[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Tombs v Wilson Connolly Ltd. [2004] EWHC 2809 (TCC) (09 November 2004) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2004/2809.html Cite as: [2004] EWHC 2809 (TCC) |
[New search] [Printable RTF version] [Help]
QUEENS BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
MR N. K. TOMBS |
Claimant |
|
- and - |
||
WILSON CONNOLLY LTD (Formerly Wilcon Homes Ltd) |
Defendant |
____________________
Mr Gideon Scott-Holland (instructed by Eversheds) for the Defendant
Hearing dates : 4th, 5th, 6th, 7th,11th and 13th October 2004.
____________________
Crown Copyright ©
HIS HONOUR JUDGE PETER COULSON Q.C:
INTRODUCTION
THE BACKGROUND
"The top triangle of brickwork forming the front gable wall above first floor window head level appears to be out of plumb…parts of the wall seem to lean inwards and parts seem to lean outwards…there are decorative brick corbels at the eaves of this gable wall. This corbelled brickwork is deformed.
Generally speaking, the facing bricking workmanship is of an exceptionally poor quality around the entire building. The thickness of perpend and bed joints varies considerably, and perpend joints do not line up. Mortar joints have not been finished off properly. Mortar joints where concrete lintels meet brickwork are very poorly formed. On the rear elevation there appear to be some slight ripples in the face brickwork. It looks as though the bricks have been laid by a person without any training in bricklaying.
We are of the opinion that the deformation of the brickwork of the front gable wall is due to exceptionally poor workmanship rather than due to structural movement. However, in view of the obvious lack of care and expertise exhibited by the bricklayers, one is led to think that perhaps there are hidden defects in the facing brickwork also. Namely, have sufficient cavity wall ties been provided, have the wall ties been fixed to the timber frame properly and has the deformation of the wall resulted in the cavity wall ties having insufficient embedment in the brickwork.
We recommend that the top triangle of brickwork of the front gable wall be taken down to first floor window head level. The wall ties for the top triangle of the gable wall should then be inspected. If the wall ties are adequate, the brickwork should be rebuilt plumb. If there are insufficient wall ties, or if the wall ties have been poorly fixed, then a general survey of the wall ties throughout the building would be justified…"
"… I was able to view inside the cavity to establish if sufficient wall ties had been used by the builder during the construction process. To my amazement, I have established that throughout the cavity area at the rear elevation of the house, there appears to be no more than twenty wall ties securing the outer skin of bricks to the timber frame. This area measures almost 70 square metres and when you consider that there should be at least four wall ties within a square metre, then you don't have to be Einstein to realise that I am a few short.
…
I have today spoken to Mr Gerald King who I am sure you are aware of from the NHBC. He was appalled at what I told him and tomorrow will be initiating an enquiry with the inspections manager to establish who represented the NHBC during the build process and why they missed out the fact that the wall ties had not been fitted to the house or the under cloaking to the garage, both of which are NHBC requirements."
"I will as agreed supply all labour and materials to carry out the works to remedy the wall tie deficiency to this plot and will also finish off the items as mentioned in the NHBC report that we had begun to complete.
I will as agreed await to hear the final decision that will be made by the NHBC after Friday's inspection and will carry out the works as they recommend."
"The recent cavity inspection by Wilcon Homes confirms that there are indeed hidden defects in the external walls, and that the load bearing timber frame might have been damaged by the careless fixing of wall ties, or by the transmission of moisture across the cavity from the outer skin of brickwork. If a repair using remedial ties is employed, you would be left with the present extremely poor quality facing brickwork, the facing brickwork would be rather blemished by an array of marks where the remedial wall ties were inserted, and there could be problems in the future with damp penetration across the cavity. … We are of the opinion that the entire facing brickwork should be removed, the exposed timber structure inspected, and a new skin of facing brickwork be built in a workmanlike manner".
"The remedial options are:-
Remove the outer brick leaf to damp proof course level and rebuild the walling, ensuring the wall ties are inserted in the correct positions. This will also resolve the other reported brickwork problems such as the chipped bricks, brickwork out of alignment and areas of unsatisfactory standard of brickwork.
If the builder proposes to install remedial wall ties instead of rebuilding the brick outer leaf, the builder should provide full details of the installation method to NHBC and the owner for approval before works commence … the repair must not be noticeable on completion."
"Further meeting held with N.K. Tombs, bricklayer on 11th March, with J. Badcock, where he was told that we had decided to take down and re-build. He stressed that he could rectify and would not accept financial responsibility for the total cost of the taking down and rebuilding. He asked that he be given the opportunity to prove effective and invisible repair by remediating the worst elevation and allow further inspection".
