QUEEN'S BENCH DIVISION
Strand, London, WC2A 2LL |
||
B e f o r e :
(sitting as a Judge of the High Court)
____________________
HDK LIMITED trading as Unique Home |
Claimant |
|
- and - |
||
SUNSHINE VENTURES LIMITED RASHMI THAKAR |
Defendants |
|
- and- |
||
HUSSEIN KURDIEH |
Third Party |
____________________
Benedict Rodgers (instructed by Layard Horsfall Ltd.) for the third party
The claimant did not appear and was not represented.
Hearing dates: 5, 6 and 7 October 2009
____________________
Crown Copyright ©
His Honour Judge Richard Seymour Q.C. :
Introduction
The contracts
"1st payment £10,000
2nd 3775 + 1000
3rd 3775 + 1000
4th 3775 + 1000
5th 3775 + 1000
6th 3775 + 1000
7th 3775 + 1000
8th 3775 + 1000 "
"13. Rashmi Thakar had various architects [sic] plans for Flat 1; I submitted 3 estimates dated 02/02/06, 26/02/06 and a final estimate 31/03/06, ("the final estimate" detailing the works and giving a price. We started in early March 2006.
14. Rashmi Thakar accepted the final quote shortly after receipt. The oral contract was made between myself and Ms Thakar in or about end March/the beginning of April 2006, and I summarise the terms of the contract.
(a) The scope of the works was as set out in the final estimate at the price stated;
(b) The build time was estimated 3 months with completion in or about July 2006, but agreed to be extended.
(c) The start time I recall was early March 2006.
(d) Payment was £10,000 on commencement with £4775 by 7 instalments spread over the contract, and a final payment of £5310 [that would make the total agreed price £48,735].
(e) Rashmi Thakar was to engage architects to obtain all necessary consents to the works, including building control consents with Landlord's consent."
"Dear Rashmi
We are pleased to submit our quotation for the followings [sic] work at the above address.
Demolition
To strip out walls and all stairs
To remove stairs and make good
To take out false ceiling
To cut out walls to take new lay out
To strip out bathrooms and kitchen
Building work
To cut out walls and fit lintels
To build up new stud work
To make good all disturbed area
To fit new doors and architrave
Painting
To prepare and make good all walls and doors
To prepare all woodwork and make good
To apply two coats of paint
Plumbing
To fit new bathrooms
To fit new pipe work to suit
Parquet
To supply and fit new under lay
To supply and fit new solid parquet
Electric's [sic]
To supply and fit electric's [sic] all through
All the above for the sum of £38000.00
All prices plus vat at 17.5%
We hope our quote meets with your kind approval. "
"Building work
To build up new stud work
To make good all disturbed area
To bond and skim walls
To fit new doors and architrave £5800.00
Painting
To prepare and make good walls, ceilings
To prepare all wood work and make good
To fill all cracks rub down
To apply two coats of paint £6500.00
Plumbing
To alter pipe work
To fit new bathrooms £4200.00
Parquet
To supply and fit solid parquet £5300.00
Heating
To supply and fit new under floor heating xxxxxxxxx
Electrics
To complete re wire all through £6300.00
Tiling
To tile bathrooms and kitchen floor £2600.00
Preliminaries £2500.00
All prices plus vat
We hope our quote meets with your kind approval."
"Dear Mrs. Thakar
We are pleased to submit our quotation for the following works at the above address.
Lift
To take out existing lift
To take out the two walls
To extend the walls to take the new lift
To build the walls in the laundry room &
Top bedroom
To make good all area and paint
Boiler
To drain down out system
To take out old boiler
To supply and fit new boiler
New Bedroom
To dig foundation
To fill concrete
To build new room
To fit all new electrics
To fit new shower room
Dinning [sic]/Breakfast Room
To dig foundation
To fill up concrete
To build the walls
To fit new windows and doors
Dinning [sic] Breakfast cont
To fit new steel beam
To cut walls to connect to new building
To move corridor wall to accommodate wheel chair
To strip down ceiling & walls
To supply and fit new ceiling plaster board
To bond and skim ceiling and walls
To re arrange electrics
All the above for the sum of £59,950.00
All prices plus vat at 17.5% (£10,491.25)
We hope our quote meets with your kind approval."
