[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Dalkia Energy and Technical Services Ltd v Bell Group UK Ltd [2009] EWHC 73 (TCC) (21 January 2009) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2009/73.html Cite as: 122 Con LR 66, [2009] EWHC 73 (TCC) |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
133-137 Fetter Lane, London, EC4A 1HD |
||
B e f o r e :
____________________
DALKIA ENERGY AND TECHNICAL SERVICES LIMITED |
Claimant |
|
- and - |
||
BELL GROUP UK LIMITED |
Defendant |
____________________
12-14 New Fetter Lane, London EC4A 1AG
Telephone No: 020 7936 6000. Fax No: 020 7427 0093
Email: [email protected]
MR MICHAEL BLACK QC (instructed by Nabarro LLP) appeared for the Defendant
Hearing Dates: 19th and 20th January 2009
____________________
Crown Copyright ©
MR JUSTICE COULSON:
A. BACKGROUND
a) The Bell standard terms and conditions were not incorporated into the contract between the parties.
b) If they were, the Bell standard terms and conditions did not comply with section 108 of the 1996 Act, and so therefore the Scheme applied instead.
c) The adjudicator did not have the jurisdiction to decide the dispute referred to him, principally because:
i) He had been appointed under the Bell standard terms and conditions and not the Scheme;
ii) The approach to the RICS took place before the provision of the notice of adjudication to Dalkia;
iii) The notice of adjudication purported to refer more than one dispute to the adjudicator.
B. SUITABILITY/ABUSE OF THE PROCESS
B1 Suitability
B2 Abuse of Process
"The Way Forward
For the reasons set out above, Dalkia contends that you lack the jurisdiction to decide the dispute referred to you by Bell and respectfully invite you to withdraw forthwith.
Pending the outcome of your investigations into your own jurisdiction, Dalkia strictly reserves its position as to participation in the adjudication thereafter. However, for the avoidance of doubt, at present, Dalkia is not prepared to sign up to your terms of appointment.
In the event that you do decide that you have jurisdiction, this letter is intended to put you on notice that, should Dalkia wish to participate further, such participation of course being strictly without prejudice to the fact that you have no such jurisdiction, Dalkia will advance a robust defence of set-off and a substantial counterclaim."
"We trust that you are now in receipt of our fax of yesterday's date in which we challenge your jurisdiction to decide the dispute before you. We invite you to consider these challenges and inform us of your conclusions in this regard as soon as practicable.
Until you have ruled accordingly upon your jurisdiction (and it remains our view that you have no option but to withdraw), we consider that it is premature to order directions in relation to the dispute.
As you are aware, we are currently reserving our position with regard to participation in the adjudication, but, should you decide that you have jurisdiction to decide the dispute and should we decide to participate, for the reasons set out in our letter of yesterday's date we would request that time be extended for the service of a response until mid-January 2009."
"Now that you have received our submissions in reply, we look forward to receiving your rulings as to your jurisdiction as soon as is practicable. Should you rule that you have jurisdiction, Dalkia hereby requests that the time for service of a response be extended beyond 22nd December 2008 and that Bell be asked to properly reconsider its refusal to extend the time for the communication of your decision."
This last was a reference to the adjudicator's original order that Dalkia respond to the substantive matters in issue in the adjudication by 22nd December
"I have considered the above submissions and I conclude that the Issue for me to decide upon at this stage is one of threshold jurisdiction. That is, whether despite the opposing arguments of the parties concerning jurisdiction, I consider that I nevertheless have jurisdiction to move the matter forward, although not being in a position at this point to decide on the matters contended by each side.
I conclude that I do have jurisdiction to proceed at this stage and set out below my reasoning in respect of the main issues raised."
The adjudicator then went through and rejected each of Dalkia's propositions on jurisdiction. In so doing, he expressly found that the Bell standard terms and conditions were incorporated into the contract between the parties.
C. THE COURT'S JURISDICTION
C1 Introduction
C2 The Parties' Agreement
a) Dalkia reserved their position at the outset in the letter of 16th December.
b) Dalkia never resiled from that reservation and repeatedly said that the adjudicator did not have the necessary jurisdiction.
c) Dalkia never expressly agreed to be bound by, or comply with, the adjudicator's ruling on jurisdiction.