"Following the borascope investigation and the appointment of Mr Clive Ringer, the situation appeared to be finally showing a more positive direction. The day he and Mr Smith came to our home to inspect the faults, it was decided conclusively by them both that the outer brickwork would have to be removed totally and the wall ties inserted into the timber structure then, for the brickwork to be re-constructed in line with the NHBC standards. This was a turning point for us and I can remember saying to my wife how finally we may be nearing a resolution, but our hopes were short-lived when during your visit you asked us to consider giving Nick Tombs the opportunity to carry out remedial repairs to various areas of brickwork after he had told you he was confident he could carry out the repairs without the work showing. I think this was a little bit insensitive of you when you consider he was the original contractor that had allowed his so-called skilled labour to build the house and breach the NHBC standards in the process and because of this man, we are in this very stressful situation."
"I met with the Bulls the following week to put this [Mr Tombs' offer] to them. An amicable meeting occurred, but they were not willing to accept this and had no trust or faith in Mr Tombs – to which I have to agree. It was concluded that we would progress the complete replacement of the brickwork."
"It is because I cannot offer you a cast iron guarantee that your programmes will be met and not wishing to adversely affect your programme that I recommend that Thetford plots 15,16 and 17 are given to another sub-contractor, at Witchford plots 19 and 20 are given to another sub-contractor, at Ely plots 152 and 153 are given to another sub-contractor and that at Caldecote, plots 223 onwards are given to another sub-contractor so that you may attempt to meet your programmes as per our conversation of this morning.
With regard to Witchford, I would recommend whilst you have a site agent who is slightly less capable than David Pugh was at Thetford (although David was a better man manager), you should seek another sub-contractor for the remainder of the site."
Mr Tombs confirmed in his cross-examination that the plots identified in this part of the letter were all of the plots on the four sites which he had not yet commenced.
1) What were the operative terms and conditions of the Sub-Contracts between the parties in existence at April 2003?
2) Does the £7,872.68 paid by WCL in April 2003 fall to be deducted from the agreed sum of £34,720.58 to be credited to Mr Tombs?
3) Did WCL repudiate the Sub-Contracts in April 2003?
4) Did Mr Tombs repudiate the Sub-Contracts in April 2003?
5) If the answer to Issue 3 is yes, is Mr Tombs entitled to claim damages by reference to his alleged loss of profit, and if so, how is that claim to be measured?
6) Did the numbers of wall ties installed in various properties at Pine Lea constitute a breach of contract on the part of Mr Tombs?
7) Did the brickwork at the Bull property constitute a breach of contract on the part of Mr Tombs?
8) If the answer to Issue six is yes, are WCL entitled to claim damages and if so, how is that claim to be measured?
9) If the answer to Issue 7 is yes, are WCL entitled to claim damages and if so, how is that claim to be measured?
I now deal with each of those Issues in turn.
Issue (1): What were the operative terms and conditions of the Sub-Contracts between the parties in existence at April 2003?
"The General Conditions were not printed on the back. The actual Conditions were sent with this front sheet. They would be behind. They were sent out every single time."
Mr Berry repeated that last phrase as a question: 'Every single time?' Mr Canning replied: 'Correct'. That was the extent of his questioning on this topic.
Issue (2) Does the £7,872.68 paid by WCL in April 2003 fall to be deducted from the agreed sum of £34,720.58 to be credited to Mr Tombs?
"I received your letter dated 16th April 2003 entitled 'brickwork payment'. There was no cheque enclosed as stated in your letter, however, I was able to collect one from your Newmarket office for the amount stated… your letter stated that I would receive a breakdown of what was included in the cheque which I collected for £7.872.68. I have yet to receive this breakdown and so I have been unable to remove this amount from the total that your company owes."
Issue 3): Did WCL repudiate Sub-Contracts in April 2003?
Issue 4): Did Mr Tombs repudiate the Sub-Contract in April 2003?
