![]() |
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] [DONATE] | |
England and Wales High Court (Administrative Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Administrative Court) Decisions >> Drayton Manor Farms Ltd v Stratford-Upon-Avon District Council [2025] EWHC 775 (Admin) (06 March 2025) URL: http://www.bailii.org/ew/cases/EWHC/Admin/2025/775.html Cite as: [2025] EWHC 775 (Admin) |
[New search] [Printable PDF version] [Help]
KING'S BENCH DIVISION
ADMINISTRATIVE COURT
BIRMINGHAM DISTRICT REGISTRY
Priory Courts, 33 Bull Street Birmingham, B4 6DS |
||
B e f o r e :
Between:
DRAYTON MANOR FARMS LIMITED
- and -
STRATFORD-UPON-AVON DISTRICT COUNCIL
____________________
DRAYTON MANOR FARMS LIMITED |
Claimant |
|
- and - |
||
STRATFORD-UPON-AVON DISTRICT COUNCIL |
Defendant |
____________________
THE DEFENDANT did not appear and was not represented
____________________
Crown Copyright ©
MR JUSTICE MOULD:
Introduction
Factual background
"Nationally Significant Infrastructure Projects. This application is a 32 MW extension on an existing 50 MW solar farm. The LPA considers that this may be a Nationally Significant Infrastructure Project (NSIP) as the combined threshold is above 50 MW.
Section 15 of the Planning Act 2008 requires that any proposed generating station with a capacity of more than 50 MW in England and Wales would need to seek development consent from the Secretary of State through the nationally significant infrastructure planning regime.
You are advised to seek your own legal advice as to whether the proposals fall within the relevant thresholds set out in the Planning Act 2008.
Further to this, your attention is drawn to the recent decision in Durham County Council & Anor v Secretary of State for Levelling-up, Housing and Communities [2023] EWHC 1394 (Admin).
The Durham case is now authority for the proposition that there is nothing in the TCPA which limits the granting of planning permission only in cases where it is required, i.e. the DCO regime under the Planning Act 2008 does not preclude planning permission being granted under the TCPA for the same scheme, rather it simply states planning permission is not required in addition.
So, applying the Durham reasoning, the LPA could have jurisdiction to determine a planning application for Drayton Manor Solar Farm Phase 2. In doing so, this is not confirmation that a DCO isn't also required, if it is an NSIP. The applicant would be proceeding at its own risk if it did not apply for a DCO and proceeding without a DCO could be unlawful under section 160 of the 2008 Act. The applicant is advised to seek legal advice on this.
This note should not be taken as providing any view on which is the appropriate consenting regime for these proposals, nor should any advice given in this note be taken to prejudice any future decisions that may be made by, or fetter any discretion of, the LPA in relation to these proposals."
The question before the court
"Consent under this Act ("development consent") is required for development to the extent that the development is or forms part of a nationally significant infrastructure project."
Section 160 of the 2008 Act states:
"A person commits an offence if the person carries out, or causes to be carried out, development for which development consent is required at a time when no development consent is in force in respect of the development."
"36. The alternatives are, in my view, unpalatable. Mr Kohli's suggestion that Lightsource could make an application to the Secretary of State for development consent is impractical and would not achieve the certainty required. It is impractical because applications for development consent are "front loaded" in the sense that they involve a very large amount of preparatory work, including consulting affected parties (see ss.41-48 of the PA 2008). Why would Parliament have intended that a developer should be required to consult in relation to an application which, in its view, does not require development consent at all? How could such a consultation be carried out in circumstances where the developer considers that the project is not an NSIP without confusing or misleading those being consulted? In any event, even if a developer undertook all the necessary preparatory work and submitted an application for development consent, and the Secretary of State rejected the application on the ground that development consent was not required, nothing in the PA 2008 suggests that the Secretary of State's view would bind the court if the local planning authority took a different view and decided to prosecute (though it might, in practice, be persuasive).
37. If the developer chose not to apply for development consent, it would be open to the local planning authority to prosecute under s. 160 once the development had started. Then, as Mr Kohli accepts, the criminal court would have to determine the issue. But why should a developer have to incur the expense of beginning the development when it is clear that there is a dispute between it and the local planning authority about whether development consent is required? And why should a developer have to run the risk of a criminal conviction in order to obtain certainty on a point which both it and the local planning authority wish to have resolved?
38. Finally, even if there are cases where the question whether development consent is required turns on disputed issues of fact, that is not the position here. Even Mr Kohli did not submit that there were any material disputes of fact. He was right to submit that the question whether development consent is required involves a judgment (or, as it is sometimes put, a question of mixed fact and law). But it is not the kind of judgment which requires the court to weigh the "planning merits" (i.e. the advantages and disadvantages in planning terms of a proposed development). The judgment no doubt involves considering more than one factor, but it is the kind of judgment a court has to make whenever it asks whether a given set of facts falls within a statutory concept. I can see no constitutional or institutional reason why it would be wrong for that judgment to be made by me in circumstances where both the local planning authority and the developer invite me to resolve the issue."
I respectfully agree with those observations and shall follow that approach in this case.