"22. In about March/April 2006 I entered into a contract to build an extension at Merrymore with Rashmi Thakar, acting for an undisclosed principal, the First Defendant; the terms of the contract were as follows:
(a) The scope of the contract are evidence [sic] by an estimate dated 28/06/06; this estimate detailed the works to be undertaken and the price of £59,950 plus VAT.
(b) It was initially agreed that Rashmi Thakar would pay £51,700 by 10 equal instalments of £5,170 spread over the contract period of [4] months, and an initial cash payment of £10,000 by mutual agreement by November 2006 because of her cash flow problems.
(c) The contract period was approximately 5 months.
23. I recall I commenced work at Merrymore in March/April 2006."
"Ref. 061640
We are carrying out the new extention [sic] for one bedroom, the extention [sic] of dinning [sic] room/living room.
The works started on the 22/06/06 and would like the foundation to be inspected if possible on Monday the 26th of June 2006."
"We are please [sic] to submit our quotation for the following works at the above address.
i. Unique Home to remove the dividing wall between two bedrooms and make it good thus creating a large reception room and prepare it for new radiators
ii. when this room was divided, one of the two rooms had a false panel hiding both working and redundant pipes and wires Unique Home was to remove all
iii. Unique Home to block the existing door to the room and create a new opening but with an arch matching the large arched window
iv. between the entrance hall and the reception hall was a set of stairs in the shape of letter "A" to enable the occupier of the flat to use both entrances, and at the peak was a door and a wall parting the entrance area from the reception area Unique Home was to remove the wall and the door
v. next to the street entrance was a large store-cupboard Unique Home was to create a cloakroom there
vi. the 'old' reception was to be a master bedroom Unique Home was to remove the old radiator, run new pipes.
vii. next to the 'old' reception was a small storage area Unique Home was to create a shower room
viii. on the other side, next to the old reception was an old kitchen, full of redundant and 'working' pipes and wires running across ceiling and along the walls Unique Home was to remove the kitchen and make it good for a second bedroom, including to run new pipes.
ix [left blank in the original]
x. inside the ancient kitchen was a large built-in larder Unique Home was to move it out
xi. behind the larder in the reception hall was a large Victorian linen cupboard Unique Home was to remove it
xii. Unique Home was to create en-suite for the second bedroom
xiii. at the end of the reception hall, next to the 'old' two bedrooms was an ancient bathroom, also full of pipes and wires running across ceiling and one wall Unique Home was to move it out and make good for a kitchen
xiv. next to the 'old' bathroom was a cupboard Unique home [sic] was to create a second cloakroom
xv. the reception hall had a false ceiling and a part of a wall was false Unique Home was to remove all false panels, pipes, wires
xvi. Unique Home was to rewire the whole flat and re-piped gas and water
xvii. Unique Home was to remove (rip out) the old layers of carpet throughout the flat, the old tiles and lino in the kitchen and bathroom and in the entrance hall
xviii. Unique Home was to repair all the windows and make them functional
All the above for the sum of £38,000
All prices plus VAT at 17.5% (£6,650)
We hope our quote meets with you [sic] kind approval"
"We are please [sic] to submit an amendment to our previous quotation for the following works at the above address.
