![]() |
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | |
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Ellis Building Contractors Ltd v Goldstein [2011] EWHC 269 (TCC) (18 February 2011) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2011/269.html Cite as: [2011] EWHC 269 (TCC) |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
ELLIS BUILDING CONTRACTORS LIMITED |
Claimant |
|
- and - |
||
VINCENT GOLDSTEIN |
Defendant |
____________________
Marion Smith (instructed by Philip Ross) for the Defendant
Hearing dates: 11 February 2011
____________________
Crown Copyright ©
Mr Justice Akenhead:
The Background
"Please accept this as our Letter of Intent to enter into a Contract with Ellis… to carry out and complete the repair & refurbishment works to Bush Mews…
At this point in time, certain elements of the design are required to be finalised by our directly employed Design Team and in the interim, to establish a Contract Sum we will base this Letter of Intent on Ellis…letter dated 9 February 2009 and letter…dated 17 March 2009 identifying a contract sum of £429,270.28 plus VAT. To this will be added a contingency sum of 10% which gives a Contract sum of £472,197.31 plus VAT…
This letter provides you with the authority to commence all necessary preconstruction works to facilitate the earliest possible commencement date from the date of this letter. These works will be carried out under the specific terms of JCT 2005 Intermediate Building Works Contract, Clause 2.23 Liquidated Damages at the rate of £Nil per week…Date of issue of Interim Certificates as per Contact Particulars 4.6.1 shall state 14 days from date of possession.
In the event of failure to conclude the Contract or either party deciding that the provision of the work should cease for whatever reason, the Employer's total liability will be Ellis… pre-construction costs together with any costs and expenses reasonably and properly incurred together with associated overheads and profit.
In the event that the formal Contract is not prepared prior to commencement, following commencement the parties agree that the works will be carried out under the specific terms of the JCT 2005 Intermediate Building Contract."
This was signed by the parties.
"…we have conducted a periodic review…and are aware that the value of the works is fast approaching the value of that stated in your letter of intent dated 18 June 2009 for a Contact sum of £472,197.31 plus VAT.
Normally this would not be an issue as the letter of intent would have been superseded by the Contact Documents which had the necessary mechanism within them to cater for an increasing contract value. However, for reasons which are unclear to us, these documents are yet to be formally issued and therefore need to bring this matter to your urgent attention.
As we see it there are two options for dealing with this situation:-
1. Issue a further letter of intent to cater for the increase in value of the works.
2. Formally issue the Contract Documents.
We would anticipate that we are currently very close to the contract sum for the works actually carried out on site and have committed orders to various sub-contractors and suppliers that will exceed the value of the letter of intent. We would therefore very much appreciate if you could see your way clear to organising a prompt response to these matters…"
"Further to your letter of intent dated 18 June 2009, we now write to you to extend the authority of the aforementioned letter to expire on the execution of the Contract unless extended again in writing by us.
These works will be carried out under the terms of JCT 2005 Intermediate Building Works Contract, Clause 2.23 Liquidated Damages at a rate of £Nil per week and Clause 6.7 Option C shall apply in respect of insurance. Dates of Interim Certificates as per Contract Particulars 4.6.1 shall state 14 days from date of possession.
In the event of failure to conclude the Contract or either party deciding that the provisions of the work should cease for whatever reason, the Employer's total liability will be Ellis… pre-construction costs together with any costs and expenses reasonably and properly incurred together with associated overheads and profit.
We undertake to pay you the proper and reasonable costs incurred by you in working in accordance with the Drawings, Specification and Instructions issued by [FA] (acting as our Agents) for properly providing services, works, goods and materials for the Authorised Works, in accordance with this letter, providing that our liability to you will be extended by £107,802.69…and will not exceed £580,000…(the "Maximum Amount").
Both parties agree that the works will be carried out under the specific terms of the JCT 2005 Intermediate Building Contract.
Please acknowledge receipt of this letter and confirm the acceptance of its contents by signing the duplicate copy and returning it to us."
"FA issued two copies of the contract documents to [Ellis] for signature prior to being forward to [Mr Conway] for signing. [Mr Conway] is to then return a single signed copy of the contract to [Ellis]. FA requested [Ellis] include the second Letter of Intent prepared within the Contract Documents and forward a copy of this to FA for their records."
