![]() |
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | |
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Machenair Ltd v Gill & Wilkinson Ltd [2005] EWHC 445 (TCC) (14 March 2005) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2005/445.html Cite as: [2005] EWHC 445 (TCC) |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Oxford Row, Leeds, LS1 3BG |
||
B e f o r e :
____________________
MACHENAIR LIMITED |
Claimant |
|
- and - |
||
GILL AND WILKINSON LIMITED |
Defendant |
____________________
MR. C. DODD for the Defendant
____________________
Crown Copyright ©
14th March 2005
Part 1, introduction.
Part 2, the facts.
Part 3, the present proceedings.
Part 4, what were the terms of the sub-sub-contract between Gill and Machenair?
Part 5, what sums are due in respect of variations?
Part 6, Gill's counterclaim.
Part 7, the conduct of litigation in the Technology and Construction Court.
Part 8, conclusion.
Part 1. Introduction.
Part 2. The facts.
(1) By purchase order No. 38849 dated 12th February 2003 Gill engaged Machenair to install low pressure hot water heating, sanitary ware, soil and waste pipes, domestic services and gas installation for the sum of £40,592.(2) By purchase order No. 38850 dated 12th February 2003 Gill engaged Machenair to supply and install a ventilation system to the toilet areas for the sum of £11,500.
(3) By purchase order No. 3025 dated 1st July 2003 Gill engaged Machenair to supply and install additional ductwork to the roof void and lift shaft for the sum of £2,180.
"(1) There is no supporting substantiation for the extension of time, and on the factors raised we comment as follows.
(2) Within your letter dated 4th April you state the lack of external wall plastering has delayed the works. Whilst we acknowledge there have been problems in this respect, there has at all times been sufficient areas of work available for you. Please refer to our sub-contract progress meeting No. 5.
(3) We believe that:
(a) your initial notice that you believed it was necessary to derogate from the IBSEC outline specification indicated that you were late addressing the final boiler and flue designs;
(b) your final proposals/designs for boiler and flue configuration were submitted later than we would reasonably have expected.
(4) Furthermore, we believe that another factor affecting progress which you have failed to take into account has been the fluctuating level of resource provided by yourselves over recent weeks, which at times has been insufficient to maintain planned regular progress."
Part 3. The present proceedings.
Part 4. What were the terms of the sub-sub-contract between Gill and Machenair?
(1) On balance of probabilities Gill did not send hard copies of their purchase orders to Machenair. Gill simply relied on the faxes. In relation to this issue I note that no hard copies of the purchase orders have been disclosed by Machenair.(2) The obliteration by the fax header was of such an extent that it was unreasonable to expect the recipient to decipher the words underneath.
(3) In any event (even if I am wrong in my previous conclusions) the words at the bottom of the purchase orders were not sufficient to incorporate Gill's standard conditions into the sub-sub-contract. Gill's printed conditions are extensive. They are not one of the standard forms used within the industry. They were never supplied to Machenair. The note on the purchase orders did not contain any form of resume of those conditions. In my view, the present case should be distinguished from the authorities cited in footnote 64 on page 714 of the 29th edition of Chitty on Contracts.
Part 5. What sums are due in respect of variations?
Item 4: Strip/refit damaged ducts, £1,066.
Item 5: Builders' water service, £123.
Item 6: Erect water tanks and headers, £861.
Item 7: Raise pipework in first floor, £177.
This work was necessary because the original data line given to Machenair was too low. I reject the contention that Machenair ought to have spotted that the instructions originally given were wrong.
Item 8: Builders' holes cut for Gill, £838.
Gill were responsible for the cutting of these holes, see paragraph 11.1 of the minutes of the sub-contract progress meeting on 22nd May.
Item 9: Extra heating pipes for landings, £990.
Item 10: Soil header in basement, £631.
Item 11: Refit eight radiators, £568.
Item 12: Refit two radiators removed by plasterers, £93.
Item 13: Remove and refit radiator to new WC, £93.
Item 14: Repair damaged heating pipes in loft, £93.
I reject the contention that the original pipework was insufficiently supported. This damage was caused by the insulation contractor standing on the pipework. This comment also applies to Item 15.