C3 The Adjudicator's Decision As To The Bell Terms and Conditions
D. WERE BELL'S STANDARD TERMS AND CONDITIONS INCORPORATED?
D1 The Relevant Facts
"We thank you for your valued enquiry and have pleasure in providing the following quotation, as all Bell Group standard terms and conditions …"
"Any contract between Bell Group UK ('the company') and any of its customers ('the customers') for the supply of work and materials ('the work' and 'the materials') shall incorporate these terms and conditions, which shall prevail over any other terms and conditions contained in the customer's order form or offer, or in any other oral or written intimation which shall not be incorporated into any contract made by the company unless otherwise agreed in writing by the company."
a) The form was required to be completed by the supplier (in this case Bell);
b) The form was not completed by Bell until after the contract had been agreed;
c) Bell were never chased up to complete the form prior to the conclusion of the contract, and it was not mentioned in the correspondence/emails which both sides agree constituted the contract in writing;
d) The construction contract was therefore agreed in May 2007 without the form having been completed and without any reference either to the form or the Dalkia terms;
e) The May contract did not include or incorporate the Dalkia terms.
"I have attached the Footbridges, East and West Zone 1 schedules for your information. These sheets now show a breakdown of all the services required by Central Trains and identify the total works we would require Bell Group to complete. The total of your works is approximately £403K, although this includes Dalkia's 10% margin, which you included in your rates. I will leave you to resubmit these worksheets back to me with the removal of our margin so we can contract you for the correct value of the works. As discussed, for commercial reasons only platform markings will be delivered via a separate contractor."
D2 The Parties' Submissions
D3 Analysis
E. THE APPOINTMENT OF THE ADJUDICATOR
E1 Introduction
"12.1 Either party to the contract may give notice ('notice of intention to refer to adjudication') of its intention to refer a dispute, difference or question arising under, out of or relating to the contract for adjudication at any time and, within seven days of such notice of intention to refer to adjudication, refer the same by notice of referral ('notice of referral') to the adjudicator specified in the appendix hereto ('the appendix'). The party referring such dispute shall be called 'the referrer', and the party responding shall be called 'the respondent', collectively referred to as 'the parties'…
12.3 The adjudicator to decide the dispute or difference shall be either one of the individuals named in paragraph 1 of the appendix, or an individual agreed by the parties, or, on the application of either party, an individual to be nominated as the adjudicator by the person named in paragraph 2 of the appendix ('the nominator'), provided that, where either party has given notice of intention to refer to adjudication then: …
12.3.3 Any application to the nominator must be made with the object of securing appointment of and referral of the dispute or difference to the adjudicator within seven days of the notice of the date of the notice of intention to refer to adjudication.
12.4 Upon the appointment of the adjudicator, the parties shall comply with all the directions which he may issue for the purposes of considering the facts and issues in the dispute and so that the adjudicator shall notify his decision to the parties not later than 28 days from the date of the referral to him, or such longer period as is agreed by the parties after the dispute has been referred and the adjudicator may extend the period of 28 days by up to 14 days with the referrer's consent. The adjudicator's decision shall nevertheless be valid if issued after the time allowed. The adjudicator's decision shall state how the cost of the adjudicator's fee shall be apportioned between the parties and whether one party is to bear the whole or part of the reasonable legal and other costs and expenses of the other party relating to the adjudication. It shall be a condition precedent to the appointment of an adjudicator that he shall notify the parties that he will comply with this condition and its time limits."
"1. Under condition 12 the adjudicator shall be such person as the customer or company choose by mutual agreement in writing or, failing such agreement, such other person as may be chosen by the President, or a Vice-President, or Chairman or a Vice-Chairman of the Royal Institution of Chartered Surveyors at the request of either the customer or the company."
……
(c) require the adjudicator to reach a decision within 28 days of referral or such longer period as is agreed by the parties after the dispute has been referred;
(d) allow the adjudicator to extend the period of 28 days by up to 14 days, with the consent of the party by whom the dispute was referred; …"
Clause 12.4 of the Bell standard terms and conditions replicated both the 28-day mandatory period and the possible 14-day extension with the referring party's consent. But the clause went on to provide (in the passage identified in bold above) that the decision "shall nevertheless be valid if issued after the time allowed". It is Dalkia's case that, in providing such an open-ended extension to the adjudication time limits, clause 12.4 was not in accordance with the 1996 Act.
E2 Two Decisions of His Honour Judge Havery QC
E3 Analysis
E4 Alternative Position
F. COMPLIANCE WITH THE BELL STANDARD TERMS AND CONDITIONS
F1 Introduction
F2 Agreement First?
F3 Notice Prior to Application to RICS
G. JURISDICTION - MORE THAN ONE DISPUTE
"During the course of a construction contract many claims, heads of claim, issues, contentions and causes of action will arise. Many of these will be, collectively or individually, disputed. When a dispute arises, it may cover one, several or many of one, some or all of these matters. At any particular moment in time it will be a question of fact what is in dispute. Thus, the 'dispute' which may be referred to adjudication is all or part of whatever is in dispute at the moment that the referring party first intimates an adjudication reference. In other words, the 'dispute' is whatever claims, heads of claim, issues, contentions or causes of action that are then in dispute which the referring party has chosen to crystallise into an adjudication reference."
H. CONCLUSIONS