![]() |
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | |
England and Wales High Court (Commercial Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Commercial Court) Decisions >> Rubicon Vantage International Pte Ltd v Krisenergy Ltd (Rev 1) [2019] EWHC 2012 (Comm) (25 July 2019) URL: http://www.bailii.org/ew/cases/EWHC/Comm/2019/2012.html Cite as: [2019] EWHC 2012 (Comm), [2020] 1 Lloyd's Rep 383 |
[New search] [Printable PDF version] [Help]
BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES
COMMERCIAL COURT (QBD)
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
RUBICON VANTAGE INTERNATIONAL PTE LTD |
Claimant |
|
- and - |
||
KRISENERGY LTD |
Defendant |
____________________
Nigel Eaton QC and John Robb (instructed by Watson Farley & Williams LLP) for the Defendant
Hearing dates: 16-17 July 2019
____________________
Crown Copyright ©
Mr Nicholas Vineall QC sitting as a Deputy High Court Judge:
BACKGROUND
i) Invoice 7[1], in the sum of $1,523,108. This claimed the total costs of the Skid integration works. It was expressed as a claim for a variation, VO-01, despite the fact that the skid integration works were always to be paid for by Kegot.
ii) Invoice 9, in the sum of $147,974 in respect of modifications to the forecastle hang off. This was accompanied by a request for a variation, VO-06.
iii) Invoice 10, in the sum of $49,466 in respect of further modification to the forecastle hang off, and expressed as VO request VO-11.
iv) Invoice 13, in the sum of $107,353, in respect of a change in the identity of the Class Society from ABS to BV, expressed as VO request VO-08.
These invoices total $1,827,901.
i) Whether the guarantee is an on-demand guarantee only in relation to claims where liability has been admitted by Kegot;
ii) A series of questions as to the proper construction of the guarantee's provisions in terms of what constitutes a proper demand;
iii) A mixed question of fact and law as to whether or not, in the light of the proper construction of the contract, the demands that were in fact made were compliant;
iv) Finally there is the factual dispute between the parties as to whether or not an admission was made by Kegot, which only matters if the guarantee is limited to claims that have been admitted by Kegot.
THE TERMS OF THE GUARANTEE, AND ITS PROPER CONSTRUCTON
WHEREAS:
A. …
B. Under the terms of the Contract, the Company is required to provide a parent company guarantee to the Contractor securing the performance by the Company of its obligations under the Contract.
C. The Guarantor has agreed to provide this deed of guarantee to satisfy that requirement.
NOW THEREFORE, in pursuance of the foregoing, it is agreed as follows:
1. Guarantor hereby unconditionally and irrevocably:
(a) guarantees to Contractor and its successors and assigns, (as primary obligor and not merely as surety) as an absolute, unconditional and continuing obligation:
(i) the due and punctual performance and observance by Company of all the terms and conditions of the Contract and of all its obligations under or pursuant to the Contract;
(ii) the due and punctual payment and discharge of all monies whatsoever which may from time to time fall due to be paid by Company under the Contract … and
(iii) to discharge on behalf of Company any debts, obligations or liability incurred by Company or any person for which Company may be liable under the Contract; and
(b) undertakes that
(i) if and whenever Company defaults in the due and punctual performance of any of its obligations under the Contract, Guarantor shall on demand by Contractor (subject to Clauses 4, 5 and 6 below) perform or cause the performance of such obligations; and
(ii) if and whenever Company fails to pay on the due date any sum whatsoever due and payable under the Contract, Guarantor shall, on first written demand, and within forty eight (48) hours from receipt of the relevant notice (subject to Clauses 4,5 and 6 below), pay such sum to Contractor.
2. As a separate and independent stipulation Guarantor, as primary obligor and not merely as surety, hereby irrevocably and unconditionally agrees to indemnify and hold harmless Contractor from and against all costs, charges, expenses, claims, liabilities, losses, duties and fees and taxes thereon suffered or incurred by Contractor, as a result of any breach or non-performance or non-compliance by Company with any of its obligations under the Contract or the extent of the Company's obligations under the Contract being or becoming void, voidable, unenforceable or ineffective against Contractor for any reason whatsoever (whether or not known to Contractor or any other person).
3. Any demand under this Guarantee shall be in writing and shall be accompanied by a sworn statement from the Chief Executive Officer or the Chief Financial Officer of the Contractor stating as follows:
(a) that the amount(s) demanded are properly claimed and due and payable in accordance with the terms of the Contract;
(b) the calculation of such sums together with any supporting documentation reasonably required to assess such demand; and
(c) that the Company was duly notified of the amount(s) demanded in accordance with the terms of the Contract.