I make the following findings of fact in respect of the events leading up to Mr Tombs' decision to withdraw his labour from site:
a) I find that, prior to 4th April 2003, WCL had no reason to believe that Mr Tombs was running short of money or was in difficulties in paying his bricklayers. There was no proper evidence of any such difficulties.
b) I find that, prior to 4th April 2003, WCL did have reasonable grounds for checking carefully Mr Tombs' interim valuations/applications for payment dated 27/28.3.03, particularly those relating to Caldecote, for the reasons set out in paragraph 15 above.
c) I find that, prior to 4th April 2003, WCL did have reasonable grounds for trying to ensure that Mr Tombs performed in accordance with the respective programmes at the four principal sites. I find that it was therefore reasonable for Mr Rosher on 2nd April 2003 (paragraph 16 above) to seek some form of assurance from Mr Tombs as to his future performance. Mr Rosher may well have used the word 'guarantee' in connection with this future performance but I do not consider that, in all the circumstances, this was anything other than a reasonable request for an assurance that Mr Tombs could meet the WCL programmes. I reject the pleaded allegation that Mr Rosher was trying to (or did) impose some sort of unreasonable new condition on Mr Tombs in respect of programming and I agree with Mr Scott-Holland that Mr Tombs did not suggest that there had been any such imposition in his written or oral evidence.
d) I find Mr Tombs' written "recommendation" that new plots be given to another sub-contractor (paragraph 16 above) was made because he could not guarantee progress in accordance with the programmes on the four sites, and was honest enough to say so. I reject the suggestion that somehow Mr Rosher engineered or unfairly brought about Mr Tombs' abandonment of the brickwork at the new plots; I find that Mr Tombs provided an unqualified "recommendation" to that effect because he considered it to be the best and fairest solution to WCL's programming concerns. I also note that, in his letter of 2.4.03, Mr Tombs did not say that Mr Rosher's request for a guarantee was onerous, unfair or unreasonable.
e) I find that Mr Tombs' recollection of the meeting on 3rd April is to be preferred at least to this extent: namely that Mr Badcock effectively accepted his written recommendation by telling Mr Tombs not to start work on any new plots; and that Mr Badcock told him that WCL were expecting him to complete those plots where he had already started the brickwork. The parties were therefore agreed that Mr Tombs would not start any new plots, but would complete those which he had started. However, to the extent that it was suggested that, at this meeting, Mr Badcock made any sort of unqualified promise to pay the applications of 27/28.3.03, I reject it; it seems clear to me that Mr Badcock, and Mr Rosher, who was present for at least part of the time, told Mr Tombs that the applications were being checked and that, following that investigation process, sums which WCL considered were properly due would then be paid.
f) I find that Mr Tombs' men worked on Friday 4th April 2003 on the plots where the brickwork had started, in accordance with the effective agreement at Sub-paragraph (e) above and that on Monday 7th April Mr Tombs then unilaterally withdrew his labour from all the WCL sites where he was working because, as Mr Tombs put it in paragraph 10 of his first statement, "I informed Mr Badcock that he left me no option but to withdraw my labour force due to non-payment."
Reason 1:
The Taking Away of the New Plots
Reason 2:
The Non-Payment of the 27/28.3.03 Applications
"(28) The Company [WCL] shall make interim payment(s) to the Sub-Contractor [Mr Tombs], on provision of an invoice or … a request for payment by the Sub-Contractor, in respect of the value of all works certified by the Site Manager as properly executed to the date of the invoice by the Sub-Contractor less any amounts previously paid under this Sub-Contract and any permitted deductions or retentions.
(29) On completion of the work under this Sub-Contract, the Company shall pay to the Sub-Contractor the total sum of the agreed contract price, on provision of an invoice or a request for payment by the Sub-Contractor, less any amount previously paid under Clause 28, and any permitted deductions or retentions. Any invoice rendered by the Sub-Contractor at any time shall provide details of an appropriate VAT number and the amount of VAT due upon the sums due pursuant to that invoice.
…
(31) Invoices or requests for payment (as appropriate) delivered in accordance with Clause 28 and 29 above shall identify the site, the order number and plot(s) to which the works relate and shall be signed by the Site Manager.
…
(37) The Company will process Sub-Contractors' payments on a regular weekly/fortnightly/monthly basis based on returns received from site. It is the Sub-Contractor's responsibility to enquire about the relevant payment day and the closing day for submission of returns from particular sites. The closing day in each weekly/fortnightly/month for submission of Sub-Contractors' invoices and payment details may vary from site to site.
…
(39) Each interim payment under clause 28 and the final payment under clause 29 shall become due for payment on the date of receipt by the Company from the Sub-Contractor of a valid invoice ("the Due Date for Payment"). The Company shall (subject to the provisions of clause 36) pay each payment which has become due for payment within 14 days of the relevant Due Date for Payment (except in respect of the final payment under clause 29 which shall become payable within 28 days of the relevant Due Date for Payment ("the Final Date for Payment").
