![]() |
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | |
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Honeywell Control Systems Ltd. v Multiplex Constructions (UK) Ltd. [2007] EWHC 390 (TCC) (27 February 2007) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2007/390.html Cite as: [2007] EWHC 390 (TCC) |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY & CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
HONEYWELL CONTROL SYSTEMS LIMITED |
Claimant |
|
- and - |
||
MULTIPLEX CONSTRUCTIONS (UK) LIMITED |
Defendant |
____________________
6th Floor, 12-14 New Fetter Lane, London EC4A 1AG.
Telephone No: 020 7936 6000. Fax No: 020 7427 0093
DX 410 LDE [email protected]
MR. MARTIN BOWDERY QC and MR. ROBERT CLAY (instructed by Beale & Co., London) for the Defendant
____________________
Crown Copyright ©
MR. JUSTICE JACKSON :
Part 1. Introduction
Part 2. The facts
"Employer's Changes. The Employer may at any time issue a notice proposing a Change in the form set out in the Employer's Requirements (a 'Change Notice Proposal'). The term 'Change' means:
.1 a change (including any omission of work, services or obligations) to the Employer's Requirements ..."
"the Sub-Contractor has been issued with copies of all documents forming the Contract except any detailed prices of the Contractor included in the Employer's Requirements, the Contractor's Proposals or the Contract Sum Analysis. In addition the Sub-Contractor has examined and discussed the Sub-Contract Documents and the Contract with the Contractor at length and is satisfied:
.1 as to the feasibility, practicality and sufficiency of the Sub-Contract Documents and has consequently agreed to accept full responsibility for the feasibility, practicality and sufficiency of the designs and specifications for the Sub-Contract Works;
.2 that the Sub-Contract Works can be carried out and completed with ten timescale envisaged within the Appendix part 4 at a cost not exceeding the Sub-Contract Sum; and
.3 that there is no divergence or inconsistency between the Sub-Contract Documents or the Contract."
"the Sub-Contractor shall be deemed to have notice of all the provisions of the Contract except any detailed prices of the Contractor included in the Employer's Requirements, the Contractor's Proposal or the Contract Sum Analysis."
"the Sub-Contract comprises the conditions together with any Special Conditions annexed hereto (collectively referred to as the 'Sub-Contract Conditions'), the Appendix and the Articles of Agreement. Unless otherwise specifically stated a reference in the Articles of Agreement or the Sub-Contract Conditions or any Special Conditions to any article or clause means that article in the Articles of Agreement or that clause in the Sub-Contract Conditions or Any Special Conditions."
"Works: the demolition of existing structures, Site clearance, ground and enabling works, construction, fit out and other works, the supply of goods, materials, components and parts, and all other work specified in or as may reasonably be inferred from or implied in the Employer's Requirements, the Contractor's Proposals or otherwise in the Contract and including all work, actions and services and any changes made to the foregoing in accordance with the Contract necessary or required to implement and complete the design, construction, fit-out, testing, commissioning, setting to work and handover of the Project and any works performed or defects, shrinkages or other faults or outstanding items corrected and/or completed during the defects liabilities period in accordance with the Contract.
Contract: The Design and Construct Contract including the Contract Appendices thereto dated 26 September 2002 between the Employer, (Wembley National Stadium Limited) and Multiplex Constructions (UK) Limited and Multiplex Constructions PTY Limited as guarantor, and referred to as the 'contract'.
Inspection: The contract, the Contract Appendices, the Employer's Requirements, the contractor's proposal and the Contract Sum Analysis (excluding any detailed priced of the Contractor) and following additional documents, if any have been issued to the Sub-Contractor on Compact Disc. Any document referred to herein and/or contained on the compact disc may be viewed at the Contractors offices at a conveniently arranged time ..."
"Confidentiality
.1 save in respect of:
.1 for the purpose of complying with any law or court order,.
.2 Confidential Information in the public domain at the time of disclosure by the Contractor to the Sub-Contractor;.
.3 Confidential Information already known to the Sub-Contractor at the time of disclosure by the Contractor to the Sub-Contractor; or.
.4 Confidential Information disclosed by third parties to the Sub-Contractor;
no confidential information shall be disclosed or divulged by the sub-contractor to any third party or used by the Sub-Contractor otherwise than for the purposes of the Sub-Contract without the prior written approval of the Contractor ...
