![]() |
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | |
England and Wales High Court (Queen's Bench Division) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Queen's Bench Division) Decisions >> PJ Spillings (Builders) Ltd v Bonus Flooring Ltd [2008] 1516 EWHC (QB) (16 June 2008) URL: http://www.bailii.org/ew/cases/EWHC/QB/2008/1516.html Cite as: [2008] 1516 EWHC (QB) |
[New search] [Printable RTF version] [Help]
(Queen's Bench Division)
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
PJ SPILLINGS (BUILDERS) LIMITED |
Appellant |
|
- and - |
||
BONUS FLOORING LIMITED |
Respondent |
____________________
25 South Park Road, Wimbledon, London, SW19 8RR
Telephone: 020 8540 0766 : Facsimile: 020 8543 2227
and at
10 Herondale, Haslemere, Surrey, GU27 1RQ : Telephone: 01428 643408 : Facsimile: 01428 654059
Members of the Department of Constitutional Affairs Tape Transcription Panel
Members of the British Institute of Verbatim Reporters
Mr. Healy appeared on behalf of the Respondent.
____________________
Crown Copyright ©
Mr. Justice Forbes:
"Despite the limited design obligation upon the Claimants [i.e. Bonus] they were responsible for making sure that any concrete that was poured was workable. They cannot supervise the pouring and complain afterwards that an adjustment should be made. The time for realising that there should be an adjustment is before that pour is completed. I therefore find that the Claimants cannot claim to be paid for the area of concrete that was unsatisfactory and for the remedial measures in respect of that. If I turn to the counterclaim I therefore deduct from the claim the first two elements; that is to say, the cost of removing the defective concrete in the sum of £2,200 and the replacement concrete in the sum of £4,680. VAT has to be added to those two sums. Those are proper deductions and amount to £8,084".
"I have concluded that my figures are correct for the reasons given by the Claimants, particularly paragraph 11.3".
"By suing for damages for his costs in performing in reliance on the contract the claimant cannot recover more than he would have been entitled to if the defendant had not broken the contract. The precise arithmetical method of implementing this principle has not yet been decided, but it is submitted that the claimant should be entitled to claim his performance expenditure actually incurred to the limit imposed by the gross return or price due to poor performance. The onus of proof is on the defendant to show, on the balance of probabilities, that the claimant would have made a loss on full performance of both sides of the contract and so would not have recouped all of his own costs in performing his side".
"I am further not persuaded that there is any claim for loss of profit. This contract was run on very close to unprofitability. There was very little margin left. I cannot see how that figure is substantiated. I therefore deny them damages on those two points".
"Mr. Webb: Do you accept that if the works had continued you would have gone substantially over the contract price if these costs are to be accepted? I will rephrase that. Do you accept that if these costs are to be accepted the inevitable outcome is that by the time that another pour had been carried out and works had been completed your costs would have substantially exceeded the contract price?
Answer: Yes, I would have thought so".