I Unique Home was to remove the dividing wall between two bedrooms and make it good thus creating a large reception room
II Unique Home to remove false panels hiding both working and redundant pipes and wires
III Unique Home was to block the existing door to the room, create a large opening in size and shape matching the large arched window
IV between the entrance hall and the reception hall Unique Home to remove the door, wall and the set of stairs in the shape of letter "A"
V then because no longer there would be access to the second [sic] inside the building entrance Unique Home to block the second entrance thus creating an even-level floor for entrance hall with reception hall
VI Unique Home was to block the door to the large store-cupboard
VII Unique Home was to build a wall around the small storage area next to the 'old' reception
VIII Unique Home was to use both, the large store-cupboard (that was next to the street entrance) and the small storage area to create an en-suite for the master bedroom by making a new opening inside the 'old' reception
IX Unique Home to [sic] the redundant stairs (from ground floor to the first floor) and from the space, to create a cloakroom and above a large storage area with light and ventilation
X Unique Home was to remove the kitchen and make a space for a second bedroom
XI Inside the ancient kitchen where there was a large built-in larder with the space created after removing the large Victorian linen cupboard to install an en-suite for the second bedroom
XII Unique Home to remove the ancient bathroom and prepare for an installation a [sic] of a new fitted kitchen with all appliances
XIII Unique Home to create a larger ensuite where there was a cupboard next to the 'old' bathroom
XIV Unique Home was to remove all false panels, pipes, wires throughout the whole flat
XV Unique Home was to rewire the whole flat and re-piped gas and water
XVI Unique Home was to remove (rip out) the old layers of carpet throughout the flat, the old tiles and lino in the kitchen and bathroom and in the entrance hall
XVII Unique Home was to 'kill' radiators and run under-floor heating throughout the flat
XVIII Unique Home was to fit the whole flat with parquet-flooring
XIX Unique Home was to fit marble tiles at the entrance hall
XX Unique Home was to repair or remove the old air-condition system
XXI Unique Home was to repair all the windows and make them functional
XXII Unique Home was to repair or replace all internal door
All the above amended for the sum of £52,000
All prices plus VAT at 17.5% (£9,100)
We hope our quote meets with you [sic] kind approval"
"We are please [sic] to submit, we trust, the final quotation for the following works at the above address
We were instructed
to swap the kitchen for a bedroom (no.2) and
to swap the existing bathroom for a new kitchen,
to alter the size of the original bathroom,
to remove a pantry and replace it with an en-suite for a bedroom (no.2),
to remove the heavy iron pantry door (which was a safe door),
to remove and add walls throughout,
to move the original wall in the first room (now bedroom no. 1),
to remove and add doors (and extend the height of the door frames, as well as to create a large arch),
to throw away all the original doors,
to lower the ceiling (to accommodate dropped down-lighters) and
to install a modern air-conditioner,
to remove the original water-tank to enlarge the reception,
to remove the old coving and replace it with a modern one,
to elevate the existing floor level (to re-arrange the original water pipes to create an under-floor heating additional to new electrical under-wiring),
to remove the original stairs that were in front of the street-entrance and blocking the entrance-door from the main building (the old fire exit)
to remove a structural wall in the entrance hall,
to remove the original stairs that was coming from the flat above and to create an en-suite to a bedroom (no. 1) plus a cloakroom and closets,
to dig a hole under the original kitchen window to install an industrial safe,
to reposition the building's sewage pipes to cope with the newly created en-suites,
to create a brand new marble flooring in the reception hall (thus covering the ground-level opening to the basement)
to paint all walls with inflammatory [sic] oil paint.
All the above amended for the sum of £63,100
All prices plus VAT at 17.5% (£11,042.50)
We hope our quote meets with you [sic] kind approval"
"1. Structure alterations and insert of new steel beams and columns as required. Make good of walls and block up existing doorways. Removal of brick walls.
2. Supply and fit new wooden flooring.
3. Provide new electrical wiring throughout the flat with brass-plated or chrome-plated sockets. Provide and upgrade the existing heating system.
4. Fit new en-suite bathrooms.
5. Fit new closet in the hallway (WC).
6. Fit new kitchen.
7. Tiling of kitchen and bathrooms.
8. Joinery work to be carried out to include the fitting of new skirting boards and new doors.
9. Plaster ceilings and walls to be re-plastered throughout the flat.
10. Supply (?) [sic the question mark appeared in the original Flat Specification] and fit new panelled mirrors in the hallway.
11. Debris to be removed from site. Provide site clearance."
"1. Side conservatory
2. Single storey side extension to include fitment of fixtures, fittings, electrics and plumbing and to leave in a fit decorative state for residence occupancy.
3. Two storey lift shaft
4. Supply and fit new wooden flooring in the hallway, extended reception/dining room and the new en-suite bedroom.
5. Provide new electrical wiring throughout the new extension with brass-plated or chrome-plated sockets. Provide new radiators.