"Q: You accept, I think, that WCL could check the invoice?
A: Yes, I do not dispute that.
Q: If it therefore took longer than a week to check the invoice prior to payment, that was not unreasonable?
A: No, it was not unreasonable."
Accordingly, it seems to me that even if, which was not the case, Mr Tombs had some sort of general entitlement to be paid within 7 days of his application, such an entitlement would always be subject to WCL's right to check his invoice and, for the reasons which I have summarised at paragraph 15 above, it is plain that, in this case, the relevant invoices were quite reasonably the subject of detailed checking by WCL, which process was still ongoing on 7th April 2003. Thus, even on the basis of Mr Tombs' contention that he should have been paid generally within 7 days, he is still unable to demonstrate that WCL were in breach of contract by not paying these applications by 7th April 2003.
"Where there is such a duty [to pay by instalments] it is a question in each case whether failure to pay is a repudiation. Failure to pay one instalment out of many due under the terms of the contract is not ordinarily sufficient to amount to a repudiation."
Issue (5): If the answer to Issue 3 is Yes, is Mr Tombs entitled to claim damages by reference to his alleged loss of profit, and if so, how is that claim to be measured?
"If the employment of the Sub-Contractor shall be determined as aforesaid or in any other way, then the Sub-Contractor shall be deemed to be in breach of this sub-contract and …the Company shall only be liable to the Sub-Contractor for the value of any work actually and properly completed and not paid for at the determination and for no other sum or sums whatsoever and shall have the right to recover or deduct from or set off against any such amount the amount of damage suffered and/or loss and expense incurred by the Company by reason of the determination of this contract under this clause".
Mr Scott-Holland argued that, on the facts, the Sub-Contracts were terminated by WCL as a result of the withdrawal by Mr Tombs of his labour and that therefore this clause prohibited the claim for loss of profit. Whilst that may be right, this point actually adds nothing to WCL's case since the withdrawal of labour, being wholly unjustified as I have found, amounted itself to a wrongful repudiation by Mr Tombs, which would mean that he could not recover his loss of profit in any event. I note in passing that, even if the old conditions were incorporated into the Sub-Contracts, this point (for what it is worth) would also be available to Mr Scott-Holland, since Clause 3(iii)(c) of the old terms and conditions was in identical terms to Clause 8(c).
Issue (6) Did the numbers of wall ties installed at various properties at Pine Lea constitute a breach of contract on the part of Mr Tombs?
"The reason why the lack of wall ties was not picked up during the build by Wilson Connolly's own staff or the NHBC or myself was because the wall ties inserted matched the specification we were all working to."
His third statement (13.8.04) did not address the point at all. In none of the three statements, beyond the reference to NT3, did Mr Tombs indicate how the specification his men were allegedly working to on site differed from the NHBC Specification with which he was contractually obliged to comply. This vagueness on such an important point of his own defence was matched by Mr Andrews, who was Mr Tombs' foreman at the Pine Lea site. He simply refers to 'a new specification' supplied by Mr Blackaby. The most detail that Mr Andrews provided was that "the normal spaces between wall ties are 255mm but we were told to space them 300mm." However it was agreed by both parties that if wall ties had been spaced at 300mm, the frequency of ties would have far exceeded the maximum required by the NHBC. As a result, neither side relied on this aspect of Mr Andrews' evidence or suggested that it was right.
"As far as I am aware, Mr Tombs' gangs put in the number of ties that they were required to according to the specifications laid down by the timber frame manufacturers and/or the NHBC inspectors."
His second statement of 21.6.04 talks about the Specification of the manufacturers of the ties, Guildway/Helifix, which he said was faxed to him on site and his verbal instruction to Mr Andrews to insert the wall ties 'using the above-mentioned specification'. In cross-examination, Mr Blackaby was unable to remember the contents of the Specification faxed to him on site and could not recall what rate or frequency of wall tie insertion he had instructed the men to follow. He pointed out that the 300mm identified by Mr Andrews would have led to ties being 'very close together'.
"The sheet was marked by hand to indicate a spacing of wall ties at 2.5 m² at 600mm vertical centres which the Site Manager instructed him to follow."
At page 26, paragraph 4.04, Mr Taylor said:
"It is stated by Mr Tombs that he was instructed to install the wall ties at 2.5 per m², and this is the figure that had been circled in pen on the copy of Table B in the Helifix literature exhibited."
