![]() |
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | |
England and Wales High Court (Chancery Division) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Chancery Division) Decisions >> Marla International Ltd v Ready4s Ltd [2021] EWHC 1968 (Ch) (14 July 2021) URL: http://www.bailii.org/ew/cases/EWHC/Ch/2021/1968.html Cite as: [2021] EWHC 1968 (Ch) |
[New search] [Printable PDF version] [Help]
BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES
INTELLECTUAL PROPERTY LIST (ChD)
The Royal Courts of Justice 7 Rolls Buildings Fetter Lane London, EC4A 1NL |
||
B e f o r e :
____________________
MARLA INTERNATIONAL LIMITED |
Claimant |
|
- and - |
||
READY4S LIMITED |
Defendant |
____________________
Oliver Caplan (instructed by McHale & Co) for the Defendant
Hearing date: 26 February 2021
____________________
Crown Copyright ©
Covid-19 Protocol: This judgment was handed down remotely by circulation to the parties' representatives by email. It will also be released for publication on BAILII and other websites. The date and time for hand-down is deemed to be 14 July 2021 at 2 pm.
Deputy Master Raeburn:
Introduction
"The Defendant does not content [sic] the Claimant owns the intellectual property in question".
The Defendant's application to set aside under CPR 13.2
The Defendant's application to set aside pursuant to CPR 13.3
Promptness
Real prospect of successfully defending the claim
i) In defence to the Claimant's claims for seven specific breaches of the Development Agreement, the Defendant:
a) denies failing to provide a minimum viable product of Android EasyBooks, the Rewritten Apple EasyBooks and the EasyBooks Web Application to the Claimant;
b) denies that it failed to deliver the "Application" to the Claimant in time for the MTD regime and avers that it was not at any time an express term of the Development Agreement that EasyBooks products or part of them, were to be provided in complete form by the dates averred by the Claimant. The Defendant further pleads that any slippage of time for delivery of the products occurred as a consequence of the Claimant's own extended scope of the Development Agreement, which it says was accepted upon the Claimant's own evidence;
c) denies the claim for failing to accurately record time and puts the Claimant to proof that any overbilling took place;
d) denies that it failed to properly staff and resource the project, although it admits staff were "switched" from the project which contributed to some delay, but that the main cause of significant delays were in fact as a consequence of the Claimant's requested increase in the scope of the project and replacement / variation of the same;
e) denies failing to properly document code and asserts that the Claimant failed to request the Defendant to update or maintain the underlying technical guides as necessary;
f) denies failing to assign intellectual property rights in the development work to the Claimant in breach of the Development Agreement; it says all IP rights in the development works under the agreement are owned by the Defendant subject to payment of its incurred costs;
g) denies that the Defendant's threats to disseminate code forming part of the development work constituted a breach of the Development Agreement and avers that the Claimant remained indebted to the Defendant and in the absence of payment, the Defendant was entitled to retain part of the code relevant to that liability.
ii) In defence to the Claimant's claims for misrepresentation, the Defendant:
a) denies that it was an express term of the Development Agreement that EasyBooks products would be completed by April 2019 (and avers that in any event, the Development Agreement was replaced and in the alternative varied). It denies that it gave any assurances by representation or otherwise to this effect; and
b) admits that it represented to the Claimant that it had the requisite ability to deliver the re-written Apple and Android EasyBooks products, but that these were not completed as a result of the Claimant's unlawful termination of the Development Agreement.
i) In relation to the defence that it was not a term of the Development Agreement that the works were to be created before the MTD regime came into effect, the Claimant refers to the deficiencies in the Defendant's evidence filed in support of its set aside application; specifically the witness statement dated 23 February 2021 from Mr. Tomasz Tybon, a consultant engaged by the Defendant. Mr. Tybon states that "it was never a term of the Development Agreement that the instructed works would be completed by or before the coming into force of the MTD regime". Counsel for the Claimant submits that it is unclear how Mr. Tybon has knowledge of the Defendant's intentions in connection with the Development Agreement, given he is not employed by the Defendant and provides no indication in his evidence as to how he has such knowledge.
ii) Counsel for the Claimant also says that the Draft Defence is inconsistent. The Defendant's deny that the Android Easybooks were to be made in time for the MTD regime coming into effect on the basis that the time for the completion of the works was subject to "continual review". However the Draft Defence then admits the paragraphs of the Particulars of Claim which plead that there was a fixed number of development hours agreed for the creation of Android EasyBooks – namely 1,402.
iii) As to the Defendant's defence to claims for failure to assign intellectual property rights in the development work to the Claimant, Counsel for the Claimant submits that the Defendant advances a defence which is wholly inconsistent with the available evidence. Referring to Mr. Tybon's witness statement, the Claimant says that this again contains statements that simply deny that it was an agreed term of the Development Agreement that the Claimant would acquire the intellectual property rights that vested in the development works. It also denies that Mr. Olaf Lesniak (who at all material times was the Defendant's Business Development Manager) had the requisite authority to enter into an agreement with the Claimant in relation to the terms of ownership of intellectual property at all. Counsel for the Claimant submits that this denial / argument cannot be advanced because:
a) there is contemporaneous evidence in which Mr. Lesniak of the Defendant responds to a request from the Claimant for confirmation from the Claimant that it will own all intellectual property rights in the works created under the Development Agreement and Mr. Lesniak states: "Yes you will own all the Intellectual Property rights";
b) there is an admission in the Defendant's solicitors' witness statement dated 7 November 2020 which states that there is no dispute between the parties as to the ownership of intellectual property in the relevant works; and
c) the Defence admits that Mr. Lesniak was, at all material times, the Defendant's Business Development Manager and was the person that entered into email correspondence with the Claimant in connection with the proposed engagement. It is submitted that any argument that Mr. Lesniak did not have the requisite authority is a fabrication and no document or evidence has been adduced to support this averment.
Nature of fault | Examples of how Defendant deviated from standard accepted practice |
Bugs and quality of coding | Much higher than normal bug count, constant revisions of software code Inability to properly prioritise the resolution of bugs No automated testing or proper QA process or test cases |
App not fit for sale, Cannot be used by more than a few customers with normal amounts of data | No caching of data for performance (non - viable solution at scale) No search capability No paging (non- viable solution at scale) Failure to implement various other development standard features such as dark mode screen, screen rotation, attachments, free trial sign up, credit notes and refunds function. |
"We are not going to meet this deadline, for a number of reasons. We have increased the scope of the project by about a 2:1 ratio, and also the complexity of the project has increased, [by] about the same 2:1 ratio. These things have meant that there is a possibility about 4X the amount of work involved as initially thought, by all of us.".
"Hi Mark,
Please answer till Monday 9 AM. No response will start procedure of debt collection.
At the same time we are going to consider to:
- report to AppStore and Google Play IP issue
- sell the source code of the product to cover our costs which I described in previous emails
I would like to avoid the above steps. I don't feel comfortable with writing that but I have to inform you about the consequences of no response."
The Publicity Order
"37(1) The High Court may by order (whether interlocutory or final) grant an injunction….in all cases in which it appears to the court to be just and convenient."
"A declaration is a discretionary, equitable remedy. The injunction is an adjunct to the declaration."
Some other good reason
"the versions of the software it received contained features or functions that were mocked up or misrepresented to give the misleading impression that progress was further along, and that aspects were working when they were not".
Denton and Discretion