[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Banner Holdings Ltd v Colchester Borough Council (No 2) [2010] EWHC 655 (TCC) (19 March 2010) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2010/655.html Cite as: [2010] EWHC 655 (TCC) |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
133- 137 Fetter Lane London EC4A 1HD |
||
B e f o r e :
____________________
BANNER HOLDINGS LIMITED |
Claimant |
|
- and - |
||
COLCHESTER BOROUGH COUNCIL |
Defendant |
|
No 2 |
____________________
Mr Robert Clay (instructed by Messrs Anthony Collins Solicitors) for the Defendant.
____________________
Crown Copyright ©
Mr Justice Coulson :
'If the total of the following sums (hereafter called "the third amount") exceeds the second amount determined in accordance with Condition 57 (2) (Consequences of Determination by Employer), the Employer shall be liable to pay the Contractor the amount of the excess. If the second amount exceeds the third amount, the Contractor shall be liable to pay the Employer the amount of the excess. The individual sums are –
(a) the value of all the work carried out in accordance with the Contract up to the date of determination;
(b) the value of any work carried out or other things done in accordance with any direction given under Condition 56 (3) (Determination by Employer);
(c) the value (ascertained on the basis of fair and reasonable prices) of all Things for incorporation brought onto the Site, or in the course of preparation or manufacture off the Site which the Employer elects to keep;
(d) any reasonable sum expended by the contractor because of the determination of the Contract in respect of –
(i) the uncompleted part of any subcontract and other contracts (including those for the hire of plant, services and insurance); and
(ii) any unavoidable contract of employment entered into in connection with the Contract; and
(e) the Contractor's other unavoidable losses or expense directly due to the determination, including without limitation loss of profit on the Contract.'
'28. The revised valuation of the works as at the date of determination, and the presentation of the claim, is the product of an analysis [in relation to which, as Mr Mallins makes clear, privilege is not waived by or on behalf of the Claimant] carried out by the Claimant's independent QS expert, Mr Stuart Whittle, who is a partner in the well known firm of Gardiner & Theobald.
29. Mr Whittle is satisfied that a valuation of the claim in the manner presented in the Response is a proper and valid valuation of the claim in accordance with Condition 58 (4) and (5). Indeed, he has expressed the opinion that it is the best way in which to value the claim.
30. Mr Whittle does not consider that the complaint that the Claimant "treats a stage payment certificate as if it were a valuation" has any validity. He regards it as entirely appropriate to rely upon the certificate dated 23rd March 2009 as a valuation of the works as at the date stated.'