1) The note on the 2023 planning permission raises a legal and practical uncertainty as to the lawfulness of the Development, notwithstanding the grant of the 2023 planning permission which is on the record. That uncertainty presents an obvious barrier to investment in the project, notwithstanding the grant of the 2023 planning permission;
2) There is no alternative procedure available to the claimant to resolve that uncertainty in a definitive and legally binding way other than to seek a ruling from this court;
3) The defendant, as local planning authority, do not say otherwise (see their acknowledgement of service). They do not intend to contest the claim -
"The defendant believes it is for the court to determine whether to grant the proposed declaration based on the evidence provided. The defendant would endeavour to assist the court on relevant issues of fact and law by filing such evidence as it anticipates will assist the court in determining the claim without advocating for a particular outcome."
I note that in the event, the defendant did not file either evidence or any submissions in response to the claim.
4) On the direction of Eyre J on 21 October 2024, the claimant served proceedings on the Secretary of State for Housing, Communities and Local Government. On 6 December 2024, the Government Legal Department wrote as follows on behalf of the Secretary of State:
"Absent confirmation by the local planning authority as to whether the Development constitutes an NSIP or a declaration from the court, the claimant perceives a risk of prosecution in the event the Development is implemented. Whilst the Secretary of State has the power to grant development consent, upon receipt of a properly constituted application, it does not have the range of enforcement powers afforded to the local planning authority under Part 8 of the 2008 Act. In any event, her view as to whether development constitutes an NSIP cannot bind the local planning authority (see paragraph 36 of the judgment of Chamberlain J in Durham County Council v The Secretary of State for Levelling-up, Housing and Communities [2023] EWHC 1394 (Admin))."
The evidence
"The 2016 solar farms were designed, developed, constructed and commissioned by a single entity, Anesco Limited. Whilst planning was secured as part of a single application, the intention of the development was to design and build 10 separate solar farms, each being a size less than 5 megawatts of power in a way which would secure additional ongoing funding through subsidy schemes, such as Feed-in Tariffs and Renewable Obligation Certificates.
Initial planning consent ("the 2015 planning permission") was varied by the 2016 planning permission, which included the separation of the original application into 10 separate solar farms, together with additional ancillary details relating to their connection to the Distribution Network Operators' licensed distribution networks. During the development phase… it was decided only to design, construct and operate nine solar farms. The site known as "The Paddocks" was never constructed."
Mr Hutchings confirms that the nine separate solar farms were designed with a cumulative total generating capacity of around 45 MW. Nine new legal entities were incorporated by Anesco which were to take on ownership and operation of the nine solar farms. He gives details of the names of those companies. He continues -
"Construction and operations and maintenance contracts were entered into between Anesco and each legal entity as part of the development and construction process.
At varying stages during the development and construction process, Anesco sold each legal entity to a number of their customers, who acquired the full rights to own and operate the solar farms."
Mr Hutchings says that at present, five of the solar farms are held in community interest companies (CICs). Each of the nine solar farms took advantage of Government subsidy schemes which were available at the time of commissioning and initial operation. Those subsidy schemes were significant to the financial model of each solar farm at the time. He says that he is not aware of any similar sized solar farm constructed and commissioned at that time without the benefit of any subsidy.
"Each of the 2016 Solar Farms benefits from its own 11kV dedicated connection to the DNO electricity distribution network, (now operated by National Grid Electricity Distribution ("NGED"), but in 2016 was known as Western Power Distribution ("WPD")). In order to support nine new solar farms, WPD required a new 66kV substation to be constructed, splitting the existing 66kV overhead line between Stratford and Great Alne in two, looping in and out of the new 66kV substation.
Within the 66kV substation, a new 10-way 11kV distribution panel was constructed. Each 2016 Solar Farm connects via an 11kV dedicated cable to one of these ways. A tenth way was required by the DNO for future use, (available for any new DNO customer, not limited to solar farms).
Located within each 2016 Solar Farm is a boundary settlement meter. This meter demarks the boundary between equipment which is owned by the solar farm operator and that which is owned by the DNO."
"The following is owned and operated by the DNO and forms part of the licensed distribution network.
i) 11kV cables between each meter and the 66kV substation,
ii) the 11kV 10-way panel,
iii) the 66kV to 11kV transformers,
iv) the 66kV cables connecting to the overhead line,
v) and all associated ancillary equipment."
The claimant's case
"33. …the factors which suggest an extension [of the 2016 solar farms] on the facts of this case are as follows:
a) the 2023 solar farm and the 2016 solar farms will be broadly adjacent;
b) the landowner is the same for all of the solar farms;
c) all of the solar farms share the same vehicular access, although that is in common with the development and use of the wider landholding.
34. The features that point against that conclusion are as follows:
d) the two solar farms from inception were developed separately and at different times by different applicants; the 2023 solar farm was not anticipated when the 2016 solar farm obtained permission, and they were not conceived of as one project. Permission for the projects were granted seven years and five months apart;
e) the two projects would have separate distribution and connection agreements and would be separately metered. The 2016 solar farms actually have nine different distribution / connection agreements;
f) the solar farms would be operated by different solar farm operators with different landowner lease agreements;
g) the solar farms would operate independently of each other - both in contractual terms and in terms of physical infrastructure;
h) while there would be a common substation, NGED shall require additional capacity and will expand their existing infrastructure, creating an extended 66kV substation to include a new connection point dedicated to the 2023 solar farm. The separate connection point will include a boundary settlement meter, with all infrastructure to the north side being owned by the 2023 solar farm operator;
i) in any event, the substation is part of the DNO's apparatus for transmitting and distributing electricity, rather than being part of the generating station itself, and is the network to which all electricity customers connect to."
Conclusions
Relief