![]() |
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | |
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Re-Source America Ltd. v Platt Site Services Ltd & Anor (No 3) [2005] EWHC 2242 (TCC) (20 October 2005) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2005/2242.html Cite as: [2005] EWHC 2242 (TCC) |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
Re-Source America Limited |
Claimant |
|
And |
||
Platt Site Services Limited |
Defendant and Part 20 Claimant |
|
And |
||
Barkin Construction Limited |
Defendant to Part 20 Claim |
____________________
Mr Robert Moxom Browne QC (instructed by Watmores, Chancery House, 53 – 64 Chancery House, Chancery Lane, WC2A 1RP (Ref: IKM.TAD.TU PLATT/1) for Platt Site Services Limited
Re-Source America International Limited was neither a party to, nor represented at, Barkin Construction's application.
Hearing date: 28 July 2005
____________________
Crown Copyright ©
Judge Thornton QC:
1. Introduction
2. Factual Background
"The judge found, as he said, a long catalogue of negligence against Barkin. It had undertaken entire responsibility for the way in which the hotwork was to be done and the protection of Re-Source's stock. Platt's fault, through its young welder Mr Atherton, was to acquiesce in the use of the unsatisfactory protection provided by Mr Andrews [Barkin's managing director]. Mr Atherton's evidence was that he had never used welding blankets before. His employer Mr Platt was unaware of the holes in the blankets."
Laws LJ put the matter pithily in stating:
"As Brooke LJ [the third member of the court] succinctly states, the fire was Barkin's fault, not Platt's."
"There remains one concern which is whether in the light of the terms of the judgment and the strong criticism of Barkin the insurers will honour the policy. They might have grounds for saying that they have been the victims of a total lack of co-operation from their insured from the word go and that there would have been other ways of disposing of the litigation. … we ask you to accept for present purposes that there is a question mark over the ability of Barkin to pay …
Until we have an unequivocal assurance from Barkin that the insurers will honour the policy and the policy will respond, then our position is that we should not be put on risk of having to pay [Re-Source] either costs or damages and be at risk of failing to recover from Barkin. …
It is about who should bear the risk. If that risk can be removed either by Mr Cannon [counsel for Barkin] saying the insurers are not going to repudiate or putting the money on the table or giving it to me or your Lordship making an order that I do not have to pay [Re-Source] until I have been paid, there are a number of ways as long as the risk is removed. But the risk should not stay with [Platt], who are blameless in this matter …
We have to be released from the action by [Re-Source] and Barkin … ."
"As a consequence of a judgment given by the Court of Appeal, Barkin has paid too much to Re-Source on behalf of Platt and now seeks to recover that over-payment from Platt."
3. The Parties' Submissions
4. The Relevant Orders
A. Order entered on 10 June 2003
"1. There be judgment for Re-Source on the issues of liability and causation, for damages to be assessed. …
5. Barkin do fully indemnify Platt in respect of its liability to Re-Source for damages and costs.
6. Barkin do pay Platt its costs of the action and the Part 20 proceedings to date … ."
B. Order entered on 8 July 2003
"1. Barkin do by 21 July 2003 pay Re-Source the sum of US$500,000 by way of interim payment on account of damages.
2. Barkin, and not Platt, do pay Re-Source any further damages or costs to which Re-Source may be adjudged entitled as against Platt."
C. Order entered on 14 November 2003
1 – 11. [Orders concerned with case management matters which were directed solely to Re-Source and Barkin and in which Platt was not named].
"12. Platt agrees to be bound by the judgment on quantum."
D. Order entered after the damages trial
"Judgment to Re-Source America International Ltd in the following sums:
(i) US$1,367,746.43
(ii) £100,391.56
(iii) Interest: US$159,592.92
(iv) Interest: £12,773.45."
E. Order giving effect to the judgment of the Court of Appeal made on 8 February 2004
"On reading [Barkin's] Notice … filed on behalf of [Barkin] on appeal from the Order of His Honour Judge Thornton QC dated 23rd December 2003
And on reading [Re-Source's] Notice … filed on behalf of [Re-Source] seeking to affirm the order of His Honour Judge Thornton QC on different or additional grounds
And on hearing Mr Mark Cannon counsel for [Barkin] and Mr Alexander Hickey counsel for [Re-Source]
It is ordered
(2) that the appeal be allowed and the judgment for damages in favour of [Re-Source] in the order … dated 23rd December 2003 be reduced by US$503,884 and US$58,795 interest
(3) that Re-Source repay to [Barkin] $562,679 together with interest thereon from 20th January 2004 until 8th February 2005 at 1% over base rate totalling US$32,123.
