[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Galliford Try Construction Ltd v Michael Heal Associates Ltd [2003] EWHC 2886 (TCC) (01 December 2003) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2003/2886.html Cite as: [2003] EWHC 2886 (TCC), 99 Con LR 19 |
[New search] [Printable RTF version] [Help]
QUEENS BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
133-137, Fetter Lane, London, EC4A 1HD |
||
B e f o r e :
____________________
GALLIFORD TRY CONSTRUCTION LIMITED |
Claimant |
|
- and - |
||
MICHAEL HEAL ASSOCIATES LIMITED |
Defendant |
____________________
Justin Mort (instructed by Beachcroft Wansbroughs for the Defendant)
____________________
Crown Copyright ©
H.H. Judge Richard Seymour Q. C. :
Introduction
(i) whether a contract was concluded between Galliford and Heal in relation to the provision by Heal of the Post-Tender Services;
(ii) if so, whether that contract was a contract "in writing" within the meaning of s. 107 of the 1996 Act, it being accepted by Mr. Mort that any contract would have been a "construction contract";
(iii) if not, whether Masons and BW agreed to submit disputes in relation to the Post-Tender Services to adjudication without there being any reservation of a right on behalf of Heal to contend in any adjudication proceedings that the adjudicator did not have jurisdiction because either no contract had been made between Galliford and Heal in respect of the provision of the Post-Tender Services, or any such contract had not been "in writing";
(iv) as an alternative to (iii), whether Heal was estopped by representation or convention from denying that the adjudicator had jurisdiction to determine disputes as to the performance of the Post-Tender Services;
(v) what, if anything, was the significance of the fact that Galliford had changed its position as to the contract alleged between the parties and no longer contended for a contract incorporating the provisions of which Mr. Eggleston found Heal to be in breach.
Was a contract concluded between Galliford and Heal in relation to the Post-Tender Services?
"As to the law, the principles to be derived from the authorities, some of which I have already mentioned, can be summarised as follows:
(1) In order to determine whether a contract has been concluded in the course of correspondence, one must first look to the correspondence as a whole (see Hussey v. Horne-Payne).
(2) Even if the parties have reached agreement on all the terms of the proposed contract, nevertheless they may intend that the contract shall not become binding until some further condition has been fulfilled. That is the ordinary "subject to contract" case.
(3) Alternatively, they may intend that the contract shall not become binding until some further term or terms have been agreed; see Love and Stewart v. Instone, where the parties failed to agree the intended strike clause, and Hussey v. Horne-Payne, where Lord Selborne said at p.323:
"…The observation has often been made, that a contract established by letters may sometimes bind parties who, when they wrote those letters, did not imagine that they were finally settling terms of the agreement by which they were to be bound; and it appears to me that no such contract ought to be held established, even by letters which would otherwise be sufficient for the purpose, if it is clear, upon the facts, that there were other conditions of the intended contract, beyond and besides those expressed in the letters, which were still in a state of negotiation only, and without the settlement of which the parties had no idea of concluding any agreement [ My [Lloyd LJ's] emphasis]
(4) Conversely, the parties may intend to be bound forthwith even though there are further terms still to be agreed or some further formality to be fulfilled (see Love and Stewart v. Instone per Lord Loreburn at p. 476).
(5) If the parties fail to reach agreement on such further terms, the existing contract is not invalidated unless the failure to reach agreement on such further terms renders the contract as a whole unworkable or void for uncertainty.
