![]() |
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | |
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Letchworth Roofing Company v Sterling Building Company [2009] EWHC 1119 (TCC) (05 May 2009) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2009/1119.html Cite as: [2009] EWHC 1119 (TCC), [2009] CILL 2717 |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
133-137 Fetter Lane London EC4A 1HD |
||
B e f o r e :
____________________
LETCHWORTH ROOFING COMPANY |
Claimant |
|
- and - |
||
STERLING BUILDING COMPANY |
Defendant |
____________________
THE DEFENDANT did not appear and was not represented
____________________
Crown Copyright ©
MR. JUSTICE COULSON:
"Letchworth, however, do not wish for any party to be disadvantaged by the Christmas holiday and will thus grant an extension to the date when the adjudicator must make his decision."
The adjudicator noted this concession in his letter of 15th December 2008, written to both parties, in which he set out a proposed timetable. He said that he would "take this into account if it proves necessary".
"In order to allow sufficient time for SBD to respond I will allow their response time to be extended until close of business on Wednesday, 7th January 2009 thus allowing them this week and a further three days into week commencing 5th January 2009.
In order to accommodate this I will reset the date for the decision to 19th January 2009, i.e. plus one week (although I would reserve my position on the further week allowable between referring party and adjudicator)".
"Following the Christmas/New Year break I would like to confirm the present position as to timetable as my previous directions 1 and 2.
1. SBD to respond by close of business Wednesday, 7th January 2009.
2. Decision issued on Monday, 19th January 2009."
a) The 28/42 Days
(a) The claimant's referral notice made plain that it would agree to an extension because of the intervening holiday period.
(b) On three separate occasions the adjudicator indicated that he would avail himself of a one week extension to the 28 days (see above), so as to produce a decision on 19th January. The claimant did not dispute or object to that course. Indeed, the claimant would not have been in a position to do so, having earlier indicated that it would not object to an extension.
(c) As I put to Mr. Hussain during the course of argument this afternoon, if the boot had been on the other foot, and the claimant had not liked the adjudicator's decision and so claimed that it was a nullity because it had been produced out of time, I would have had no hesitation, on these facts, in concluding that the claimant was estopped from taking such a point. The claimant had acquiesced in the timetable set out by the adjudicator. To that extent this case would then have been indistinguishable from AC Yule & Son v. Speedwell Roofing & Cladding Limited [2007] EWHC 1360 (TCC), where the claimant was estopped from denying that the adjudicator had been granted the necessary extension.
b) The Dispute And The Alleged Breach Of Natural Justice
"152. Whilst we will demonstrate below that there is no valid withholding notice in place and as such no monies can be deducted, notwithstanding Sterling have failed to issue a valid withholding notice, the claim against Letchworth fails in its entirety, and is a total fabrication.
153. We have requested that the adjudicator still considers the merits of the Sterling claim, even if he determines no withholding notice is in place, and we ask here for Sterling to consent to this request, which is made to benefit the conclusion of the account after the decision."
"I consider, therefore, that Ms. McCredie was right to submit that if the adjudicator had considered the defence and decided, even if wrongly, that it could not succeed in the absence of a withholding notice, that would be a decision within his jurisdiction and would not be one which this court could review on an enforcement hearing. This is consistent with the judgment of Lord MacFayden in SL Timber Systems Limited v Carillion Construction Limited [2001] BLR 516, to which she referred me, at paragraph 23."
I respectfully agree with that conclusion.