(4) …
(5) that there be liberty to Barkin to apply to the Technology and Construction Court in the event that Re-Source should fail to pay any sum which it is liable or becomes liable to pay pursuant to this order."
5. Basis of Court of Appeal's Order Against Re-Source
5. The Relevant Orders
(1) Barkin was the obviously guilty party whose negligence had caused the fire and who Re-Source should have sued direct. Furthermore, Barkin's culpable misconduct had put its insurance cover at risk of being avoided. If it was avoided, Barkin would then be unable fully to meet its liability to indemnify Platt.
(2) Platt was in receipt of a complete indemnity that required Barkin to indemnify it for its entire liability to Re-Source for damages, interest and costs.
(3) Platt was at risk of being unable to meet the judgments in favour of Re-Source if Barkin failed to indemnify it in full.
(4) If the judgment sums were not paid in full due to insolvency, the risk of non-payment and any insolvency should not fall on Platt but, instead, should fall on Re-Source.
(5) Re-Source supported the applications for direct payment because it did not want to run the risk that money would be paid by Barkin to Platt which was not then paid on because Platt had become insolvent and the payments then used by the liquidator to meet the claims of all creditors proving in the liquidation.
(6) Platt was entitled to be spared further expense in conducing continuing litigation involving the quantification of Re-Source's damages. Barkin should, if possible, take full responsibility for contesting and paying the damages that Re-Source was entitled to.
(1) Platt would not be a party to any order requiring it to pay money to Re-Source;
(2) Responsibility for payment, and the risk of non-payment, of the judgment in favour of Re-Source would not fall on Platt; and
(3) Platt would take no part in, nor be a party to, any further litigation involving the quantification of damages.
"… shall amount to a complete indemnity." (section 2(2) of the Contribution Act 1978)
(1) A Part 20 defendant may be ordered to pay a judgment sum to the claimant direct where the payment would otherwise initially have to pass through the hands of another party to the action. This power arises because the court has an inherent power to regulate the manner in which a judgment should be discharged by all other parties who have a liability to pay the judgment sum when directing how a judgment or order should be drawn up. This power should be exercised in accordance with the overriding objective which requires that cases should be dealt with proportionately and fairly. Relevant considerations include who should bear the risk of insolvency, the avoidance of circuitry of action and what is necessary to enable procedural justice to be achieved. Such considerations can, in an appropriate case, lead to a direct payment order.
(2) A Part 20 defendant may be ordered to make a direct payment in respect of the claimant's costs pursuant to the court's power to direct that a party ultimately liable to pay another party's costs can be ordered to pay them directly rather than through a third party to the action. This power is provided by CPR 44.3(2) which provides that although the general rule is that the unsuccessful party will be ordered to pay the costs of the successful party, the court may make a different order.
… if the second defendant is insolvent the plaintiff loses them. The proper form of order now is to order the defendant who is liable for them as between himself and his co-defendant to pay them to the co-defendant.[4]
Sanderson orders have repeatedly been authorised by the court in insolvency and other cases that have followed Sanderson, particularly Mayer v Harte[5].
6. Barkin's Contentions as to the Relevant Orders
7. Barkin's Alternative Restitutionary Claims
8. Barkin as Platt's Agent
9. Barkin as the Indemnifying Party
10. Conclusion
HH Judge Thornton QC
Technology and Construction Court
20 October 2005
Note 1 The liability judgment was handed down by the TCC on 4 June 2003, [2003] EWHC 1142 (TCC) and the Court of Appeal judgments on appeal were handed down on 28 May 2004, [2004] EWCA Civ 665. The quantum judgment was handed down by the TCC on 23 December 2003, [2004] EWHC 1405 (TCC) and the Court of Appeal judgments on appeal were handed down on 22 February 2005, [2005] EWCA Civ 97. [Back] Note 2 Sanderson v Blythe Theatre Co [1903] 2 KB 533, CA. [Back] Note 3 (1881) 17 Ch D 600, CA. [Back]