![]() |
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | |
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> CFW Architects (A Firm) v Cowlin Construction Ltd [2006] EWHC 6 (TCC) (23 January 2006) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2006/6.html Cite as: 105 Con LR 116, [2006] EWHC 6 (TCC), [2006] CILL 2335 |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
131 137 Fetter Lane, EC4A 1HD |
||
B e f o r e :
____________________
CFW Architects (A Firm) |
Claimant |
|
- and - |
||
Cowlin Construction Limited |
Defendant |
____________________
Mr Sean Brannigan (instructed by Hammonds, Rutland House, 148 Edmund Street, Birmingham, B3 2JR, (Ref: JCB/COW.068-0003) for the Defendant
Hearing dates: 11 13, 17 19, 24 & 27 October 2005
____________________
Crown Copyright ©
HH Judge Thornton QC:
1. Introduction
2. Issue 1: What Were the Relevant Contract Terms and Obligations Relating to the Timing and Programming of the Production of Design Drawings?
"Further to our telephone call yesterday. I am pleased and relieved that we have reached agreement regarding our appointment details, I will prepare the appointment documents and forward them to you for signature, I confirm the following basic points:
03. Form of appointment to be the standard RIBA Standard Form of Appointment for Design & Build
The instalment breakdown will be subject to the programme of design information, the details of which will no doubt become clearer at the meeting on [13 June 2000]; it is therefore probable that I won't be able to issue the appointment document to you until week commencing 19 June 2000 as I am on leave next week."
"Further to my fax to Ian Natt of the 8th June 2000, I have now liaised with the team in our office that will be producing the drawing information to suit your building programme, and have prepared a draft Architects Appointment Document which I will forward to you for signature. However we are still to agree the instalment schedule for our stage payments, which will be recorded in the Appointment Document. I therefore propose the following:
[a list of 24 small monthly payments from June 2000 to May 2002] ".
"Further to my fax earlier today, I have again liaised with the team in our office who will be producing the drawing information, and confirm that we will discuss/agree the 'milestone' payments at our meeting tomorrow, however I propose the following which perhaps you could give some thought to prior to tomorrow:
10 July 2000 - £75,000 > see notes below for definition of milestone stages
7 August 2000 - £75,000 > leading up to completion by 30th October 2000
4 September 2000 - £30,000 >
2 October 2000 - £30,000 >
30 October 2000 - £30,000 >
[a list of 19 small monthly payments from November 2000 to April 2002]
Month 1 10 July 2000
- general arrangement plans for sites 1, 2 & 3
- general arrangement house sections for sites 1, 2 & 3
- sit layouts for sites 1, 2 & 3
Month 2 7 August 2000
- block elevations for sites 1, 2 & 3
- general arrangement plans for site 4
- general arrangement sections for site 4
Month 3 4 Sept 2000
- site layout for site 4
- external works details for sites 1, 2 3 & 4
- external fabric details for sites 1, 2, 3 & 4
Month 4 2 Oct 2000
- block elevations for site 4
- miscellaneous details/kitchen
layouts for all four sites
Month 5 30 Oct 2000
- completion of miscellaneous details
- overall completion on checking of
production information"
"Following the agreement of the 'milestone' stage payments of our lump sum fee with Mike Spiller, I have been able to complete the Appointment Document and attach two copies. Please complete as follows and return one copy for our use, and retain one for your records:-
a. Insert the date of the building contract on page A
b. Execute as a deed on page G
c. Initial the foot of each page adjacent to my initial
Many thanks."
"11. The services that were to be performed by CFW were as described in SFA/99 with Amendment DB2/99. As part of these services, the architect is to identify any key dates that the contractor client wishes to achieve and to advise on the consequences of any subsequent changes on cost and programme. [The adjudicator referred to Note 3 and E5 of DB2/99]
12. There is both an express and an implied duty on the architect that he will actively seek out the key dates, advise if these are achievable and notify the contractor of the consequences if these dates are changed or are failed to be met. The architect is therefore under a duty to produce the information that he has been commissioned to produce in a timely manner that will meet the contractor's programme, provided always that such a programme is reasonable and achievable."
(1) The payment schedule was to be read with the contract programme, being the revised version of that programme issued on 6 July 2000.
