[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Edmond Stern Settlement, Trustees of v Levy (t/a Simon Levy Associates) [2009] EWHC 14 (TCC) (13 January 2009) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2009/14.html Cite as: [2009] NPC 6, [2009] Lloyd's Rep 345, [2009] 1 Lloyd's Rep 345, [2009] EWHC 14 (TCC) |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
THE TRUSTEES OF THE EDMOND STERN SETTLEMENT |
Claimants |
|
- and - |
||
SIMON LEVY ( trading as Simon Levy Associates) |
Defendant |
____________________
Kim Franklin (instructed by Berrymans Lace Mawer) for the Defendant
Hearing dates: 18 December 2008
____________________
Crown Copyright ©
Mr Justice Akenhead:
Introduction
The Background
"If one of the consequences of that might, in the event, mean that all the fees were paid long before the work was completed, then so be it".
He rejected the charge of fraudulent invoicing made by the Stern Trustees. It followed that he found that Mr Stern's termination of Mr Levy's contract was wrongful.
"1. The [Stern Trustees are] to identify any issues as to quantum by 12th October 2007.
2. [Mr Levy] is to respond to the Respondent's case on quantum by 26th October 2007.
3. The Arbitrator is to decide any dispute on a documents-only basis (unless otherwise ordered) with a view to issuing an Award on quantum by 14th December 2007…"
The Award of 13 October 2008
"4. The submissions filed on both sides are voluminous and detailed, and refer me to a number of cases, but in the end both sides admitted that there is no case law directly in point, and I must, therefore, apply simple logic to the issues involved. What I must remember here is that in October 2004 the contract between Mr Levy and Mr Stern was, as I have already decided, wrongly terminated by Mr Stern. That gave rise immediately to the right for Mr Levy to claim damages for breach of contract, and that right of action accrued at that point. That claim for damages consisted of two elements, the first being a claim in respect of outstanding fees for work already done under the Contract, and the second being a claim for general damages in respect of the breach of contract, and at all material times the claim was pleaded and conducted on that basis. In my view both of those parts of the claim crystallised at the point of breach, and events, such as the agreeing of a later final account with the builder, could not affect the quantification of those rights. It is true that had the Contract continued to full term, and there had been a final account to which Mr Levy was a party, then under the terms of the Contract there might have been an adjustment of some sort to Mr Levy's final entitlement. But, in the nature of the events which happened, that end result could never take effect, and Mr Levy ceased to be a party to the transaction at the point when his Contract was terminated. I am therefore firmly of the view that the quantification of damages in respect of outstanding fees can only be based on the evidence which was adduced at the original hearing as interpreted by me in my Award No. 1. It follows, therefore, that the outstanding quantum in respect of unpaid fees must be based on the Scott Schedule as amended during the course of the hearing and subject to my deletions of the claim in respect of the cobbles.
5. It should be possible now for the parties to agree those figures without further guidance from me, but, if necessary, I will consider any applications. That then leaves the question of general damages. The Claimant, in Paragraph 10 of the letter of 28 August, 2008, submits that the only evidence which I have heard on this question was the evidence presented at the hearing by Mr Jonathan Russell, a forensic accountant, and the Respondent called no evidence to contradict that evidence, so that, in default of agreement, I ought to base my assessment of quantum on that evidence. If the parties are not able to agree a figure within 28 days of the delivery of this Award, then I will permit the Respondent to make further submissions on the issue of quantum within 28 days thereafter, but, subject to further applications, I am not minded to have an oral hearing on the point."
"I therefore award, declare and direct as follows:-
1. Leave for the Respondent to adduce further evidence on quantum is refused.
2. Leave to amend the Defence is refused.
3. Liberty to apply.
4. Costs are reserved."
Applicable Principles
"(3) Leave to appeal shall be given only if the court is satisfied –
(a) that the determination of the question will substantially affect the rights of one or more of the parties,
(b) that the question is one which the tribunal was asked to determine,
(c) that, on the basis of the findings of fact in the award –
(i) the decision of the tribunal on the question is obviously wrong, or
(ii) the question is one of general public importance and the decision of the tribunal is at least open to serious doubt, and
(d) that, despite the agreement of the parties to resolve the matter by arbitration, it is just and proper in all the circumstances for the court to determine the question."
"(a) The identification of a true question of law, as opposed to complaint about the Arbitrator's findings of fact masquerading as a point of law;
(b) that the Arbitrator was obviously wrong on the relevant point of law or, if it is a point of general or public importance, that the Arbitrator's decision was at least open to serious doubt;
(c) that the point of law substantially affects the rights of the parties in the arbitration (see The Northern Pioneer [2003] 1 Lloyd's Rep 212);
(d) that it is just and proper for the court to determine the point of law (see Kershaw Mechanical Services Ltd v Kendrick Construction Ltd [2006] EWHC 727 (TCC))."
"(1) A party to arbitral proceedings may … apply to the court challenging an award in the proceedings on the ground of serious irregularity affecting the tribunal, the proceedings or the award. …
(2) Serious irregularity means an irregularity of one or more of the following kinds which the court considers has caused or will cause substantial injustice to the applicant –
(a) failure by the tribunal to comply with section 33 (general duty of tribunal) …"
"(a) act fairly and impartially as between the parties, giving each party a reasonable opportunity of putting his case and dealing with that of his opponent …"
The Section 69 Application
"Both of those parts of the claim crystallised at the point of breach, and events, such as the agreeing of a later final account with the builder, could not affect the quantification of those rights."
Mr Levy's Counsel argued that there was no question of law decided. In effect all that the Arbitrator was doing was ruling upon a late application to amend which he refused. It was a procedural and discretionary decision which does not as such, she argued, give rise to a question of law.
Serious irregularity
"… the quantification of damages in respect of outstanding fees can only be based on the evidence which was adduced at the original hearing as interpreted by me in my Award No. 1."
Decision