(6) It is sometimes said that the parties must agree on the essential terms and that it is only matters of detail which can be left over. This may be misleading, since the word "essential" in that context is ambiguous. If by "essential" one means a term without which the contract cannot be enforced then the statement is true: the law cannot enforce an incomplete contract. If by "essential" one means a term which the parties have agreed to be essential for the formation of a binding contract, then the statement is tautologous. If by "essential" one means only a term which the Court regards as important as opposed to a term which the Court regards as less important or a matter of detail, the statement is untrue. It is for the parties to decide whether they wish to be bound and, if so, by what terms, whether important or unimportant. It is the parties who are, in the memorable phrase coined by the Judge, "the masters of their contractual fate". Of course the more important the term is the less likely it is that the parties will have left it for future decision. But there is no legal obstacle which stands in the way of the parties agreeing to be bound now while deferring important matters to be agreed later. It happens every day when parties enter into so-called "heads of agreement"…"
"Before I turn to the facts it is important to consider briefly the approach to be adopted to the issue of contract formation in this case. It seems to me that four matters are of importance. The first is the fact that English law generally adopts an objective theory of contract formation. That means that in practice our law generally ignores the subjective expectations and the unexpressed mental reservations of the parties. Instead the governing criterion is the reasonable expectations of honest men. And in the present case that means that the yardstick is the reasonable expectations of sensible businessmen. Secondly, it is true that the coincidence of offer and acceptance will in the vast majority of cases represent the mechanism of contract formation. It is so in the case of a contract alleged to have been made by an exchange of correspondence. But it is not necessarily so in the case of a contract alleged to have come into existence during and as a result of performance. See Brogden v. Metropolitan Railway (1877) 2 AC 666; New Zealand Shipping Co. Ltd. v. A. M. Satterthwaite & Co. Ltd. [1974] 1 Lloyd's Rep 534 at p.539 col.1 [1975] AC 154 at p. 167 D-E; Gibson v. Manchester City Council [1979] 1 WLR 294. The third matter is the impact of the fact that the transaction is executed rather than executory. It is a consideration of the first importance on a number of levels. See British Bank for Foreign Trade Ltd. v. Novinex [1949] 1 KB 628 at p. 630. The fact that the transaction was performed on both sides will often make it unrealistic to argue that there was no intention to enter into legal relations. It will often make it difficult to submit that the contract is void for vagueness or uncertainty. Specifically, the fact that the transaction is executed makes it easier to imply a term resolving any uncertainty, or, alternatively, it may make it possible to treat a matter not finalised in negotiations as inessential. In this case fully executed transactions are under consideration. Clearly, similar considerations may sometimes be relevant in partly executed transactions. Fourthly, if a contract only comes into existence during and as a result of performance of the transaction it will frequently be possible to hold that the contract impliedly and retrospectively covers pre-contractual performance. See Trollope & Colls Ltd. v. Atomic Power Constructions Ltd. [1963] 1 WLR 333. "
"Following our meeting in your offices last Monday, we have now had an internal meeting and we are now progressing with the design, as far as we are able to at this stage.
For your information, although I will be involved, John Ruddy will be responsible for the day-to–day running of the job, working alongside Paul Easingwood (Engineer) and William Hird (Senior Technician). Any one of these three can be contacted with respect to queries or information.
Would it be possible to have a letter of appointment in the near future? Also, it would be extremely helpful to have a copy of your anticipated programme, together with a schedule of your requirements. Whilst we would make every effort to meet your schedule, we would like to re-assure you, and ourselves that we are able to meet your target dates. (Better to examine this now, rather than leave it until it is too late to do anything about it!)"
"Following instructions from Taywood Homes Ltd. we have pleasure in confirming our intention to appoint you as Structural Consultants for the above project, subject to the Client's confirmation of Galliford Northern as Main Contractor.
You will be aware that we are working on a letter of intent from the Client dated 1st September 2000, a copy of which is enclosed, and you will note that they have placed a limit on expenditure until such time as a formal contract is completed.
The conditions of the Client's letter of intent will be applicable to this instruction and no other conditions will apply.
The ACE Form will be the basis of the Contract between us. Fees will be in accordance with the sums stated in the Tender Documents in the sum of £35,000 with stage payments to be agreed.
There will be a requirement to provide a Design Plan for the project to meet out QA Procedures. If you are ISO9001 accredited this Plan can be in accordance with your own procedures, but if you are not ISO9001 Accredited you will be required to assist in the preparation and implementation of the Plan in consultation with our team.
We look forward to working with you on this project and to a successful outcome for all parties."