4. In circumstances where the amount(s) demanded under this Guarantee are not in dispute between the Company and the Contractor, the Guarantor shall be obliged to pay the amount(s) demanded within forty-eight (48) hours from receipt of the demand.
5. In the event of dispute(s) between the Company and the Contractor as to the Company's liability in respect of any amount(s) demanded under this Guarantee:
(a) the Guarantor shall be obliged to pay any amount(s) demanded up to a maximum amount of United States Dollars Three Million (US$3,000,000) on demand notwithstanding any dispute between the Company and the Contractor;
(b) the Guarantor shall be entitled to withhold and defer payment of the balance of the sum demanded in excess of United States Dollars Three Million (US$3,000,000); and
(c) the Guarantor shall be entitled to withhold and defer payment of any other disputed amounts claimed under this Guarantee,
until a final judgment or final non-appealable award is published or agreement is reached between Company and contractor as to the liability for the disputed amount(s).
6. In the circumstances described in Clause 5 the Guarantor shall not make any payment in excess of United States Dollars Three Million (US$3,000,000) under this Guarantee unless the Contractor obtains a final judgement or final non-appealable award in its favour or the Company and the Contractor agree that an amount is payable by Company to Contractor. ... In circumstances where the final judgment or non-appealable award is given in favour of the Company ... the Contractor shall refund to the Guarantor the sums paid by the Guarantor to the Contractor pursuant to clause 5(a) of this Guarantee to the extent that it is found that the Contractor was not entitled to the sums demanded and paid. ...
7. In order to illustrate how Clause 5 and Clause 6 are intended to work, reference is made to the worked examples set out in Appendix 1 to this Guarantee.
8. …
9. ...
10. Save as set out in Clause 3, in no circumstances whatsoever shall Guarantor's liability hereunder vis-a-vis Contractor be greater than that of Company vis-a-vis Contractor under the Contract. The Guarantor shall have all the limitations rights and defences of the Company under the Contract
11. All payments pursuant to this Guarantee shall be made in full without set off or deduction. …
12. This Guarantee shall remain in full force and effect until all of the obligations under the Contract have been performed and shall then be returned to the Guarantor. …
…
24. The terms of this Guarantee shall be governed by and construed in accordance with the laws of England and Wales....
Whether, on its true construction, the Guarantee is an on-demand guarantee up to the value of $3m
(a) regardless of whether or not Kegot's liability under the charter is admitted; or
(b) only where Kegot's liability under the charter is admitted, but where quantum is in dispute.
The clause 3 requirements for a valid demand
3. Any demand under this Guarantee shall be in writing and shall be accompanied by a sworn statement from the Chief Executive Officer or the Chief Financial Officer of the Contractor stating as follows:
(a) that the amount(s) demanded are properly claimed and due and payable in accordance with the terms of the Contract;
(b) the calculation of such sums together with any supporting documentation reasonably required to assess such demand; and
(c) that the Company was duly notified of the amount(s) demanded in accordance with the terms of the Contract.
Any demand under this Guarantee shall be in writing and shall be accompanied by
- a sworn statement from the Chief Executive Officer or the Chief Financial Officer of the Contractor stating as follows
(a) that the amount(s) demanded are properly claimed and due and payable in accordance with the terms of the Contract
[c] that the Company was duly notified of the amount(s) demanded
- [b]the calculation of such sums together with any supporting documentation reasonably required to assess such demands
Was clause 3 complied with?
Whether there was an admission of liability by Kegot
In summary, KE agreed that the metering skid integration is required however feels that the overall cost of the metering was excessive
And then this under a column entitled first "Remarks" and then "ROI Position:"
It was agreed that compensation and reimbursement is due for the metering skid however the figure is to be discussed between the higher management of KE and ROI.
(KE) Agreed that the metering skid integration is required and there should be compensation for the integration works however considersfeelsthat the overall cost of the work was excessive.
(ROI) It was agreed that compensation and reimbursement is due for the metering skid integration however the figure is to bediscussedagreedbetweenwiththe higher management of KE and ROIKE's CEO. KE will discuss with their CEO and invite Rubicon's COO for a meeting.
CONCLUSION
Note 1 In fact 1800000007, but I will use only the final digits, since they are sufficient to distinguish between the invoices [Back]