capacity of the installation appears to be marginally less than 500 megawatts. Earlier in the letter this is explained as being the net output of an installation taking account of energy produced less auxiliary and parasitic losses of the energy installation. This seems to me to accord with the definition in Schedule 2 of the Environmental Impact Assessment Regulations 2011, which refers to an installation designed to produce (emphasis added) more than 0.5 megawatts, i.e. it is its output that is relevant.
7. Even if the point in the above paragraph is incorrect there is nothing in the letter from Thames Renewables that led me not to agree with the applicant's understanding of the output of the installation as underlined by the manufacturers quotation… In particular paragraph 7 on the second page, immediately above the Conclusion, refers to reliance on 'historic data sets' but gives no indication what these are. It also does not accord with the plain wording of the manufacturer's specification."
Ground 4: the process was procedurally unfair
"The Committee discussed the acceptability of the application in terms of noise, as other matters had been decided upon during the meeting held on 15 April 2015, with there being no new planning issues of any significance having subsequently arisen."
Ground 5: condition NSO1 relating to noise
"The sound energy level from the operation of the hydro power scheme when assessed at representative residential and commercial noise sensitive premises and/or locations or when measured elsewhere and calculated to the said locations, shall not exceed the limit levels detailed in the table below. The hydro power scheme may not be operated unless these provisions are met."
"Having considered the information provided in … both the initial and subsequent acoustic reports the Commercial EH Department considered the noise emissions from the operation of the hydro power scheme can be mitigated and minimised so as not to cause adverse impact on the health and/or quality of life of occupiers of residential and/or commercial premises in the vicinity of the proposed hydro power scheme and therefore will comply in principle with National Planning Policy and Guideline requirements and as such the scheme is acceptable subject to compliance with the noise control conditions detailed below."
There then follows the officers' advice:
"Officers advice having considered the additional information and response nevertheless remains that the imposition of the conditions as proposed, contrary to what opponents are suggesting, should give sufficient certainty to members to agree the recommendation. They are considered to be both restrictive and enforceable."
"The committee felt that the proposed condition safeguarded residents and other nearby establishments, although a concern was raised over how feasible it would be for the applicant to comply with them."
"14. … MPS represents the boundary of the Teddington Studios Site with the Lensbury Site. The site plan and perspective … are taken from Teddington Studios application submission 14/0914/FUL. It is considered that MPS position is representative of the closest properties within the Teddington Studio site to the Hydro Scheme.
…
17. Condition NSO1 details representative locations but does not exclude other locations from being assessed. The same relative external and absolute internal criteria limits would apply.
18. With regard to the external noise limiting level this will be dependent on the background noise level which is dominated by the hydrodynamic noise from the weir at location MP6 and will attenuate with distance as well as being screened by building blocks. Therefore background noise on the opposite side of the Teddington Studio site will be lower and require a lower rating level as this is relative to the background level. A report by Hoare Lea on behalf of the Claimant has indicated that the location of their background noise survey was shielded from weir noise, hence the lower background noise levels. We have not been given a copy of the Hoare Lea acoustic assessment so do not know the exact location of the measurement position. However, the shielding effect from the existing Lensbury buildings will also shield noise from the hydro scheme. Using the Hoare Lea background measurement of 41dB(A) and the Defendant's proposed condition of -5, analysis of the noise model indicates that the external level will be compliant with the Defendant's external and internal requirements.
19. Moreover the rating level (LArTr) contains a 7dB character correction therefore the required level is in absolute terms -12dB below the existing background level. Hoare Lea have recommend[ed] a further 5dB which would make 17dB below the underlying background level, this is considered to be an unreasonably high requirement and in excess of NPPF/NPPG requirements."
Conclusion