"Thank you very much for your fax of 2 October 2000 confirming your intention to appoint us as Structural Consultants for the above.
As you know we are well underway with Detail Design and we are scheduled to meet the agreed dates for delivery of information, particularly the steelwork.
I note there is a requirement to provide a Design Plan for the project. We are not currently ISO9001 accredited (although we are working towards this) and so I confirm that we are prepared to assist when required in the preparation and implementation of that plan.
As far as fees are concerned, you will appreciate that we are already incurring costs, but I do appreciate there is currently an upper limit on all costs, until the Contract is formalised.
Nevertheless, I would like to propose a schedule of stage payments, based on the 14 month programme, bearing in mind that the greater part of our work will be in the early stages of the Project. I am suggesting a monthly schedule, which I trust you are agreeable to:
October 2000 £6000 November 2000 £8000December 2000 £8000 January 2001 £3000February 2001 £4000 March 2001 £2000April 2001 £1000 May 2001 £1000June 2001 £1000 July 2001 -August 2001 £1000 September 2001 -October 2001 £1000 November 2001 -December 2001 £1000Total £35,000
It would be our intention to invoice on or around the 20th of each month, and, subject to your own arrangements with Taywood Homes, we would expect payment within one calendar month.
This is a project we feel very excited about, given its location and the fact that we are effectively restoring a building that has suffered greatly throughout it's [sic] life.
Also, I personally am very keen to continue to forge links with Galliford's [sic] who I see as making a positive contribution to construction in this area."
"You will be aware that we have received a letter of intent from Taywood Homes Ltd. for the full Contract Sum. We were not in agreement with the wording of that letter and have proposed an alternative to one particular paragraph.
This alternative has been accepted verbally and, in order to avoid any further delays in instructions, we are working on this agreement.
We can now instruct you to proceed with design work to meet the required procurement programme. This instruction is based on the content of Taywood Homes Ltd. letter appended, dated 5th October 2000, as amended by Galliford.
All references to cost reimbursement contained in the letter will apply equally to this instruction. We will inform you when formal Contracts are signed and will prepare ACE Forms for your agreement.
We trust this instruction is sufficient to enable you to proceed, Should you have any problems it would be best to discuss these with Derek Norfolk who is carrying out negotiations with the Client."
"In the event that the works do not proceed prior to entry into the contract or for any reason, except for the reasons stated in the following paragraph, you are not required to enter into the contract, you will be reimbursed by us in accordance with the provisions of payment to be contained within the contract documents for all the services and/or works that you have properly carried out in compliance with this letter up and until the date you are advised in writing that the works will not proceed or that you will not be required to enter into the contract. The level of reimbursement shall be agreed with the Employer's Agent, Burtenshaw Associates, and shall be based on the rates and prices contained within the Contract Sum Analysis. Reimbursement shall not include any resultant consequential losses or loss of overheads recovery and/or profit."
"21. Galliford do not, for a moment, dispute the proposition that these parties negotiated after October 2000 with a view to nailing down the detailed terms of their agreement and that these negotiations never resulted in agreement on those matters. However, it is Galliford's case that the arrangements entered into in October 2000 were sufficient for there to be a provisional contract ("heads of agreement" in Lloyd LJ's analysis) which the parties intended to replace in due course with a more formal arrangement.
22. In particular, the following matters had been agreed by 20.10.2000:
(1) Parties
These were to be Galliford and MHA [that is, Heal].
(2) Price
A fee of £35,000 to be paid in agreed monthly instalments and on 28 day terms, and subject to the terms as to cost reimbursement set out in the letter of 5.10.2000.
(3) Time
To meet the required procurement programme.
(4) Scope
Design works of a detailed, post-tender nature as structural consultants.
23. Moreover, MHA by their conduct in performing their post-tender works, receiving fees in the sum of £35,000 on a monthly basis and so on have made it easier for the Court to resolve any uncertainty arising in the October negotiations: Archital Luxfer."
