![]() |
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | |
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Landfast (Anglia) Ltd. v Cameron Taylor One Ltd. [2008] EWHC 343 (TCC) (26 February 2008) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2008/343.html Cite as: 117 Con LR 53, [2008] EWHC 343 (TCC) |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
LANDFAST (ANGLIA) LIMITED |
Claimant |
|
- and - |
||
CAMERON TAYLOR ONE LIMITED |
Defendant |
____________________
6th Floor, 12-14 New Fetter Lane, London EC4A 1AG.
Telephone No: 020 7936 6000. Fax No: 020 7427 0093
DX 410 LDE [email protected]
MR RICHARD WILMOT-SMITH QC and MISS JESS CONNORS (instructed by Cayton & Co Solicitors) for the Defendant
____________________
Crown Copyright ©
MR JUSTICE AKENHEAD :
Background
"24. By reason of Fordham's breach of contract and/or negligence as aforesaid, the site investigation report commissioned did not address the risk of settlement across the site and Landfast was accordingly unaware that a conventional surface and foul water drainage system would not be appropriate and that special measures would need to be taken in respect of the construction of the roads.
25. Landfast prepared costs estimates on the basis of a conventional drainage and road system being suitable and appropriate for the Development Site. In early March 2005 and in reliance upon those estimates reflecting the nature of the work to be undertaken, Mr Robert Curry on behalf of Landfast made an offer of £1.5 million to the Turners for the Development Site, which Turners accepted.
26. By reason of the matters aforesaid, Landfast's estimates did not reflect the construction costs of an appropriate surface and foul water drainage system and/or stabilisation costs such that allowance was not made for the appropriate works to address settlement across the Development Site. Landfast therefore lost the opportunity to negotiate for and secure the Development Site at a lower price namely one that reflected the site conditions.
Particulars of Loss
Had Landfast been aware that a conventional surface and foul water drainage system was not appropriate and that either ground stabilisation works or a vacuum system would be required it would have offered £1,000,000 for the Development Site, reflecting the additional cost of a vacuum system and additional stabilisation works. Landfast will say that in all the circumstances that applied at the material time there was a 100% chance that the Turners would have accepted this lower offer. As assignee of the rights previously held by Landfast, Anglia claims the full value of the lost chance, namely £500,000."
"By no later than 18th June 2004 Fordham were aware that Anglia was to proceed with the development in Landfast's place. Fordham well knew at or about this time that Anglia was a single purpose vehicle and that Anglia had obtained bank funding to undertake the development. It was also envisaged by the parties that the completion of the first plots would take place in March 2006."
"Further or in the further alternative it is averred that Fordham owed Anglia a duty of care to exercise all due professional skill and care in the performance and provision of its services to Anglia."
"On 24 June 2004 Anglia entered into a sale contract with the Turners for the development site for the total contract price of £1,500,000 unaware that a conventional surface and foul water drainage system would not be appropriate; further or alternatively, that special measures would need to be taken in respect of the construction of the roads; further or in the further alternative, that additional ground investigation works would need to be undertaken."
"By reason of the matters aforesaid Anglia has suffered loss and damage.
Particulars of Loss
Anglia claims the diminution in value between the value of the Development Site on the basis that a conventional road and drainage system could be constructed - as maintained by Fordham's - and the true condition of the Development Site had the true nature of the ground conditions and the consequent impact on construction methods been known. Anglia assesses the diminution in value as £1,115,000, being the difference between the price at which Anglia agreed to purchase the Development Site (£1,500,000) and the value of the Development Site had the true ground conditions been known and understood (£385,000)."
"In order to mitigate its loss, Anglia … attempted to secure additional financing for the development rather than surrendering its interests in the development to the bank. In anticipation of an agreement being reached with a new investor, Anglia was advanced funds through a company called Bastia Investments Limited totalling £850,000 with interest being charged at 3% per month. This agreement was not executed and the demand for repayment of the sums advanced and interest was made on 6 February 2006".
"(a) Additional Management time and professionals fees: £234,558.75
Robbett Limited: £126,252.75
Anglia claims the costs of employing Robert Curry through his management company incurred in his dealing with the defective design, evaluation and consideration of remedial schemes and works and management of the Development that he would not otherwise have been involved in and but for the failure of Fordham's design and the costs of employing him to secure alternative financing for the project when the bank withdrew support due to the discovery of the defective design and the additional forecast costs.
Holmes & Hills
Anglia claims its solicitors costs of advising upon and drawing up contracts and agreements for alternative financing when the bank withdrew support due to the discovery of the defective design and the forecast additional costs.
(b) Increased costs of financing: £493,235"
The principles to be applied
"19. The Master divided his approach into consideration of dismissing the claim under CPR 3.4(2) and dismissing the claim under CPR 24. In agreement with counsel for the defendant and with Mr Martin Mann QC and Mr Stuart Adair, who appeared for Mr Chan, it seems to me that ultimately the question is singly whether or not the claim stands any real chance of success. Whether one approaches that issue under one or other of the CPR Rules does not seem to me to matter – a view which seems consistent with the approach in the House of Lords in The Three Rivers case.
20. Ultimately it is normally wrong that a claim should be allowed to proceed if the court can decide at an interlocutory stage that it stands no chance of success. Equally, however, if the court considers that the claim, though very weak, stands a chance of success, it is not consonant with basic principles of English justice or indeed, as I see it, with Human Rights Law, for a party seeking to pursue such a claim to be barred from proceeding with it. However much one may seek to apply the rules of proportionality, it is not and cannot be the court's function to stifle a claim merely because it looks very weak and unlikely to succeed.
21. Quite apart from principle, everyone concerned with litigation, whether a solicitor, a barrister or a judge, has seen cases which at an interlocutory stage look remarkably weak (or where defences look remarkably weak) where after disclosure, exchange of witness statements and cross-examination and full argument the case (or the defence) succeeds. Furthermore, it is important to bear in mind the well-established principle that it is not the function of a court at an interlocutory [stage] to carry out a mini trial.
44. I accept that the court should be slow to permit a claim to proceed beyond an interlocutory stage where it involves the hope that something will turn up. None the less, as again is clear from the speeches from Lord Hope and Lord Hutton in the Three Rivers case, each interlocutory application to dismiss a claim on the basis that there is no evidence to support it must be judged by reference to the particular facts of the case."
Head 1 – Lost Opportunity
"What was assigned was a cause of action and not an assignment of loss. The assignment included the remedy in damages which was not limited to the loss suffered as at the date of the accrual of the cause of action or as at any particular time thereafter."
Reference is made there to Paragraph 41 in the judgment of Mummery LJ with which Rix LJ and Peter Smith J agreed.
"Underlying all these cases can be heard the drumbeat of a constant theme which could possibly be described as ubi jus ibi remedium – the maxim that, where there is a right, there is a remedy. But it could also be said that the courts are anxious to see, if possible, that where a real loss has been caused by a real breach of contract then there should, if at all possible, be a real remedy which directs recovery from the defendant towards the party which has suffered the loss. In the case of property development where it is readily contemplated that a party which prepares the development will transfer the fruits of his work to one or more partners or successors, there is a particular need for some such solution."
Head 2 – Diminution in Value
Head 3 – Financing and Associated Costs
Conclusion