![]() |
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | |
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Carillion JM Ltd v Bath & North East Somerset Council & Anor [2009] EWHC 166 (TCC) (05 February 2009) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2009/166.html Cite as: [2009] TCLR 5, [2009] EWHC 166 (TCC) |
[New search] [Printable RTF version] [Help]
TECHNOLOGY AND CONSTRUCTION
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
CARILLION JM LIMITED |
Claimant |
|
- and - |
||
BATH AND NORTH EAST SOMERSET COUNCIL and NICHOLAS GRIMSHAW & PARTNERS LIMITED |
Defendant Third Party |
____________________
Mr David Friedman QC and Ms Rachael Ansell (instructed by Taylor Wessing ) for the Defendant
Mr Richard Coplin (Instructed by CMS Cameron McKenna) for the Third Party
Hearing date: 31st January 2009
____________________
Crown Copyright ©
Mr Justice Coulson :
Introduction
Preliminary Issues/ General
The Repudiation Issues
a) On 24.3.05 NGP, on behalf of B&NES, instructed CJM, by Architect's Instruction 133, to carry out a lengthy list of works (including remedial works in respect of the pool paint and the waterproofing) and accompanied that instruction with a notice under clause 4.1.2 of the contract, requiring compliance within 7 days. Whether deliberately or not, these documents were issued by NGP just before the Easter holiday shutdown.
b) On 4.4.05, CJM replied, complaining about the short space of time in which they were being asked to carry out the work and taking a large number of other points about the detail of the works being instructed.
c) On 5.4.05, B&NES replied, requiring CJM to reply by 5pm on 6.4.05 as to whether it was their intention to comply with AI 133 or not.
d) On 6.4.05, CJM replied referring, amongst other things, to "an attempted holiday period ambush"
e) On 8.4.05, B&NES wrote to CJM purporting to accept what they alleged was CJM's wrongful repudiation of the contract. The letter referred to CJM's reaction to the issue of AI 133, but also said that they were "driven to the conclusion by this latest incident (when taken with earlier non-compliance with the contract) that Mowlem does not regard itself as bound by the contract." The letter then went on to identify numerous alleged breaches of the contract, some very general in nature, but others relating to specific, dated events. The letter required CJM to vacate the site.
f) On the same day, CJM wrote a lengthy letter to NGP dealing with AI 133.
g) On 11.4.05, CJM purported to accept B&NES lengthy letter of 8.4.05 as being itself repudiatory, because, amongst other things, it had required them to vacate the site.
The Proposed Preliminary Issues
"1.1. Whether B&NES affirmed the building contract by the issue and service of AI 133 and the clause 4.1.2 notice each dated 24.3.05;
1.2. If the answer is 'yes' whether (1) CJM's response by letters dated 4th and 6th April 2005 and/or (2) the alleged subsequently disclosed defects (if true) constituted a repudiation of the contract which B&NES was entitled to accept by its termination letter of 8.4.08;
1.3. If the answers to (1) and (2) above are no, whether B&NES' letter of 8.4.05 was itself repudiatory; and so accepted by CJM's letter of 11.4.05."
a) General
b) Particular
" the court should not adopt an unduly technical approach to deciding whether the injured party has affirmed the contract and should not be willing to hold that the contract has been affirmed without clear evidence that the injured party has indeed chosen to go on with the contract notwithstanding the other party's repudiation. In my view, the court should generally be slow to accept that the injured party has committed himself irrevocably to continuing with the contract in the knowledge that if, without finally committing himself, the injured party has made an unequivocal statement of some kind on which the party in repudiation has relied, the doctrine of estoppel is likely to prevent any injustice being done."
It seems to me that, for the reasons that I have given, it would be "unduly technical" to consider these issues without hearing evidence as to what the chief protagonists on each side thought about the pre-24.3.05 events, their understanding of the effect of AI 133 and the notice of the same date, and any other matters which may be relevant to the alleged decision to "go on with" the contract.
Should B&NES Be Allowed To Call Two Expert Architects?