At paragraph 15 of his Opening Note Mr. Williamson seemed to rely in particular on the attendance of Heal at monthly progress meetings and at regular design meetings, the fact that it corresponded with Galliford on design matters and the fact that it raised regular invoices for fees as conduct evincing acceptance of the memorandum dated 20 October 2000.
Was any contract concluded between Galliford and Heal an agreement "in writing" within the meaning of s. 107 of the 1996 Act?
Did Masons and BW enter into an agreement to submit to adjudication disputes in relation to the Post-Tender Services without there being a reservation of a right to Heal to contend that the adjudicator lacked jurisdiction?
"1.5 By way of an exchange of correspondence, Galliford and MHA entered into agreements in October 2000 regarding detailed design work and post-contract services ("the post-tender appointment"). Galliford asked MHA to "commence the detailed design of the work" and moreover to "proceed with design work to meet the required procurement programme" for the project. The correspondence refers to the ACE Conditions of Engagement. …
6.3 The second contract is the post-tender appointment dated October 2000. This contract incorporates the ACE Conditions of Agreement version B1. In accordance with clause B9.2 [in fact in the 1998 ACE Conditions and not in the 1995 ACE Conditions] either party may refer any dispute arising under the contract to Adjudication in accordance with the Construction Industry Council Model Adjudication Procedure. Again, please confirm that you agree with this interpretation."
"We refer to your letter of 12 March 2002 to Michael Heal Associates Ltd. and to the more recent telephone conversation (Roberts/Davis) on 27 March. We are considering your requests regarding adjudication but require further clarification from you in order to be able to respond in detail.
At paragraph 1.6 of your letter, you refer to an executed Deed of Novation. Michael Heal Associates Ltd. has never been provided with a copy of the executed deed. We will need to consider this document to be able to determine whether there is indeed any construction contract with your client in connection with the pre-tender work. Could you provide us with a copy of this document.
At paragraph 2, you have set out the dispute which appears to be that the pre-tender design concept was inadequate. As a result, a revised design was commissioned during construction which you claim led to delay and expense to your client. The dispute, therefore, appears to be regarding the adequacy of the pre-tender design but at paragraph 6.4 you refer to "both disputes". We note that at paragraph 5 you believe that there may be further claims but you indicate these do not form part of the dispute referred to in your letter. Therefore, could you clarify in precise detail what you consider to be the second dispute and explain why it is separate and does not flow from the issues regarding the pre-tender design."
"We refer to our without prejudice telephone conversations on 11 and 12 April (Harris/Roberts).
We are instructed to pursue an adjudication in order to determine the liability of your client in respect of breaches of two consultancy appointments, the details of which have already been provided. The Notice of Adjudication, Referral Statement and supporting documents are prepared and collated. We have asked for your client's consent to determine matters arising under both agreements and from a common factual matrix in a single adjudication before a single adjudicator. Without the consent sought we will invoke two adjudications and seek the appointment of a single adjudicator to determine both.
To date you have failed to give the consent sought and instead you have asked for more time to investigate the matter.
Notwithstanding the position outlined above our client recognises the merits of exploring all of the matters arising (both liability and quantum) in a neutral non-binding fashion. We note that your client is of a similar view.
Accordingly, we write to confirm the proposal that we have formulated as a consequence of our recent discussions. Our client is prepared to postpone (and indeed hopefully avoid) commencing an adjudication(s) on the understanding that our respective clients submit to mediation in respect of all outstanding issues between them. This proposal is made strictly on the basis that we agree the following immediately:-
1. to the extent that it is necessary, all disputes between the parties will be determined by reference to a single adjudicator;2. disputes under both appointments will be determined by a single adjudication;3. the parties will agree the identity of an adjudicator for these purposes. The adjudicator will be a solicitor or barrister with construction experience;4. the parties will agree an appropriate adjudication procedure to be applied; and5. the mediation will take place by no later than 17 May 2002.
To the extent that you are able to agree to all of these matters (without qualification) by close of business tomorrow we are instructed to refrain from instigating an adjudication, allow access to site for your client's expert (under supervision) and seek to agree a mediator.