6. Fit new en-suite bathrooms.
7. On first floor create new en-suite bedroom out of existing upstairs reception area.
8. Relocation of doors on existing upstairs room (room 24) opposite bathroom.
9. Fit en-suite in the room upstairs.
10. Fit new kitchen.
11. Tiling of kitchen and bathrooms.
12. Joinery work to be carried out to include the fitting of new skirting boards and new doors.
13. Plaster ceilings and walls to be re-plastered throughout the extension and the extended reception and dining room.
14. Insulate the garden office.
15. Debris to be removed from site. Provide site clearance.
16. At all times the work should be carried out with due regard to Health & Safety standards as necessary when operating within a Nursing Home."
"Living Room
1. Finish the cornice around the boxing adjacent to the window
2. Prepare and paint the ceiling, cornicing and window.
Hall
1. Remove the old door frames and raise the door openings up to a height of approximately 2200. Plaster and make good ready for the new door frame and door (not chosen)
2. Finish the cupboard next to the kitchen using mdf and completing the cornice over the front
3. Build cupboard doors and frame in mdf above the guest loo and paint with primer
4. Prepare and paint the front door inside and out.
5. Level the floor and fix ditra matting to form a secure base for the marble floor tiles.
6. Prepare and paint the cornicing and cieling [sic]
Childs [sic] Bedroom
1. Prepare and paint the walls, ceiling and window
2. Build cupboard frame and doors above the bathroom
3. Remove bath panel tiles. Extend the bath panel and fit the mosaic tiles
4. Remove/replace the loo and cistern and the defective tile on the floor
5. Remove all the tiles on the wall behind the towel warmer and prime the substructure to accept new tiles
6. fit the architrave and glass door
WC
1. Tile the floor and walls in marble and fit the loo and basin/taps
2. Prepare and paint the ceiling and metal door
Main Bedroom
1. Prepare and paint the ceiling walls and windows
2. Lift the ply floor by the door and make a secure base and replace
3. Fix the skirting under the shower tray and seal with silicone
4. Prepare and paint the ceiling in the bathroom
Kitchen
1. Prepare and paint the ceiling and walls
2. Fit the extractor"
"In view of the cash flow problems the project is experiencing we are concerned about further investment. I am sorry that Rashmi feels aggrieved but she was warned that we were not able to accurately assess the state of your electricians [sic] wiring from sight and I believe she was regularly informed of the problems we exposed. In addition to the agreed work we have rewired large sections of the installation, installed new speaker cables, connected your boiler thermostats and electronic valves, put in intruder alarm and external light cables plus moved various outlet positions and installed extra ceiling lights."
"54. In April 2006, I had discussions at Merrymore and in the car whilst travelling to and from Merrymore, in my capacity as a Director of the First Defendant, with Mr. Kurdieh over proposed extension works and building works to be carried out to Merrymore. I gave Mr. Kurdieh a written specification for the works and drawing number 6662/01 [the Anders Roberts Drawing] so that he could give me a price for carrying out the works. Pg 81 82 of Exhibit RT1 contains the written specification [the reference was to the Home Specification] and drawing number 6662/01 Revision C. The work that was to be carried out included:
(i) An extension to the rear of the property to include one bedroom with disabled en suite bathroom with all electrical works complete.
(ii) An extension to the front of the property to extend the dining room and reception area. To include all electrics and carpets. I would pay for the carpet separately on supply of receipts.
(iii) A lift shaft to be installed.
(iv) To fit a kitchen. I would provide the fittings.
(v) To put convert [sic] a double room upstairs into an en suite bathroom.
(vi) To install a wall mounted boiler in the laundry room.
(vii) To move the doorway in room 24 to the side facing the bathroom.
(viii) To install a lift shaft [sic].
55. I explained to Mr. Kurdieh that I wanted the works completed as soon as possible and in any event before August 2006 as I wanted to be able to hold a summer party for the residents and I also wanted to fix the period of time over which my residents would be inconvenienced by the builders work. Mr Kurdieh said that he would carry out the works as soon as possible within that time period for the sum of £42,000 + VAT i.e. £49,350.00. I verbally accepted this offer on behalf of the First Defendant in April 2006. I had previously obtained a quotation for the work to be carried out by Bendon & Nash Architecture Limited for £45,000."