And on the following page at paragraph 5.02 Mr Taylor repeated:-
"It is alleged by Mr Tombs that he was instructed by the Site Manager to install wall ties at 2.5 per m². The Site Manager, Mr Blackaby, confirms in his second witness statement that he did give instruction to Mr Tombs regarding the spacing of wall ties."
It was therefore crystal clear from Mr Taylor's report, as he confirmed in his oral evidence, that his understanding from Mr Tombs was that the bricklayers were instructed to install the ties at 2.5 ties per m². It should also be noted that it was not only Mr Taylor who understood that his client's case was that there was an instruction to install the ties at 2.5 ties/m²; that is also the case set out in Mr Berry's Written Opening provided in the week before the trial started.
Issue (7) Did the brickwork at the Bull property constitute a breach of contract on the part of Mr Tombs?
Issue (8) If the answer to Issue 6 is Yes, are WCL entitled to damages and, if so, how is that claim to be measured?
"For the avoidance of doubt, the Company may employ others to make good any defects for which the Sub-Contractor is responsible which appear in the sub-contract works without informing the sub-contractor and the company is not obliged to first afford the sub-contractor an opportunity to remedy the defects itself."
Issue (9): If the answer to Issue 7 is Yes, are WCL entitled to claim damages and, if so, how is that claim to be measured?
Item 1: Ibstock Brick Claim: £2,853.13.
The adjusted figure of £2,428.20 is less than the amount originally claimed because of the concession on VAT. Mr Taylor accepted it as reasonable.
Item 2: Meadowstone Claim: £766.54.
Mr Taylor suggested that this figure should be reduced because some of the sills could have been salvaged. However, in cross examination, he accepted that it was reasonable for WCL to conclude that all the lintels and sills would break when they were being removed and that it was reasonable for WCL to ensure that a complete set of replacements was available. He also accepted that the sills that had been in place for some months would look weathered and would therefore contrast with the new sills that were being provided. For all these reasons, it is clear to me that Mr Taylor's attempted reduction of this figure must fail. The correct figure for this item is therefore £766.54.
Items 3, 5, 7, 11, 17 and 22: Storage Charges
Total Claim: £4,335.27
Mr Greenwood made a reduction to this claim of £363 on the grounds that he had reduced the relevant work period. The total reduced sum was £3,378.88 which also takes into account the concession on VAT. Given my conclusion that Mr Greenwood's 15-week period is reasonable and the right starting point for an evaluation of these costs, no additional reductions should be made to Mr Greenwood's figures: the principle of recovery was not in dispute. The right figure for this item is therefore £3,378.88
Item 4: Ibstock Brick Claim: £214.32
Mr Greenwood's reduced figure of £182.40 was not challenged.
Item 6: CQMS Claim: £1,028.13
Mr Greenwood has reduced the amount claimed to £875, but considers that this sum is recoverable in principle. It seems to me that, given Mr Taylor's answers in cross-examination, Mr Tombs cannot challenge this item. This item is for a Health and Safety Plan. There was a potential argument that, since this was a domestic property, no such plan was required but Mr Taylor could not say that it was unreasonable for WCL to prepare a plan; indeed, he said that he would promote such plans "in all aspects". The challenge to this item is therefore rejected, and the right figure is £875.
Items 8, 15, 16, and 21: TB Scaffolding Claims £12,255.25.
Mr Greenwood's figure for these items was substantially reduced to £3,695. This reduction from the sums originally claimed reflected Mr Greenwood's view as to how the work should have been carried out and also reflected his reduction in respect of the period the work should have taken. Mr Taylor took no other points in respect of these items. Therefore the reduced sum of £3,695 identified above by Mr Greenwood is recoverable.
Item 9: Salvage of Chimney Liners Claim £209.92
There was a dispute about this small item because Mr Taylor suggested that the chimney liner ought to have been salvaged. However, based on his evidence and that of Mr Greenwood, I reject that contention. There was a clear risk that the liner would be damaged when it was removed and cracks might form in the liner which, on re-use, could have been disastrous. I therefore reject this attempted reduction; the right figure is £209.92.
Item 10: Existing stopcock Claim: £24.73
It was suggested that this item should not be allowed, because it was in the timbered frame not the brickwork. However, I am satisfied on the evidence that the stopcock had to be removed to enable the brickwork outer leaf to be removed and that a new stopcock was not unreasonable. The right figure is therefore £21.05 (taking into account the concession on VAT).
Item 12: Meadowstone Claim: £103.17
This item was not challenged, and should therefore be allowed in the sum of £87.30, which is exclusive of VAT.