If we unable [sic] to agree any of the preconditions we are instructed to withdraw the proposal to mediate and to commence adjudication proceedings without further delay.
We look forward to hearing from you."
"We refer to your without prejudice letter of 15 April 2002.
We have discussed the options with our client for progressing this matter and in particular the proposals set out in your letter.
We have repeatedly asked for a copy of the executed Deed of Novation referred to in your letter of claim dated 12 March 2002 but have not yet received a copy of this document. Without this document, we cannot advise our client regarding the assertions that there are two appointments. We are therefore, not in a position to be able consider [sic] whether any disputes arising under separate appointments can be determined by a single adjudication.
Without prejudice to our contentions on jurisdiction, we agree it would be sensible for disputes to be considered by the same person. However, before we can obtain our client's full instructions regarding your proposals we require a copy of the executed Deed of Novation.
Notwithstanding the above, we see no legitimate need to jump into an adjudication at this stage, especially without giving mediation the opportunity to work. We therefore, welcome the proposal that a mediation take place no later than 17 May 2002. We agree that the mediation should be in respect of all outstanding issues between the parties. The precise details of the mediation and the identity of the mediator can be agreed in due course.
However, we also put forward the proposal that prior to the mediation taking place, the parties and their respective engineering experts could meet to determine the main issues and the areas of disagreement.
Furthermore, in order to resolve all outstanding issues through mediation we would welcome details of the breakdown of the quantum of your client's claim. If appropriate, a meeting could then be held between the respective quantity surveying experts to narrow the issues.
We believe the parties will incur significant unnecessary costs if the matter is referred to adjudication at this stage. We trust your client will accept our agreement to refer the matter to a mediation to be conducted within the timescale put forward by your client of 17 May 2002.
We look forward to hearing from you. "
"We refer to your without prejudice letter of 16 April 2002.
Please find attached a copy of the executed Deed of Novation. We trust you are now in a position to advise your client regarding the two appointments.
With regard to your proposed meeting between the parties and their experts, we would suggest that the mediation would be the best venue for this, in the interests of saving costs.
Our letter of 15 April 2002 outlined our client's proposals regarding a possible postponement of an adjudication(s) on the understanding that our respective clients submit to mediation in respect of all outstanding issues between them. The proposals are:
1 to the extent that it is necessary, all disputes between the parties will be determined by reference to a single adjudicator;2 disputes under both appointments will be determined by a single adjudicator;3 the parties will agree the identity of an adjudicator for these purposes. The adjudicator will be a solicitor or barrister with construction experience;4 the parties will agree an appropriate adjudication procedure to be applied; and5 the mediation will take place no later than 17 May 2002.
You have failed to agree proposals 1-4 and we are consequently instructed to initiate adjudication proceedings unless the proposals are agreed immediately.
With regard to your request concerning access to site and discussion of quantum information, we see this as part of the adjudication/mediation process and as and when the matters set out above are agreed we can discuss this further.
We look forward to hearing from you."
"Thank you for your letter of 19 April 2002 and for providing us with a copy of the executed Deed of Novation. We have taken our client's further instructions and are able to respond to your client's proposals regarding a possible postponement of an adjudication.
We agree that, to the extent that it is necessary, all disputes that are referred to adjudication should be referred to the same adjudicator.
However, we do not agree that disputes arising under separate appointments should be dealt with by way of a single adjudication. Any disputes that arise from separate appointments should be dealt with by separate adjudications. There will be different issues arising from different forms of appointment and it is essential, to avoid any confusion and to ensure all matters can be dealt with fairly, that separate notices are issued. We consider this is the most appropriate way of dealing with this matter, particularly as the same adjudicator can deal with all adjudications and therefore may only need to deal with common issues once which should avoid any inconsistency. However, there is a significant risk that dealing with all issues under a single adjudication will lead to confusion and could affect the adjudicator's decision.