"73. In April 2006, Mr. Kurdieh entered into discussions with me, acting on behalf of the First Defendant, concerning proposed works to be carried out to 3 Gore Road. These were works that were required by New Forest District Council to be carried out. Details of this work is attached at pg 117 of RT1. This was basically some fire precaution works to the doors and door frames and other small items of work. There is no specification of works as such. The contract period agreed with Mr. Kurdieh was 3 months for the works to both Gore Road and Merrymore.
74. In April before he started work at Merrymore, I verbally agreed, acting on behalf of the First Defendant, with Mr. Kurdieh that I would pay for the materials required and that Mr. Kurdieh's men would be allowed to live rent free at 3 Gore Road for the 3 months contract period if he carried out the works. Mr. Kurdieh verbally agreed to this as it was convenient for his men and avoided the need for them to travel to Merrymore every day."
"25. By August 2006 the works at 3 Gore Road had become urgent, and legal action was being threatened. Rashmi Thakar requested that I undertook these works urgently, and I considered I ought to help Rashmi Thakar, despite my misgivings about the numerous delays in the payment schedules.
26. The works at 3 Gore Road were evidenced by an estimate dated 04/11/06 and an oral contract was made between Rashmi Thakar, acting as an agent for an undisclosed principal in about August 2006. £500 was paid on account, and the balance was due on completion."
Additions to the Flat Works
Additions to the Home Works
The termination of the contracts
"This fax to highlight the points we discussed Saturday.
The one problem that keeps occurring on this job the finance of the job always we are short of funds.
We have to go eight weeks without payment now the problem is occurring and this has to be sort [sic] out ASAP.
All outstanding matter [sic] are solved with the architect and the music man.
All what we are waiting for the arrival [sic] of the finance.
To date all materials have been ordered for the job but my boys have not been paid for the second week in a row and go without wages and that is putting strain on us.
If you can sort out the finance issues now this will speed up the progress of work with no more arguments or delays.
Rashmi from day one I promised to treat her as a sister and I did but one of her serious problem [sic] she change her mind so easy or it take [sic] so long to make decision.
It was my pleasure to meet you on Saturday and I hope through you we can push things forward as we require about fifteen thousand pounds urgently to make things happen."
"Thank you for your fax. I have spoken to Mrs. Thakar and we do not feel it is worth rehearsing misunderstandings in the past. The priority is to complete the work to the requisite standard as soon as possible.
I understand you have now agreed with Mrs. Thakar that you will complete the parquet and marble flooring and bathrooms and she will transfer to you £10,000 immediately. The outstanding monies will be settled on satisfactory completion of all the works."
"Further to my fax of Monday 25th September 06, I understand you have had further discussions with Miss Thakar. May I suggest the best way forward is as set out in my fax. Please complete the outstanding works as a matter of urgency. Miss Thakar is now resident in Walton House and her daughter returned this weekend and to find it in hospitable [sic] and in dirty conditions.
The £10,000 has been arranged and outstanding payments on Walton House will be made as soon as work is finished to an acceptable standard. Please do now complete the work as we agreed."
"If this had been originally a contract without any stipulation as to time and, therefore, with only the implication of reasonable time, it may be that the plaintiffs could have said that they had fulfilled the contract; but in my opinion the case is very different when there was an initial contract, making time of the essence of the contract: "within six or at the most, seven months". I agree that that initial time was waived by reason of the requests that the defendant made after March, 1948, for delivery; and that, if delivery had been tendered in compliance with those requests, the defendant could not have refused to accept the coach-body. Suppose, for instance, that delivery had been tendered in April, May, or June 1948: the defendant would have had no answer. It would be true that the plaintiffs could not aver and prove they were ready and willing to deliver in accordance with the original contract. They would have had, in effect, to rely on the waiver almost as a cause of action. At one time there would have been theoretical difficulties about their doing that. It would have been said that there was no consideration; or, if the contract was for the sale of goods, that there was nothing in writing to support the variation. If the defendant, as he did, led the plaintiffs to believe that he would not insist on the stipulation as to time, and that, if they carried out the work, he would accept it, and they did it, he could not afterwards set up the stipulation as to the time against them. Whether it be called waiver or forbearance on his part, or an agreed variation or substituted performance, does not matter. It is a kind of estoppel. By his conduct he evinced an intention to affect their legal relations. He made, in effect, a promise not to insist on his strict legal rights. That promise was intended to be acted on, and was in fact acted on. He cannot afterwards go back on it.