(2) The general arrangement plans and sections and block elevations for sections 1, 2 and 3 would be prepared, completed and approved by, respectively, 10 July 2000 and 7 August 2000;
(3) The designs for sections 1, 2 and 3 would be prepared and made available for approval by Pick Everard at times that would enable the drawings to be made available to Cowlin having been approved at times that would enable Cowlin to start construction work on 7 August 2000; and
(4) The design information would be provided in a form, to the necessary level of detail and by the necessary dates as would reasonably allow all necessary pre-construction consents to be obtained and for the starting and completion of the units in accordance with the contract programme. This required the designs to be presented in a form that meant that the overall design was substantially complete;
(5) Each separate instalment would be paid on the stipulated date but it was a condition precedent to each payment that the work attributed to that payment had been completed so that any delay in completion would lead to a corresponding postponement of the payment obligation.
" the evidence shows that [the parties] were of one mind on the matter. Their common intention was that the engineer should design a warehouse which would be fit for the purpose for which it was required. That common intention gives rise to a term implied in fact."[2]
" what we needed to put in our appointment document was a schedule of drawings and dates when they would be completed by. So that became our design programme which was attached to our appointment document."[3]
"Q. You at least accept that, in accordance with your schedule, this milestone schedule, the design works had to be finished at some time before 7th August 2000 for areas one to three?
A. For the items listed there, yes."[4]
"In accordance with well-known and settled principles, therefore, any time obligation would be set at large by any prevention event. CFW would simply have an obligation, in these circumstances, to complete its design within a reasonable time taking into account the impact of the acts of prevention."[5]
3. Issue 2: Did CFW Breach the Terms of Its Engagement in Failing to Produce the Drawings Necessary to Allow Construction to Commence on North and South Avon Until Shortly Before 20th October 2000?
"[Cowlin to] Complete the design and detailing of part(s) of the Work as specified and provide complete production information (including, as appropriate, fabrication/installation drawings, all design calculations, specifications etc.) based on the drawings, this specification and other information provided, liaising with the [Project Manager] and others as necessary to help ensure co-ordination of the work with related buildings and services.
All drawings should be provided at 1.50 scale with 1:5 details of all building envelope elements. All design work is to be substantially complete before the Contractor will be allowed to commence work on site. Production details for North and South Avon Estates is to be provided as part of the tender package.
When preparing the Programme make reasonable allowance for completing design/production information including submission to the Planning Supervisor for comment, inspection by the PM, and any subsequent amendment(s) and reinspection(s). A minimum of 2 weeks should be allowed for the PM to respond to any query or document etc."
(1) It was not possible in the time available to produce the necessary detail and, in any case, this timetable was even more onerous than the contractual timetable;
(2) There were delays in receiving much needed detail from other design team members;
(3) The approval process was unduly and unreasonably prolonged, whether as a result of Cowlin or Pick Everard or both;
(4) Pick Everard insisted on a series and continuing number of changes which were not, as suggested, needed corrections to allow the designs to accord with the contract specification and drawings but were variations to that outline scheme. These needed time to incorporate into the designs;
(5) Cowlin also insisted on a series and continuing number of changes which, again involved further time to incorporate them. These included changes required to reinstate details provided for by the contract specification which CFW had reasonably omitted as part of its obligation to attempt to make reasonable cost savings by changes to or omissions from the contract specification or other design engineering methods. Cowlin also was late in supplying essential details needed from its subcontractors and suppliers to enable the design to be completed; and
(6) Pick Everard was unreasonable in not allowing construction work to start on site at both South and North Avon until 20 October 2000.
(1) The information being produced by CFW was substantially lacking in detail;
(2) Often, what detail there was failed to accord with the tender specification and drawings which had to be worked to. The result was substantial changes were demanded by Pick Everard, a stance it was entitled to take;
(3) The various changes demanded were reasonably needed to correct CFW's errors of design and were not needed to correct design details reasonably provided by Cowlin. These change instructions were not actioned sufficiently speedily by CFW and, on occasion, were not actioned at all by CFW;
(4) CFW did not have adequate resources on the job, it allowed the project to be led and managed by a partner who lacked the capability to undertake those roles and it failed to provide adequate resources. This was a particularly glaring omission since CFW had had a detailed involvement in the initial production of the construction programme and in the planning for the necessary design programme needed to enable the implementation of that construction programme; and
(5) Cowlin attempted as best it could to assist CFW by attempting to persuade Pick Everard away from insisting upon its entitlement to peer review a completed design substantially in accordance with the contract and to refuse to permit a start of construction work on site until the designs were substantially complete, in both cases with only limited success.