Your client's claim is a claim for professional negligence by a structural engineer. Therefore, the allegations are best assessed by a fellow professional of the same discipline. If your client has concerns regarding contractual issues, there are a number of engineering adjudicators who are experienced in dealing with contractual issues. One such person is David Loosemore of Arups. He is on the adjudication panel of the Institution of Civil Engineers and we enclose a copy of his CV. We confirm that, to the best of our knowledge, neither our client nor ourselves have any connection with him, save for requesting a copy of his CV.
In respect of the adjudication procedure to be applied, we are prepared for any dispute to be dealt with under the terms of the Construction Industry Council Model Adjudication Procedure, second edition.
We trust your client will agree to the slight amendments to the proposals and we can now seek to agree a procedure for a mediation of this matter.
We look forward to hearing from you."
"We refer to previous correspondence.
We write to confirm our agreement as follows:
1. to the extent that it is necessary, all disputes between the parties will be determined by reference to a single adjudicator;2. the disputes under both appointments to be determined by separate adjudications;3. the parties agree the appointment of Brian Egglestone [sic] as adjudicator (this is subject to availability and to any comments you have; we enclose a copy of his CV for your information);4. the adjudication procedure will be the Construction Industry Council Model Adjudication Procedure; and5. the mediation will take place no later than 17 May 2002.
We propose Lawrence Kershen Q.C. as the mediator and will contact him for details of his availability if you agree to his appointment.
We look forward to your response."
"Thank you for your letter of 30 April 2002.
We confirm our agreement that any disputes that are referred to adjudication may be dealt with by the same adjudicator. We also reiterate our view that any disputes arising under separate appointments can only be determined by separate adjudications.
We have no objection to the appointment of Brian Egglestone to act as adjudicator, subject to confirmation from you that neither you nor your client have had or have any connection with him. We are prepared to agree that the conduct of any adjudication will be under the Construction Industry Council Model Adjudication Procedure.
We note the timescale within which a mediation is to take place but in order for it to be productive you must provide us with further details of your client's claim. As previously requested, it would greatly assist the understanding of your client's claim if you could provide us with a copy of your client's expert's report and any report or assessment undertaken by your client's checking engineer during the contract. It would then be sensible if our expert could visit the site and meet with your expert to discuss the technical aspects with a view to narrowing the issues.
We also require details of the quantum of the claim including a breakdown of the elements of the costs and how they have been incurred. We will be grateful if you could provide this information to us as soon as possible. We can agree the formal mechanism for conducting the mediation in due course.
We do not consider that a barrister would be the most appropriate mediator. We have contacted two organisations that specialise in conducting mediations, the ADR group and CEDR and asked them to provide us with the CV's of appropriate mediators with experience in the construction industry. We anticipate receiving those details today, and will forward them to you as soon as they are received.
We are pleased your client is taking a pragmatic approach to resolving this dispute and look forward to hearing from you. "
"…the decision of the adjudicator is binding until the dispute is finally determined by legal proceedings, by arbitration (if the contract provides for arbitration or the parties otherwise agree to arbitration) or by agreement."
In other words, in this case the parties were agreeing to accept as binding the decision of Mr. Eggleston until the disputes referred to him were finally determined by legal proceedings, arbitration or agreement.
Was Heal estopped by representation or convention from denying that Mr. Eggleston had jurisdiction to make the Decision?
What, if anything, is the significance of the fact that Galliford has changed its position and no longer contends for a contract containing the terms of which Mr. Eggleston in the Decision found Heal to be in breach?
"The Post-Tender Appointment was made between the parties in October 2000 and incorporates the ACE Conditions of Agreement version B1. In accordance with clause B9.2, either party may refer any dispute arising under the contract to adjudication in accordance with the Construction Industry Council Model Adjudication Procedure. In any event, the Construction Industry Council Model Adjudication Procedure, 2nd edition, has been agreed between the parties. The parties have further agreed to nominate Mr. Brain [sic] Eggleston as adjudicator for this dispute and indeed another dispute arising under a separate appointment ("the Post [sic]-Tender Appointment")."
"9. Galliford asserts that MHA has breached express and/or implied and/or tortious obligations concerning the performance of its investigation and design duties owed to Galliford under the Post-Tender Appointment.