Items 13 and 30: Smith Building Services Claims: £28,098.97
These two items of claims have been reduced to £10,000 and £13,914.02 respectively in consequence of the concession on VAT. Although Mr Greenwood makes a number of very small points about these claims at pages 10-12 of his Supplemental Report, they do not amount to very much. No alternative figures have been produced by Mr Greenwood, and I therefore reduce the first figure of £10,000 by £1000 to cover all those minor points that he has raised. Although Mr Taylor had no particular points to make about the Smith Building Services claims, Mr Berry had a number of general criticisms to make about the use of Smith Building Services in the first place. These points were dealt with in Mr Greenwood's cross-examination. Mr Greenwood confirmed that, in their reduced amounts, the costs of Smith Building Services were reasonable. He said that it was quite appropriate that they should have been employed to act as supervisors, and he rejected the criticisms of their supervisory regime. He did not believe that there was an overlap between Smith Building Services and the inspections carried out by Mr King. Whilst he said that he thought file notes of these inspections should have been produced, he did not consider that that was any reason to reduce the amount claimed. He rejected the suggestion that a handling fee in respect of those items which Smith Building Services sub-contracted was inappropriate: indeed he said that it was normal to charge such fee by way of profit and attendance. On his calculation, profit and attendance 15% would have given rise to greater sums than those claimed by Smith Building Services. Accordingly, given that Mr Taylor did not seek to challenge the Smith Building Services sums in any detail and given Mr Greenwood's comprehensive answers to the points put to him in cross-examination, I accept the (reduced) figures for Smith Building Services as reasonable, in the sums of £9,000, and £13,914.02 respectively.
Item 14: Cavity Socks Claim: £122.20.
Mr Taylor confirmed that the reduced figure of £104 reasonable.
Item 18: Osborn Brickwork Claim: £22,945.40
This figure was reduced to £19,528 exclusive of VAT. Mr Greenwood considered that that sum was reasonable. In his evidence, Mr Taylor endeavoured to take as the start point the sums paid to Mr Tombs originally, but he accepted that there would be a 25-32% uplift on that figure because, since this was remedial work, it would attract a premium. He also said that it was a relatively small job compared to the work for which Mr Tombs had tendered so there would not be any economies of scale. He also identified a number of other things for which Mr Tombs' price would not have included. He confirmed that, even on this basis, he had no alternative figure to suggest: he confirmed that he did not even know how much Mr Tombs had been paid. Mr Greenwood was cross-examined on the Osborn invoice. With one exception, he stuck to his view that the sums claimed were reasonable. The exception were the two items referable to the brickwork above the DPC having been built up and then being taken down again because the DPC was defective. These two sums, at £240 and £385 respectively, are not recoverable and will have to be deducted from the figure of £19,528, giving a revised total of £18,904. Accordingly, having heard the evidence of Mr Greenwood and Mr Taylor, I consider that the right amount recoverable in respect of Osborn Brickworks' principal invoice was £18,904, a reduction of £624 from the figure originally assessed by Mr Greenwood.
Items 19, 20, 23 and 24: Other brickwork Claims: £529.60
Mr Greenwood had discounted these four small items in full and I agree that they should not be recoverable.
Items 25 and 26: Landscaping Claims: £870 and £609.44
Mr Greenwood considered that the charges were reasonable. Mr Taylor accepted that the plants would have inevitably been damaged when the scaffolding was put up and that protection to the plants would not have prevented such damage. He was unable to comment on the cost of replacing the shrubs. In the circumstances, therefore, I allow these costs in full in the sums of £870 and £609.44.
Items 27, 28: Portico Claims: £264 and £245
These items were claimed in the sum of £264 and £245 respectively and were not challenged by Mr Taylor. They should therefore be allowed in full.
Item 29: Cleancare Claim: £443.56
Mr Greenwood was of the view that the sum claimed was too high and reduced it to £122.50. I accept that lower amount.
Item 31: Norfolk Drywall Claim: £240
Mr Greenwood considered the sum of £240 claimed was reasonable and it was not challenged by Mr Taylor.
Item 32: P & B Flooring Claim: £1,029.30
This item was claimed at £1,029.30 but Mr Greenwood reduced it to £150 on the basis that there should not have been any significant charge for replacing carpets given the fact that protection was, or should have been, provided. This reduced figure is not challenged by Mr Taylor and I therefore accept the sum of £150 for this item.
Item 33: Steve Leigh Claim: £52
This claim was for £44.25 exclusive of VAT. As a matter of principle, it follows from Item 10.
CONCLUSIONS