[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Administrative Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Administrative Court) Decisions >> British Gas Trading Ltd, R (on the application of) v The Gas and Electricity Markets Authority & Ors [2019] EWHC 3048 (Admin) (13 November 2019) URL: http://www.bailii.org/ew/cases/EWHC/Admin/2019/3048.html Cite as: [2019] EWHC 3048 (Admin) |
[New search] [Printable PDF version] [Help]
QUEEN'S BENCH DIVISION
ADMINISTRATIVE COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
THE QUEEN (ON BEHALF OF BRITISH GAS TRADING LIMITED) |
Claimant |
|
- and - |
||
THE GAS AND ELECTRICITY MARKETS AUTHORITY -and- (1) NPOWER LIMITED (2) SSE ENERGY SUPPLY LIMITED (3) EDF ENERGY CUSTOMERS LIMITED (4) EON UK PLC (5) SCOTTISH POWER ENERGY RETAIL LIMITED (6) ENERGY UK (7) CITIZENS ADVICE |
Defendant Interested Parties |
____________________
Alan Maclean QC, Jessica Boyd and Tom Coates (instructed by Ofgem) for the Defendant
Hearing dates: 3 and 4 October 2019
____________________
Crown Copyright ©
Mrs Justice Andrews:
INTRODUCTION
THE RELEVANT STATUTORY FRAMEWORK
(1) As soon as practicable after this Act is passed, [GEMA] must modify the standard supply licence conditions so that they include conditions ("tariff cap conditions") that impose a cap on all standard variable and default rates that may be charged by the holders of supply licences for the supply of gas or electricity under domestic supply contracts…(2) [GEMA]
(a) may modify the tariff cap conditions from time to time, but
(b) must secure that such conditions continue to be included in the standard supply licence conditions until they cease to have effect by virtue of section 8.(6) [GEMA] must exercise its functions under this section with a view to protecting existing and future domestic customers who pay standard variable and default rates, and in so doing it must have regard to the following matters–(a) the need to create incentives for holders of supply licences to improve their efficiency;(b) the need to set the cap at a level that enables holders of supply licences to compete effectively for domestic supply contracts;(c) the need to maintain incentives for the domestic consumers to switch to different domestic supply contracts;(d) the need to ensure that holders of supply licences who operate efficiently are able to finance activities authorised by the licence.
"before making the first modifications under section 1 [GEMA] must… consult such persons as it considers appropriate on the methodology to be used for the purposes of the cap." [Emphasis added].
Section 2(4) provides that consultation undertaken before the Act was passed is as effective for the purposes of subsection (3) as consultation undertaken afterwards. Both parties accepted that an obligation to consult on the methodology is not confined to consulting on the broad structure to be adopted, i.e. "bottom up" versus alternative approaches. The consultees should be consulted about the key ingredients of, and material assumptions adopted in, the chosen approach.
FACTUAL BACKGROUND
"to ensure the wholesale allowance better reflects the underlying costs that suppliers are likely to have incurred when purchasing energy for delivery during the first cap period. Large suppliers have most likely already bought much of the energy SVT customers will use in early 2019. Now that the wholesale market has increased since April 2018, our initial approach risked customers paying significantly more than suppliers' underlying costs. Had market prices reduced, our proposal would have risked setting the wholesale allowance below suppliers' actual costs, and would have needed correcting".
By necessary implication from the final sentence, GEMA acknowledged that if it did adopt an approach which resulted in the wholesale allowance being set too low to enable the hypothetical "typical" efficient supplier to cover its costs, it would need to make an adjustment to rectify that situation.
"we are minded to consider this from the perspective of setting the level of the cap at a level such that a supplier with efficient costs, noting the inherent uncertainty in assessing the efficient cost benchmark, could finance its activities. Our principal measure is the ability of an efficient supplier to make a long run normal rate of return under a default tariff environment."This was echoed in paragraph 4.15 of Appendix 4 to the September consultation, where GEMA stated that its primary function was to set an allowance that gives "a realistic allowance to cover the costs that suppliers might incur delivering energy." Whilst it had indicated in paragraph 4.13 that it was proposing to adjust its approach from the proposal in May "to improve outcomes for customers and ensure the wholesale allowance reflects underlying costs more closely," the adjustment was not intended to create a situation in which the allowance would be insufficient to cover the likely costs of an efficient supplier. Of course, that did not mean that everyone's actual costs would be covered.
"suppliers are unlikely to sell all of their contracts, and then buy them back again at newly available prices. Even if they did so, this would incur costs (reducing potential profits) or realise potential losses. If market prices had increased since that supplier purchased the contract initially, they would make a gain (adjusting for transaction costs). As such, the default tariff cap would provide a higher allowance than their actual cost required. If the market had fallen since the supplier had first bought contracts, they would incur a loss. Our default tariff cap would set a lower allowance than the supplier's actual cost required. In the latter case, we may have needed to consider a temporary adjustment to allow suppliers to recover their actual cost."
(i) suppliers were unlikely to have adjusted their hedging strategy to align with the indicative April-September window, and
(ii) even if they did, their costs would be sufficiently covered in a rising market.
Although it was not expressly articulated, the thinking behind reason (ii) was that when aligning, suppliers would have cashed in their pre-purchased forward contracts, and that this would have yielded sufficient profit to outweigh the difference between (a) the cost to them of forward contracts purchased in May-September and (b) the lower allowance provided by the observation window proposed in September (February-July).
"An approach that uses more prices from earlier in 2018 is more likely to better reflect that actual cost, and better protect customers".
THE DECISION
"given their stated rationale for their approach to purchasing energy as provided to us in 2017, it is unlikely that the 6 largest suppliers would have deviated materially from that approach in the succeeding months (before our May consultation)". [Emphasis added].
In other words, it assumed that the Big Six would have largely continued with a long-term purchasing strategy (of 18 months or more) until May 2018. It went on to say that, given market conditions, suppliers may have adjusted their strategy in small ways, but not in a way that changed the overall rationale, and that no development in the market since 2017 suggested a substantial change in approach before May 2018. That ignored the proposed introduction of a default tariff price cap, which GEMA itself acknowledged was not a consideration informing any supplier's hedging strategy at the time that the data that it relied on was gathered. It is now known that this development did have a significant impact on the general nature of suppliers' hedging strategies after October 2017.
a) what it called the 'typical' approach, an 18-month observation period between April 2017 and September 2018;
b) the May consultation proposal: a 6-month observation period between April 2018 and September 2018;
c) the statutory consultation proposal, a 6-month observation period between February and July 2018 with a two-month lag before the contract start date; and finally
d) what it described as a 'medley' approach: the contracts that a supplier would have purchased if it adjusted its strategy as GEMA published its proposals in the May consultation and September consultation.
WAS THE CONTINUITY ASSUMPTION MATERIAL TO THE DECISION?
WAS THE CONTINUITY ASSUMPTION COMMUNICATED TO CONSULTEES?
THE CLAIM FOR JUDICIAL REVIEW
"Consultees must be told enough – and in sufficiently clear terms – to enable them to make an intelligent response.".
CONCLUSION