10. Galliford appointed MHA to advise and prepare a detailed design on behalf of Galliford. In undertaking its duties under the agreement MHA failed to advise on the further investigations necessary and failed to check the adequacy of the outline design. Crucially, Galliford assumed that the design was adequate during its negotiations with the employer and in adopting design responsibility.
11. Part way through construction the existing roof slab was found to be inadequate to support the additional floors safely and the design had to be substantially changed, following MHA's failure to produce design or structural calculations (or indeed any other evidence) to support its design. The amendments to the design resulted in a 24 week critical delay to the project and £2,118,332.14 additional direct and time-related cost. Other amendments to the design were required with regard to the infill steel work and it was discovered that steel work strengthening and structural repairs were required, which had not been provided for.
12. Galliford alleges that in carrying out or commissioning investigations and subsequently in preparing the outline and detailed design (including where necessary the requirement to review the design and advise on its sufficiency) MHA has failed to discharge its obligations to the degree required by contract or common law. Galliford has obtained an independent expert's report which supports this view.
13. Galliford asserts that if MHA had discharged its obligations to the required standard the various changes to the design and resulting delay and additional costs would not have been incurred in so far as the additional time and cost required would have been identified and incorporated in the original contract price. Alternatively, the parameters of the revised design would have been known to Galliford prior to entering into contract and the roof design could have been adequately priced in the contract sum."
"I am satisfied that in principle GALLIFORD is entitled to recover damages suffered as a result of MHA's breaches of contract and that such damages can be assessed by reference to its proven costs."
"On Gallford's case as now advanced the dispute which it purported to refer to adjudication never existed. In the circumstances the adjudicator's decision resolving such dispute must be without validity."
"40. At paragraph 4 of the Decision [in fact in dealing with the supposed contractual provision for adjudication], the Adjudicator stated that the post-tender appointment incorporated the (1998 version) of the ACE Conditions: …
41. However, this does not invalidate the Decision. It is clear from the appellate authorities (in particular Bouygues v. Dahl-Jensen [2000] BLR 522 and C&B Scene Concept Design v. Isobars [2002] BLR 93) that the key jurisdictional issue is whether the Adjudicator has answered the question he was asked to decide.
42. Here the question was essentially whether MHA were liable to Galliford in damages for breach of the provisions of the post-tender appointment: see Adjudication Notice Para 15 [which was concerned with "Nature of Redress Sought"] …The Adjudicator answered that question: see Decision paras. 50 [which summarised the effect of the Decision] and 51 [which merely ordered payment of a sum of £722,586] …The fact that, in passing, he made reference to a clause in the ACE Conditions which, it is accepted, is not applicable, is neither here nor there."
"29. But the adjudicator's jurisdiction is determined by and derives from the dispute that is referred to him. If he determines matters over and beyond the dispute, he has no jurisdiction. But the scope of the dispute was agreed, namely as to the Employer's obligation to make payment and the Contractor's entitlement to receive payment following receipt by the Employer of the Contractor's Applications for interim payment Nos. 4, 5 and 6 … In order to determine this dispute the adjudicator had to resolve as a matter of law whether clauses 30.3.3 –6 applied or not, and if they did, what was the effect of failure to serve a timeous notice by the Employer. Even if he was wrong on both these points that did not affect his jurisdiction.
30. It is important that the enforcement of an adjudicator's decision by summary judgment should not be prevented by arguments that the adjudicator has made errors of law in reaching his decision, unless the adjudicator has purported to decide matters that are not referred to him. He must decide as a matter of construction of the referral, and therefore as a matter of law, what the dispute is that he has to decide. If he erroneously decides that the dispute referred to him is wider than it is, then, in so far as he has exceeded his jurisdiction, his decision cannot be enforced. But in the present case there was entire agreement as to the scope of the dispute, and the adjudicator's decision, albeit he may have made errors of law as to the relevant contractual provisions, is still binding and enforceable until the matter is corrected in the final determination."
Conclusion