[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Administrative Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Administrative Court) Decisions >> Rydon Group Holdings Ltd, R (On the Application Of) v Arta Residents' Management Company Ltd & Ors [2024] EWHC 3234 (Admin) (10 December 2024) URL: http://www.bailii.org/ew/cases/EWHC/Admin/2024/3234.html Cite as: [2024] EWHC 3234 (Admin) |
[New search] [Printable PDF version] [Help]
KING'S BENCH DIVISION
ADMINISTRATIVE COURT
Strand London WC2A 2LL |
||
B e f o r e :
____________________
THE KING (on the application of RYDON GROUP HOLDINGS LIMITED) |
Claimant |
|
- and - |
||
SECRETARY STATE FOR LEVELLING UP, HOUSING AND COMMUNITIES |
Defendant |
|
- and - |
||
(1) ARTA RESIDENTS' MANAGEMENT COMPANY LIMITED (2) IKON MANAGEMENT COMPANY LIMITED (3) STYLUS MANAGEMENT COMPANY LIMITED (4) KDG PROPERTY LIMITED |
Interested Parties |
____________________
Lower Ground, 46 Chancery Lane, London WC2A 1JE
Web: www.epiqglobal.com/en-gb/ Email: [email protected]
(Official Shorthand Writers to the Court)
MR J HOLBORN and MR A BURRELL (instructed by Government Legal Department) appeared on behalf of the Defendant.
THE INTERESTED PARTIES were not present and were not represented
____________________
Crown Copyright ©
(1) The designation of Rydon as a designated participant developer ("the Designation Decision);
(2) the direction under clause 7.7(B) of the terms that Rydon should not carry out remediation works in respect of the three Buildings and that those Buildings should be designated as Stage D Fund Buildings ("the Clause 7.7(B) Decision");
(3) the direction that the Buildings should not be transferred to Rydon and should proceed to remediation through the Building Safety Fund ("the BSF"), with Rydon reimbursing the Fund in accordance with clause 13.8 of the terms ("the Fund decision").
Amenability to judicial review
"A scheme may be established for any purpose connected with-–
(a) securing the safety of people in or about buildings in relation to risks arising from buildings; or
(b) improving the standards of buildings".
"secure the safety of people in or about buildings and improve the standard of buildings by securing that persons in the building industry remedy defects in buildings relating to fire safety and contribute to costs associated with remedying such defect in relation to buildings".
"Whether or not a contract exists between the aggrieved person and the body, in some situations the body may be performing regulatory or other functions which create a situation where the person is left with the stark choice of either submitting themselves to the control of the body or not participating in the activity concerned. Here, it is submitted, judicial review ought in principle to be available to an aggrieved person, though if a contract exists a contractual claim will normally be an appropriate alternative remedy which may bar judicial review".
The grounds of challenge
Ground 1 - the designation decision
"The Contract permits the Secretary of State to 'designate' a Participant Developer where it, another company within its group, or a senior officer or director of the Participant Developer or of any member of its group has, inter alia:
"been the subject of significant criticism in the findings of a public inquiry, or is currently a person whose conduct is under consideration by a public inquiry, regarding their performance or behaviour in connection with building safety matters such that the Participant Developer is reasonably considered by DLUHC to be unfit to carry out or procure the carrying out of Works in accordance with these Self-Remediation Terms and/or the Contract" (Annex 1 of the SRTs ….."
Where a Participant Developer is deemed to be a Designated Participant Developer pursuant to this definition, DLUHC may:
"Notwithstanding any other provisions of these Self-Remediation Terms and/or the Contract … either in relation to all relevant Buildings Requiring Work or such Buildings Requiring Work as it may determine, elect in its sole discretion (but acting reasonably) to:
(1) require the Participant Developer to fund the Responsible Entity (via a funding agreement or otherwise) to undertake or procure the Works in accordance with Clause 6.1(iii), and not to undertake or procure the Works at its own cost in accordance with Clauses 6.1(i) and/or 6.1(ii)
… or
(2) require the Participant Developer not to undertake or procure the Works at its own cost in accordance with Clauses 6.1(i) and/or 6.1(ii), and to designate the Participant Developer's Buildings as Stage D Fund Buildings, such that the Participant Developer will reimburse the relevant Fund in accordance with Clause 13" (clause 7.7 of the SRTs….)."