So, if the matter had stopped there, the plaintiffs could have said, notwithstanding that more than seven months had elapsed, that the defendant was bound to accept; but the matter did not stop there, because delivery was not given in compliance with the requests of the defendant. Time and time again the defendant pressed for delivery, time and time again he was assured he would have early delivery; but he never got satisfaction; and eventually at the end of June he gave notice saying that, unless the car were delivered by July 25, 1948, he would not accept it."
"I was extremely reluctant to pay any more money but I wanted the job completed as soon as possible. I felt as if I had little choice but to pay further money. Mr. Kurdieh wrote to my friend Sir Colin Campbell on 25 September 2006 to set out why the money was needed. Sir Colin showed me the letter and either later that day or the following day I spoke to Mr. Kurdieh and agreed with him that I would pay a further £15,000 to him to complete all outstanding works at the flat in accordance with the specification and our discussions. Of that £15,000, £10,000 was to be paid immediately to enable Mr. Kurdieh to order the parquet and 20mm Calcutta marble flooring and to lay them both, and for completion of the bathrooms. £5,000 was to be paid when the entire works to the Flat was complete. He agreed. Sir Colin then wrote to Mr.Kurdieh on 26 September 2006 to confirm that agreement. Consequently, and in accordance with that agreement, on 28th September I paid an additional £10,000 by bank transfer to Mr. Kurdieh "
"RE: Ms Rashmi Thakar
NOTICE OF TERMINATION WALTON HOUSE, SW3
We have been instructed by our client Ms Rashmi Thakar to formally terminate your contract for building works at the above site on the following grounds:
1. Abandonment of the works.
2. Failure to supply receipted VAT invoices for monies paid to you.
3. Failure to provide authentic receipts for specific deposits to Italian suppliers to the full value as given to you by Ms Thakar in good faith in respect of parquet flooring and marble.
4. Misinformation as to the completion of electrical works.
5. Poor quality workmanship and general damage.
6. Failure to advise client of, and then obtain necessary local building consents.
All tools and equipment you wish to be removed from the site should be collected forthwith under supervision. Please contact us to make the necessary arrangements.
In the meantime, all Ms Thakar's rights remain expressly reserved."
"After intense consideration of the matter involving the works done in Walton House and in Merrymore Nursing Home, I decided that the best way forward would be to cut my losses and part with you as a friend.
It has been an experience of a life time and the end result is very disappointing, however, I do not believe for a moment, that it was your intention to cause me a grief but it was unfortunate for both of us that Walton House was a complex refurbishment and your expertise did no [sic] match it.
I would like you to recognise that it is not possible for me to continue, or actually part, living in my property having the work uncompleted. I am sure that you acknowledge that I need to find and engage another firm that comprises of an electrician, Plummer [sic]; corgi registered engineers, painters, plasterer, and other specialist [sic] in order to both, redo the work that your firm has done or complete the work that has not been done.
I would like to end this episode and I would like to meet up with you to receive your approval of me engaging another firm who can put my flat into and [sic] order, so that I can start to enjoy living in my home.
I look forward to hearing from you.
Please call me on my mobil [sic]."
Payments made to Mr. Kurdieh
Defects in the work of Mr. Kurdieh and alleged incomplete work
"Re:- Completion of existing electrical installation 1 Walton Street, London
Further to our recent meeting please see my quotation detailed below to finish the incomplete electrical works based upon the existing electrical installation being in a satisfactory condition and fully compliant with current IEE wiring regulations BS7671."
"My view is that the amount quoted by Webster Thomas represents a reasonable sum to undertake the work scheduled as a new electrician. I would expect the price to be higher than would have been charged by Mr. Kurdieh by virtue of the fact that the scope of works is smaller and that it will involve taking over from another electrician. I would expect the price to include a premium of between 10% and 15% to reflect this."
"Air Conditioning
The split type air conditioning system installed at 1 Walton House is a Fujitsu 4 way blow 'cooling only' cassette, model numbers (indoor) AUY25FUAR and (outdoor) AOY25FNAKL.