"I do regard there [as] being advanced [by CFW] a general case that the finalisation of the design drawings to be produced pursuant to the design set up programme were dependent upon the input from, amongst others, DHE's approval [and to] to variations as pleaded . Those are, however, very general allegations that do not identify in any way what the nature of the variations were and how that approval process delayed any particular set of drawings, and in the absence, as apparently there is, of expert evidence, I regard the case at the moment as being one which is only being advanced in very general terms. If, therefore, reliance is sought in closing submissions on a great deal of detail to make good in any more detailed way than the general way I have summarised, I regard that as not being within the ambit of the present pleadings and that that more detailed case is not currently open to be advanced."
"(1) Whilst a party is entitled to present its case as it thinks fit and it is not to be directed as to the method by which it is to plead or prove its claim whether on liability or quantum, a defendant on the other hand is entitled to know the case that it has to meet.
(2) With this in mind a court may indeed must in order to ensure fairness and observance of the principles of natural justice require a party to spell out with sufficient particularity its case, and where its case depends upon the causal effect of an interaction of events, to spell out the nexus in an intelligible form. A party will not be entitled to prove at trial a case which it is unable to plead having been given a reasonable opportunity to do so, since the other party would be faced at the trial with a case which it also did not have a reasonable and sufficient opportunity to meet.
(3) What is sufficient particularity is a matter of fact and degree in each case. A balance has to be struck between excessive particularity and basic information. The approach must also be cost effective. The information may already be in the possession of a party or readily available to it so it may not be necessary to go into great detail."
In this case, the general nature of each party's case is clearly pleaded, the nature of the case, that in general terms causation is or is not established on defined grounds, is also clearly pleaded and any further information either party fairly needed to advance its respective contentions was readily available to it and no further detail was needed.
"I have now liaised with the team in our office who will be producing the drawing information to suit your building programme ".
"Tim
TIDWORTH
Regarding the above, Jeff, Darren & I managed to achieve the target of 22 August 2000 after some very long & arduous days drawings.
Colin [Clark] rang us to express his views that if the 22nd August package is not enough to enable Cowlin to start then they must be f***ing barmy.
However, on a far more serious note, if you come into the office over the bank holiday weekend, it is essential that you DO NOT touch the Tidworth drawings. We, (all 5 of us) must sit down with you and discuss, amongst other things, the technical standard & accuracy of your drawing work. Many hours were spent last week correcting your work, and as a practice, I feel (and I am sure that the other 4 feel also) that we cannot continue in this manner for the next 10 years, and therefore it is vital that you acknowledge there is a serious problem which must be properly addressed.
I have saved several of these if you require examples, but there have unfortunately been too many discovered to save them all.
For the sake of the Practice and everyone's sanity, we must all speak soon regarding this.
Neil."
4. Issue 3: Did CFW or Cowlin Repudiate the Contract in August 2001?
"Neil noted that there is an awful lot of work to do. Noses to the grindstone, don't ever go home, grow an extra arm, gird the loins etc."
I am satisfied that this is a reference to the Tidworth contract and not to CFW's work generally and that the relevant minute is recording what amounts to a warning to Mr Worsfold to bring the Tidworth contract under control and to start acting as if he was a CFW partner, albeit the minute is worded in what might be described as CFW in-house code.
"With regard to the resources of the practice, I can assure you that whilst we were somewhat taken aback by the amount of retrospective works required following Tim Worsfold's departure (and I understand this is our concern not yours) we feel we have now made significant gains in this area. Part of our problem of course was not knowing exactly how much work was required, which is why we failed to meet deadlines offered on tracking sheets etc ".