.2 The expression 'Confidential Information' shall mean all literature, drawings, designs, plans, details, specifications, schedules, reports, calculations, cost plans budgets, software, computer storage discs, computer printouts, data files, databases, source codes, object codes, estimates, models, photographs, articles or works and any data used to generate any of them, and any other document and the contents of them and any other information given or prepared for or in connection with the Sub-Contract whether created, used or supplied before or after the date of the Sub-Contract, which has the necessary quality of confidentiality including any timetable or programme or contract entered into in relation to the Project."
"Relationship of Sub-Contract Documents
If any conflict appears between the Conditions and/or the Appendix and/or the Numbered Documents and/or the Special Conditions the foregoing shall take precedence in the following order:-
.1 the Articles of Agreement,
.2 the Appendix,
.3 the Conditions,
.4 the Special Conditions,
.5 the Numbered Documents."
"5.1 The Sub-Contractor shall:
.1 observe, perform and comply with all the provisions of the Contract on the part of the Contractor to be observed, performed and complied with so far as they relate and apply to the Sub-Contract Works (or any portion of the same). Without prejudice to the generality of the foregoing, the Sub-Contractor shall observe, perform and comply with the following provisions of the Contract: clauses 6, 9 and 34; and
.2 Indemnify and save harmless the Contractor against and from:
.1 any breach, non-observance or non-performance by the Sub-Contractor or his servants or agents of any of the provisions of the Contract insofar as they relate and apply to the Sub-Contract; and
.2 any act or omission of the Sub-Contractor or his servants or agents which involves the Contractor in any liability to the Employer under the provisions of the Contract insofar as they relate and apply to the Sub-Contract;
.2A any act or omission of the Sub-Contractor or his servants or agents which prejudices or leads to diminution or loss of any rights, entitlements or benefits of the Contractor under the Contract as they relate and apply to the Sub-Contract; and
.3 any claim, damage, loss or expense due to or resulting from any negligence or breach of duty on the part of the Sub-Contractor, his servants or agents (including any wrongful user by him or them of the scaffolding referred to in the Sub-Contract or other property belonging to or provided by the Contractor).
5.2. Nothing contained in the Sub-Contract Documents shall be construed so as to imply any liability on the Sub-Contractor in respect of any act, omission or default on the part of the Employer, the Contractor, his other sub-contractors or their respective servants or agents nor create any privity of contract between the Sub-Contractor and the Employer or any other sub-contractor."
"When the Contractor gives written notice of dissent under clause 14.1 practical completion for all the purposes of this Sub-Contract will be deemed to have taken place on such date as may be agreed or, if the parties fail to agree, as may be determined by the Adjudicator. Failing such agreement or determination practical completion will be deemed to have taken place on the date of practical completion of the Works as certified by the Employer's Agent in accordance with clause 16 of the Contract and 'practical completion' of the Sub-Contract Works for the purposes of the Sub-Contract shall mean either the date notified by the Sub-Contractor under clause 14.1, the date agreed between the Contractor and Sub-Contractor pursuant to clause 14.2, the date determined by the Adjudicator pursuant to clause 14.2 or failing such determination the date of practical completion of the works under the Contract as appropriate."
"The contractor will so far as he lawfully can at the request and cost, if any, of the Sub-Contractor obtain for him any rights or benefits of the Contract so far as the same are applicable to the Sub-Contract Works but not further or otherwise."
"Project Agreements
The Subcontractor may, from time to time, be allowed access to or have been supplied with copies of agreements now or hereafter entered into between the Employer and/or the Contractor and third parties, or between third parties (including those identified in clauses 41, 41A, 41B and 41.1.15) which affect the Employer and/or the Contractor, or further information concerning the Project, including funding agreements, security agreements, shareholder agreements, consultancy agreements, planning agreements, Statutory Agreements, and agreements for lease or sale. Subject to the Sub-Contractor having had access to or receiving copies of such agreements or information (or such parts of the same as shall be material) and to the extent that such agreements or information relate to or affect the performance of, directly or indirectly, the Sub-Contract Works including any design of the Sub-Contract Works for which the Sub-Contractor is responsible:
.1 the Sub-Contractor shall at all times so perform its duties and obligations under the Sub-Contract having due regard to such information and so as not to, by any act or omission, cause or contribute towards a breach or act or omission of default on the part of the Contractor and/or the Employer under such third party agreements.