27. The Defendant set out his reasons in support of the Designation Decision as follows:
"The conduct of Rydon Maintenance Ltd ("Rydon Maintenance") in connection with its role as the lead contractor for the refurbishment of Grenfell Tower is currently under consideration by the Grenfell Tower Inquiry ("the Inquiry"). The Inquiry has heard concerning evidence that notwithstanding its responsibilities as lead contractor for the refurbishment, Rydon Maintenance failed to undertake proper due diligence before appointing subcontractors; that it lacked the expertise necessary to identify non-compliance of designs and buildings materials with statutory requirements and industry guidance; that it relied entirely on others to check these matters; that it did not have in place proper systems to establish whether subcontractors knew or had considered whether subcontractors knew or had considered whether designs and buildings materials complied with the relevant standards; and that it did not adequately supervise the quality of subcontractors' work (including where concerns had been raised).
Rydon Maintenance is a subsidiary of and controlled by Rydon. In view of the troubling evidence heard by the Inquiry, Rydon is not currently considered to be fit to carry out or procure remediation works in respect of the three buildings referred in your 15 September 2023 letter…..DLHUC is prepared to consider further the designation of Rydon ….once the Inquiry's Phase 2 report is publicly available."
28. The Defendant then went on to consider the other 11 buildings for which Rydon was responsible, acknowledging Rydon's information that it had completed works in respect of 5 developments, was currently carrying out works in a further four which were due to be completed by 28 March. The Defendant concluded that he would not issue any directions under clause 7.7. of the Terms in respect of these four buildings and instead audit the qualifying assessments to be provided by Rydon on completion. The Defendant had not yet made a decision in respect of the other three buildings in Rydon's data return.
Ground 1A
Ground 1B
Ground 1C
Ground 1D
Ground 1E
Ground 1F
Ground 2 - the 7.7(B) decision
"….Each of these buildings suffers from life-critical fire safety defects. By default, they are classified by the SRTs as Stage C Fund Buildings, because at the time Rydon entered into the Contract as the Participant Developer for its group (15 September 2023), awards of full funding had been communicated to the Responsible Entities but the Grant Funding Agreements ("GFAs") had not yet been signed by all parties, DLUHC not yet having provided its countersignature.
Had the GFAs been countersigned by DLUHC by 15 September 2023, the buildings would have been automatically classified as Stage D Fund Buildings and the planned works programmes would have commenced on or around 30 October 2023.
Stage C and D Fund Buildings are to be contrasted with Stage A and B Fund Buildings (where no award of full funding has been communicated as at the date of the Contract). Whereas the default position is that Stage A and B Fund Buildings will be transferred to the relevant Participant Developer (see generally clause 12 of the SRTs), a Stage C Fund Building may only be transferred to a Participant Developer where it requests this in writing and "DLUHC, acting reasonably, accepts such request" (clause 13.2). Stage D Fund Buildings may not be transferred to Participant Developers to carry out remediation works themselves (see clause 13.8).
…..