The second document was a report from CFW to the design team which included this passage:
"Further to the departure of Tim Worsfold from CFW, Jeff Murray has assumed responsibility for the Project; the transition has highlighted several areas of concern to the practice, it has become evident that items such as tracking sheets, site queries and clarification over elements such as external finishes etc. have slipped behind programme. CFW are aware of their responsibilities to supply such information and endeavour to rectify the backlog.
East Wylie
Site design ongoing ".
"Outstanding £30,000 fees against East Wylie production information is not a negotiable item, we were promised payment upon providing drawings for construction purposes, this was subsequently amended to submission of peer review and then amended to receipt of peer review report. All of these items have been satisfied and we still await payment."
"When I came out of the meeting what I would say is that we agreed to differ on it and consider it and come back my parting words would have been along the lines of, "I don't think we're going to get anywhere today, I'm going back to the office, I'll take the opportunity to discuss this [i.e. Mr Spiller's proposal] with my partners and we will then respond to you in due course" as soon as possible obviously. But I was not in a position to turn round and just agree everything right there and then with Mr Spiller."[7]
"The above reflects the topics discussed, if there are any other items discussed which I have not mentioned, please let me know. In the meantime, I await your response."
(1) A party commits a repudiatory breach of contract where he threatens to, or does, breach the contract in such a way "as to show that he does not mean to accept the obligations of the contract any further"[8];
(2) Such a breach occurs:
(i) where the contracting parties have agreed, whether by express words or implication of law that any breach of the contractual term in question shall entitle the other party to elect to put an end to all remaining primary obligations of both parties, i.e. were there is a breach of condition; or
(ii) where the event resulting from the breach of contract has the effect of depriving the other party of substantially the whole benefit which it was the intention of the parties that he should obtain from the contract, i.e. where there has been a fundamental breach of contract[9];
(3) Repudiation is a drastic conclusion which should only be held to arise in clear cases of a refusal, in a matter going to the root of the contract, to perform contractual obligations[10];
(4) An absolute refusal to carry out the work or an abandonment of the work before it is substantially completed, without any lawful excuse, is a repudiation[11];
(5) In relation to the failure by an employer to pay an instalment of the contract price:
(i) there cannot be a repudiation if there is no contractual duty to pay the instalment[12];
(ii) failure to pay one instalment out of many due under the terms of the contract is not ordinarily sufficient to amount to a repudiation[13];
(iii) a failure to pay is less likely to be a repudiation if it occurs towards the end of a contract[14];
(6) Where a party affirms a contract after becoming aware of repudiatory breach by the other party, he cannot thereafter rely on that breach in order to discharge his obligation to perform the contract[15]; and
(7) Where one party has failed to perform a condition of the contract, the other party cannot rely on that non-performance if it was caused by its own wrongful acts[16].
5. Issue 4: Did CFW's Repudiation Cause Cowlin to Suffer Loss?
Factual Background.
Cowlin's contentions.
(1) Cowlin had to find an alternative architect who could complete the outstanding design work and correct any outstanding detailing errors in CFW's drawings.
(2) ST was the obvious and reasonable choice, particularly given its previous involvement and familiarity with CFW's designs and it was willing and able to accept the commission and to provide, as the maximum resources it could offer, a team of up to 5 design technicians to work on the Tidworth project.
(3) ST was reasonably instructed first to complete the West Wylie designs and then to turn to, carry out and complete the East Wylie designs. This led to the East Wylie designs being available to allow a start of construction work at that site in June 2002. Work could not have started any earlier for two reasons, the need to complete the design drawings and the construction work at West Wylie.
(4) It was not reasonably possible, given the amount of unfinished design work requiring ST's attention at West Wylie and the limited resources it could make available, for the East Wylie designs to be completed any earlier than they were or for construction work to start any earlier than it did on the East Wylie site.
(5) The work proceeded at East Wylie at as fast a pace as could reasonably be achieved and, without any delay being caused by the dry lining work, was completed by 30 April 2003. This was a shorter period than had been programmed for originally.
(6) It was necessary, as a result of DHE's instructions, for the external works to be carried out in their entirety after the construction work had been completed. In consequence, the external works were carried out over a 12-week period immediately preceding 30 April 2003.
(7) CFW's repudiation delayed the commencement of the East Wylie works by a period of at least 35 weeks. This, in consequence, delayed the completion of those works by an equivalent period.