.2 the Sub-Contractor shall comply with any and all procedures set out in such third party agreements requiring liaison, consultation and/or submission of plans and/or proposals for approval by third parties.
.3 except in relation to agreements between the Contractor and such statutory undertakers, to the extent such agreements or information were not available to the Sub-Contractor until after the Base Date and such performance or compliance constitutes a Variation, the Sub-Contractor shall be entitled to claim an extension of time and an adjustment to the Sub-Contract Sum in accordance with clause 4.6."
Part 3. The Present Proceedings
"1. On a true construction of the sub-contract between Multiplex and Honeywell dated 27th May 2004, Appendix Part 1 of the Articles of Agreement confers on Honeywell the right to view at a conveniently arranged time the main contract ('Main Contract') between Multiplex and Wembley National Stadium Limited ('WNSL').
2. Honeywell's right to view the main contract described in paragraph (a) above extends to any variations thereof irrespective of whether such variations are formally described as such).
3. The completion agreement entered into between Multiplex and WNSL on or about 19th October 2006 is presumed to vary the terms of the main contract.
4. Honeywell is entitled under the sub-contract to view the completion agreement described above."
(i) Multiplex is given an extension of time for completion of the stadium apparently to 1st June 2006.
(ii) Multiplex cannot claim any further extension of time in respect of events preceding the Settlement Agreement. Thus the extension of time mechanism in the main contract is superseded.
(iii) Multiplex will receive a substantial bonus payment if the stadium is completed in time for the FA Cup final on 19th May 2007.
(iv) The obligations as to time in the main contract are replaced by a new set of obligations as to time for completing the remaining works.
(i) Under the sub-contract does Honeywell have a continuing right to inspect the main contract?
(ii) If so, does that right of inspection extend to the Settlement Agreement?
(iii) If so, is Honeywell entitled to obtain copies of the Settlement Agreement?
Part 4. Under the Sub-Contract Does Honeywell Have a Continuing Right to Inspect the Main Contract?
"The recital of an agreement does not create a covenant where there is an express covenant to be found in the witnessing part relating to the same subject matter."
Part 5. If So, Does That Right of Inspection Extend to the Settlement Agreement?
(i) The terms of the main contract in its current form are of importance to the sub-contractor for many reasons. It can be seen from the provisions which I have read out that the main contract and sub-contract are linked in a variety of ways. For example, the terms of the main contract are relevant to determining when practical completion has been achieved under clause 14. Also they determine benefits to which the sub-contractor is entitled under clause 22. They are highly relevant to quantifying the sub-contractor's liability, if the sub-contractor is in delay or is otherwise in breach of contract. And so forth.
(ii) Accordingly, the sub-contractor has a legitimate interest in inspecting the current version of the main contract. On the other hand, the sub-contractor has no interest in inspecting the historic, outdated version of the main contract because (a) he has already examined and discussed that document and (b) he already possesses the text of that document on compact disc. (See recital 4 and paragraph 3 of Part 1 of the Appendix).
(iii) The phrase "any document referred to herein" in paragraph 3 of Part 1 of the Appendix must add something to the phrase "and/or contained on the compact disc". In my judgment, what that phrase adds is a reference to future versions of the main contract which, by definition, cannot be contained on the compact disc previously provided.
(iv) It can be seen from clause 1.3 of the Sub-Contract Conditions that the reference to "Employer's Requirements" in the inspection clause comprises not only the Employer's Requirements identified in the main contract, but also all post-contract amendments to those Employer's Requirements. In such circumstances, it would be bizarre to treat the inspection clause as excluding any amendments which might be made to the main contract itself.
(v) In order to maintain his purist approach to the inspection clause, Mr. Thomas is forced to postulate certain implied terms permitting Honeywell to inspect amendments to the main contract, when the need arises. When pressed in argument, Mr. Thomas said that clause 14 of the Sub-Contract Conditions is supplemented by an implied term entitling Honeywell to be informed about amendments to the main contract, when relevant. Likewise, said Mr. Thomas, clause 22 is supplemented by an implied term requiring Multiplex to inform Honeywell of amendments to the main contract, generating benefits in which the sub-contractor might share. This approach is not a convincing one. If the inspection clause is interpreted in a sensible and reasonable fashion, the need for such elaborate implied terms disappears.
Part 6. If so, is Honeywell entitled to obtain copies of the Settlement Agreement?
Part 7. Conclusion