Item 15: Repair damaged MCW pipes in loft, £93.
Item 16: Replace damaged pipework in loft, £1,323
This damage was caused by the erection of steelwork after Machenair had installed the pipes.
Item 17: Install revised overflows, £471.
Item 18: Revised plant from layout, £2,475.
Mr. Friend was cross-examined vigorously and entirely properly on this item. On the basis of the oral evidence, and also the time sheets, I am satisfied that two men (a welder and an assistant) spent 50 hours each carrying out this task.
Item 19: Install external MDPE, £123.
Item 20: Remove and refit disabled WC, £139.
Item 21: Cut and re-route soil pipe in disabled WC, £141.
Item 22: Extend soil pipes in roof space, £918.
Item 23: Remove and refit damaged sink top, £69.
Item 24: Remove and refit water heater in staffroom, £46.
Item 25: Re-test heating services, £269.
I reject the contention that this work was for the benefit of Machenair. The re-test was instructed by Gill. It demonstrated that three fitments provided by Gill were faulty.
Item 26: Strip out and replace three faulty fittings, £185.
This work followed on from Item 25.
Item 27: Strip out wastes to basins, £46.
Item 28: Additional works to water heaters, £2,500.
I agree with Mr. Jacklin that Machenair should give credit for the work in respect of the original 11 water heaters. This work has been omitted. Nevertheless, the omitted work would have been substantially less than the work required by the new heaters. It should also be noted that Machenair's figure for this item increased by more than £1,000 between Version 1 and Version 3 of the final account.
Item 29: Additional works to wastes, £672.
Item 30: Re-route services in ground floor WC, £185.
Item 31: Attend meetings, nil.
Item 32: Supply and fit boilerhouse vent, £830.
Item 33: Modifications to boilerhouse vent, £320.
Item 34: Install 16 valves to domestic services, £370.
Item 35: Install water mains to water heaters, £4,662.
Item 36: Fit MCW to bypasses, £215.
Item 37: Heat test and set up water heaters, £926.
Item 38: Alter tank connections, £370.
Item 39: Alter basement wastes, £141.
Item 40: Alter and refit feed and expansion pipes, £278.
Item 41: Strip and remake tap wastes, £370.
Item 42: Paint gas pipework, nil.
This was part of the original work, and not a variation.
Item 43: Remove and refit pipework roses, £463.
Item 44: Reseat taps and refit WC, £278.
Item 45: Premium time for weekend working, nil.
Part 6. Gill's counterclaim.
(1) As can be seen from Part 5 of this judgment, there was a considerable amount of additional work which Machenair was required to undertake.(2) The late installation of the IPS system by the joiners caused substantial delay to Machenair.
(3) The late delivery of water heaters by Gill caused substantial delay to Machenair.
(4) Gill's instruction to install 16 extra valves (Item 34 in the schedule of variations) was not issued until 1st August. There has been some debate as to whether Machenair should have appreciated in advance that this work would be required. In my judgment, Machenair would not have appreciated that. Mr. Jacklin accepted in cross-examination that these valves were not shown on the drawings.
Part 7. The conduct of litigation in the Technology and Construction Court.
(1) Costs would have been reduced if at an early stage the device of a Scott Schedule had been used to set out the parties' contentions in respect of variations. This should either have been proposed by the parties or, alternatively, ordered by the court as a matter of case management. Furthermore, the existence of a Scott Schedule would have made my task easier at trial.(2) Much relevant evidence was omitted from the witness statements - in particular, that of Mr. Friend. The consequence was prolonged oral examination-in-chief. If I had not imposed a guillotine on the length of evidence-in-chief, this trial would have overrun its estimate, thus generating substantial further costs.
(3) The purpose of cross-examining witnesses is not to elicit their opinions about points of law or about the nature of the legal obligations imposed on the parties, nor is it the purpose of cross-examination to obtain a witness's general comments on the merits of the case. The purpose of cross-examination is to elicit factual or expert evidence which is within the witness's personal knowledge or expertise, and which is relevant to the issues before the court. In a case like the present, where the volume of fact is almost infinite, both restraint by counsel and occasional intervention by the court are necessary in order to confine the trial to its proper length.
Part 8. Conclusion.