(8) Cowlin secured a fortuitous settlement with DHE to the effect that it received an extension of time for the period of delayed completion for all but 12 weeks of the delay that CFW had caused at East Wylie.
(9) In consequence, the only loss Cowlin suffered was the loss attributable to the last 12 weeks of the contract.
(10) Although the external works were the only works being undertaken in that last 12-week period, the delay was not caused by those works or by any late design of those works. The 12-week period of delay had been caused, as a knock-on by the delay in starting and completing the design work and the consequent delay in starting construction work and that initial delay had been directly caused by CFW's repudiation.
Findings in relation to Cowlin's case.
"On the case presented by Cowlin, CFW repudiated its contract and the contract came to an end in August 2001. The remaining progress was the best that could be achieved by way of a reasonable response to that repudiation without particular recourse to any specific programme. As a matter of fact, given the resources available, the drawings were produced as quickly as they could have been and the work was then carried out within a reasonable timescale. CFW repudiated the contract and therefore any delay that occurred thereafter was a consequence of the repudiation and is not a matter for which you are responsible. Cowlin was the "victim" of that repudiation and it had a duty to mitigate the loss that that repudiation caused. However, unless CFW can show that Cowlin acted wholly unreasonably in the steps it took to mitigate its loss, it cannot be said to have failed in its duty to mitigate its loss."[17]
"We took every step. We had a meeting with Strides, we set out what we required, they afforded us the amount of resources they could put to what our requirements were. There was not any way that they could afford any more resources and I could not go anywhere else in terms of architecture to procure another company to actually carry out any works. We had taken Strides on the understanding that we would soak up all their extra resources and anybody additional to that that they could put on to this project, bearing in mind the remainder of the project was virtually dealt with by one architect, where on Strides we had five people I believe working on the drawings."[18]
(1) Cowlin instructed ST to start with the West Wylie drawings and to complete those before embarking on the East Wylie drawings. This was a reasonable decision to have taken, it enabled the drawings to be completed in the order in which the work was by then programmed to be done, it prevented any interruption of the work on site and it prevented even longer delays to West Wylie which would have occurred had attention been turned to East Wylie or had ST's resources been shared between both sites and it enabled the semi-complete works, which were still open to the elements, to be finished off without further damage occurring to the work that had been achieved.
(2) ST had limited resources available and they devoted the entirety of the resources that were available who worked as hard as possible under great pressure. ST could not have coped with any greater volume of work or have worked and produced drawings faster than was in fact achieved. This was because of the inherent difficulties of the design process, the need to start halfway into the project with another architect's half completed designs, CFW's many errors requiring correction and an absence of the information obtained by CFW when it was the lead design consultant.
(3) The work at East Wylie was not delayed nor could it have started before the West Wylie work had been completed. This is because there were insufficient resources for Cowlin to work on both sites simultaneously. This problem arose because of the lateness in starting work on the West Wylie site, itself a produce of CFW's delays in finalising accurate and substantially completed designs. There was no evidence adduced by either party as to causes of delay whilst work proceeded save for unsubstantiated assertions by CFW that the dry lining work caused delay and progress was appreciably faster than had originally been programmed.
6. Issue 5: What is the Recoverable Quantum of Loss Flowing from CFW's Breaches of Contract and its Repudiation of the Contract?
Breach losses
Repudiation losses
"Please find a schedule containing details of the LADs and actual handover dates as applied in accordance with the terms of the contract. The total damages under the contract are £436,000 and have been deducted from the amounts due to you
The details incorporated in the schedule are all fully in accordance with the terms of the contract and therefore are not subject to negotiation or amendment. I can confirm that the agreement contained in Amendment 2 and 4 to the contract [which included agreement as to the extent of the extension of time and consequent additional payment] was concluded on a 'without prejudice' basis."
1. The construction works were divided into phases, the critical phases being phase 3 comprising a minimum of 22 type C and 2 type D houses; phase 4 comprising a minimum of 42 type C and 4 type D houses and phase 5 comprising the balance of the works. The dates for these completion handover events were provided in the contract programme.