The indoor unit is located in the living room toward a large arch way connecting a wide hall way. The living room dimensions are approximately 5.5m x 7m with a ceiling height of approximately 3.5m.
Assuming the system was designed to suite [sic] the space, its approximate 7kW output would appear to have been sized to treat both the living room and part of the hall way. Whilst this is not good practice it is a common strategy for low or rude specification installations. The main factor preventing this strategy for [sic] working as intended in this instance is the barrier formed by the wall at the top of the arch being within 400mm of the indoor unit which will cause a curtain of chilled air to both drop down vertically and deflect back/re-circulate causing short cycling of the system. During normal operation the effect would be that there would be a cold spot at the arch way, the energy consumption would be unnecessarily high and the hallway relatively lacking in air conditioning.
The designated fuse within the fuse board in the hallway cupboard was found to be tripped and therefore the system was non operational. The fuse was found to be 20A, however the recommended fuse size for this model is 36A. This incompatibility would cause the fuse to trip as soon as the indoor unit called to the outdoor unit for cooling. This was tested by resetting the fuse and activating the system via the wired remote controller in the hallway. The indoor unit ran for a very short period and then the circuit breaker tripped.
The outdoor unit is located in an unventilated wooden enclosure in the front courtyard. It should be noted that this system receives its main power supply directly to the condensing unit from the main board an [sic] this power supply should have a local means of isolation by the condenser for both emergency and maintenance. This isolator was not present and did not look to have ever been present. The condenser was not fixed down by any means and poses a risk to the fracturing of the connecting refrigerant pipe work. This poses a health and safety risk of refrigerant burns.
If the system was operational the lack of air circulating over the condenser coil would cause the system to fail and shut down after a short period of inefficient operation.
Ms Rashmi Thakar was present during the survey and advised that the outdoor unit had initially been located closer to the front door and that the electrical wiring was unsafe, and that she had an independent air conditioning contractor make safe and move the condenser to its current location, however we could not detect any physical evidence of the unit being anywhere other than where it is now and Ms Thakar did not have any documents supporting this at the time.
Overall the installation is unsatisfactory and compromises both Building Regulations and CIBSE guidelines.
Remedial action is required to fully assess the operational status of the Fujitsu equipment and the minimum works would be the fitting of a correctly sized fuse to the main fuse board, installation of a local weatherproof isolator to the outdoor unit and a full wiring termination check. The wooden enclosure will need to be removed to test the operational capacity of the system and if the box is to be reinstated then adequate ventilation should be designed into it.
The total cost for these works would be in the region of £500-£700.
Should the system require further repair these repairs could range from £100-£300.
Should the system require replacement a new model will be required due to this model being discontinued. The value of the existing system (excluding power, connecting pipe work and labour) was £970 (2005).
The cost of a comparable unit today is £1200 + vat.
Installation costs including ancillaries would be approximately £1000 + vat.
Enabling works, disposal of old equipment and refrigerant and decorations would be between £1500 and £2800 dependant on the standard of decorations
An approximate total would be £4000.
Under Floor Heating
The underfloor heating systems heat generation is provided by a communal system and as such we were unable to access nor were we able to activate the system to carry our [sic] any testing. It is assumed that the system is in 'summer mode' and therefore dormant.
We were able [to] inspect a high level cupboard in which the incoming hot water service feeds the circulation pumps to each under floor heating circuit. This cupboard is no more than a crawl space above the Bed 2 ensuite and is not readily accessible.
The Grundfos pumps appear to be of various ages and Ms Thakar advised that at least two had been replaced due to either failure or poor operation of their circuits.
The electrical termination blocks and junction boxes have not been mounted properly or at all and there was a mixture of both old and new cables used to wire into the pumps. The wiring did not appear to be to a reasonable standard and is in our opinion unsafe.
The pipe work is a rude assembly of various makes of fittings both in copper, brass and plastic. This is not adequately fixed to any structure and there is evidence of past failure of the pipe connections causing flooding and water damage to the bathroom.
Remedial action required would be to strip out the rude manifold assembly and wiring and to replace old for new with a wall mounted manifold and with electrical labelled isolators located close to the access door.
The approximate cost for these essential works is £1800 + Vat."
The claims in this action
Conclusions