Second, having determined that Rydon is a Designated Participant Developer DLUHC has decided to exercise its powers under clause 7.7 of the SRTs to direct Rydon not to carry out or procure remediation works itself in respect of the three buildings referred to in your 15 September 2023 letter. The three buildings will instead be retained within the BSF as Stage D Fund Buildings in accordance with clause 7.7(B), such that Rydon will reimburse the BSF in accordance with clause 13.8
In reaching this decision, DLUHC has carefully considered whether to require Rydon to fund directly the Responsible Entities to enable them to arrange the necessary remediation works (i.e. in accordance with clause 7.7(A) of the SRTs), instead of the Responsible Entities receiving the funding approved by the BSF. In this regard, DLUHC acknowledges evidence you have provided to the effect that the scope and cost of works may be reduced if the buildings are not retained within the BSF. However, DLUHC considers that there is a material risk that this course of action could lead to delays in the commencement of the works and has therefore decided to exercise its right under clause 7.7(B) to designate the three buildings as Stage D Fund Buildings instead. As noted above, the GFAs between the BSF and the Responsible Entities for the three buildings have already been prepared and the planned works programmes can therefore commence with minimum further delay.
Finally, DLUHC has separately considered whether, in the absence of Rydon's designation as a Designated Participant Developer, it would accede to Rydon's request for the three buildings to be transferred out of the BSF under clause 13.2 of the SRTs. In doing so, DLUHC has carefully considered the evidence provided by Rydon in support of the transfer request but has determined that the request should not be granted in any event. In particular, DLUHC notes that as at the date Rydon entered the Contract (15 September 2023), awards of full funding had been communicated to the Responsible Entities for the three buildings, and the GFAs had been drawn up and signed by all relevant parties save for DLUHC. Had DLUHC applied its countersignature by 15 September 2023, the buildings would have been automatically classified as Stage D Fund Buildings and the works programmes contemplated by the GFAs would have commenced as planned on or around 30 October 2023. In those circumstances, DLUHC considers that it is appropriate to regard the three buildings as being unsuitable for transfer, as would automatically be the case had they reached Stage D by the time Rydon entered the Contract."
Ground 2A
Ground 2B
Ground 2C
i. there was a material risk that transferring the buildings could lead to delays in their remediation and/or give Rydon an opportunity to respond to that evidence;
ii. the responsible entities were in a position to commence work on the Buildings and/or to give Rydon an opportunity to respond to that evidence. In doing so, the defendant manifestly adopted an unfair procedure.
Ground 2D
i. purported material risk of delay to the remediation works, when Rydon had indicated that it would have been in a position to start the works within 28 days of the Buildings being transferred out of the Fund and that any delay was attributable to DLUHC taking in excess of five months to determine Rydon's application. Had the defendant determined the application within a reasonable period of time, Rydon could have commenced the remediation works before 28 February 2024. Furthermore, by failing to engage constructively in good faith negotiations, as required by clause 17 of the Terms, the defendant substantially contributed to the delay to the remediation works that Rydon would have carried out by now.
ii. the Fourth IP being able to start the remediation work to the buildings when there was no evidence to that effect.
Ground 2E
Ground 2F
Ground 3 - the Fund decision
Ground 3A
i. he gave as a reason that, had DLUHC countersigned the GFAs by 15 September, works programmes contemplated by the GFAs would have commenced on or about 30 October 2023. That reason was wholly inconsistent with the Annex D analysis.
ii. he relied on what the position would have been if the GFAs for the Buildings had been signed by 15 September 2023 when, as a matter of fact, the GFAs had not been signed, thereby rendering clause 13.2 of the Terms completely nugatory and depriving Rydon from succeeding in having a Stage 3 Fund Building transferred out of the Fund.
iii. the consequence of the Fund decision was that Rydon will be expected to reimburse the Fund for the costs of remediating the Buildings to a substantially more extensive standard of remediation (i.e. the CAN standard) which exceeds the standard required by the contract (PAS 9980) to make the building safe. It was estimated that the difference was approximately £8 million.
Ground 3B
Conclusions on grounds 1 to 3
"Bad faith is a strong accusation not lightly to be made, it is difficult to prove and is rarely encountered. There are always readily available alternative characterisations, such as bias, improper motive, failing to promote the legislative purpose".
Alternative remedy
Is the claim academic?