2. The contract provided for extensions of time to be granted for listed causes of delay in the control of, or at the risk of, the employer. These extended dates were to be fixed by the Project Manager. A final extension of time would be considered and, if necessary granted, within 42 days after completion of the works.
3. The contract was for the provision of housing. The liquidated damages therefore were calculated on a house by house basis. Each house incomplete at the relevant date for the completion of a phase that should have been completed then would have liquidated damages calculated separately in accordance with a formula which comprised 4 elements.
4. The four elements were as follows:
"Type C | ||
Calculation of liquidated and ascertained damages | ||
Week 1 | Weeks 2 - 26 | |
Alternative Accommodation | 3,800 | Nil |
Residence to place of duty charge | 190 | Nil |
Disturbance allowance | 400 | Nil |
Removal charge | 470 | Nil |
Total | 4,860 | 190 |
- Alternative Accommodation: Standard weekly charge by "Hambro" plus 5% commission plus 4% inflation
- Residence to place of duty charge: 20 miles @ £0.198 x 7 days = £27.72
Taxis, two round trips to take children to school 2 Nr x £15,00 x 5 days = £150.00 plus inflation
- Disturbance allowance: Standard MOD Charge
- Removal charge: £450.00 plus inflation; taken from actual costs on another MOD project"
5. The extension of time clause was intended to operate so that each house was treated separately and to both the phased provisions and to the date for completion. Thus, those houses due to be completed prior to the completion date would be considered for an extension of time from the phased date for completion, the balance from the date for completion.
"In my view, a pre-estimate of damages does not have to be right in order to be reasonable. There must be a substantial discrepancy between the level of damages stipulated in the contract and the level of damages which is likely to be suffered before it can be said that the agreed pre-estimate is unreasonable."[20]
7. Issue 6: Additional Claims
Drawings discrepancies
8. Issue 7. Cowlin's Overall Recovery
1. Mobilisation (paragraph 155) | 30,968.66 |
2. Lean mix (paragraph 163) | 4,301.88 |
3. Type 1 (paragraph 166) | 11,225.40 |
4. 6F2 (paragraph 169) | 14,642.97 |
5. Crushed concrete (paragraph 176) | 24,046.80 |
6. Liquidated damages (paragraph 192) | 419,670.00 |
7. Prolongation costs (paragraph 195) | 87,216.96 |
8. Head office overheads (paragraph 199) | 143,088.90 |
9. ST costs (paragraph 201) | 35,000.00 |
10. Additional fees (paragraph 204) | 7,803.62 |
4,218.23 | |
11. Price Increases (paragraph 205) | 26,170.00 |
12. Additional claims (paragraph 212) | 23,606.00 |
2,293.01 | |
Total | 834,252.42 |
HH Judge Anthony Thornton QC
Technology and Construction Court
Note 1 (1975) 4 BLR 4, CA. [Back] Note 3 Day 4/44/12 17. [Back] Note 5 Written opening submission, paragraph 10. [Back] Note 6 (1997) 82 BLR 39, at page 76. [Back] Note 7 D6/35/29 - /36/18. [Back] Note 8 Heyman v Darwins [1942] AC 356 at 378 & 398, HL. [Back] Note 9 Photo Production v Securicor [1989] AC 827 at 849, HL. [Back] Note 10 Woodar v Wimpey [1980] 1 WLR 277 at 283, HL. [Back] Note 11 Mersey Steel & Iron Co Ltd v Naylor (1884) 9 APP. Cas 434, HL. [Back] Note 12 Rees v Lines (1837) 8 C & P 126. [Back] Note 13 Mersey Steel & Iron Co Ltd v Naylor ibid. [Back] Note 14 Cornwall v Henson [1900] 2 Ch 298,CA. [Back] Note 15 Peyman v Lanjani [1985] Ch. 457. [Back] Note 16 Roberts v Bury Commissioners (1870) LR 4 CP 755. [Back] Note 17 A slightly amended version of an exchange, taken from the transcript, between the judge and Mr Brannigan after the conclusion of the evidence which was clarifying the issues that were to be addressed in closing submissions and after both parties cases had been closed. The contents of this quotation were submitted by Mr Brannigan accurately to summarise Cowlins case as it then stood. [Back] Note 18 D3/49/21 - /50/28. [Back]