The Adjudication
"was concluded through direct negotiations between the parties. These negotiations culminated in a Letter of Intent dated 18 June 2009 in the total sum of £429,270.28, to which was added a 10% contingency making the total value of the Letter of Intent £472,197.31…"
"The version of the IBC in force at that time [18 June 2009] was the version containing Revision 1 2007 with Attestation Update. This version of the IBC came into effect on 1 April 2007. This can be verified from the inside cover of the contract prepared by the Architect and handed to Ellis at the site meeting on 30 June 2010. However, should Mr Goldstein seek to challenge this and rely on the earlier and original version of this Contract, which is accepted by the Adjudicator, it matters not because all the relevant clauses and provisions relied upon by Ellis in this adjudication are common to both forms."
Ellis go on to seek to undermine the argument that the cap in the First Letter of Intent applied by expressly referring in Paragraph 16 to the Second Letter of Intent which extended the original figure up to £580,000. Paragraph 20 states this:
"The position regarding the contract documents developed on 30 June 2010, when at a site meeting held on site on that date, the Architect issued two copies of the contract documents to Ellis for signature. These documents, one signed by Ellis were to be sent to Mr Andrew Conway who was representing Mr Goldstein. Mr Goldstein would then sign them and forward one copy of the executed contract documents to Ellis. The minutes of this meeting are attached and item 2.20 refers."
Paragraph 21 goes on to invite attention to the attached copy of the contract which apparently identified the original sum of £472,197.31, albeit that this was not subject to any cap but was subject to the normal type of adjustments, for instance in for variations and prolongation allowed by the standard IBC contract. The Referral goes on in detail to explain the quantum claimed and what were said to be the outstanding sums.
"The core of Mr Goldstein's Response is that by a further Letter of Intent signed by both parties and dated 4 May 2010, as the contractual works were reaching an end, the parties agreed that Mr Goldstein's maximum liability to Ellis would not exceed £580,000 (excl VAT); accordingly, Ellis's claims for payment are not to be allowed save to the extent that they do not in aggregate (excluding VAT, and any interest) exceed £580,000."
He accepted at Paragraph 7 that the parties agreed to the incorporation of the IBC, albeit subject to what had been agreed in the Letters of Intent. He argued that, however, the parties never reached or signed agreement to the Contract Particulars in the IBC form.
"(b) the note at paragraph 2.20 of the 30 June 2010 Project Meeting… may record the architects as having issued contracts for execution, and as having asked Mr Conway to return a single signed copy; but there is nothing which records Mr Conway as having formally agreed [so] to do, or to be bound by its terms. In the event, he and Mr Goldstein did not choose to sign a copy of the IBC so as to be bound fully, not only by its standard terms, but also by the parts which had been inserted by Ellis. In any event, there is no doubt that any such signature would have been accompanied by a formal record and insertion of the Maximum Amount which had been agreed in writing between the parties; and
(c) it is not accepted that the parties have conducted themselves as though the contract document produced by Ellis…is in full effect; the parties have conducted their affairs in accordance with the terms of the two Letters of Intent and (in general terms, and save as otherwise amended) the general standard terms of the IBC, but subject (as from 4 May 2010) to the Maximum Amount…"
"The sequence of events was that following the first Letter of Intent dated 18 June 2009, a second Letter of Intent was issued on 4 May 2010…Following this [FA] issued the contract documents at a site meeting on 30 June 2010. Item 2.20 refers as does paragraph 20 of the Referral. Nowhere in these contract documents is there reference to an agreed financial limit of £580,000, despite the fact that the IBC documentation was issued after the Second Letter of Intent. Had there been the type of agreement contended for by Mr Goldstein then it is expected that [FA] would have recorded it in the contract documents, or in writing. They did not."
"What is clear is that a cap was not incorporated into the contract documents issued after the second Letter of Intent…"
Between the service of the Reply and the decision of the adjudicator, no objection was made by Mr Goldstein or his solicitors as to the reference to the "without prejudice" letter or any request made to rebut any part of the Reply.
"23. The parties are agreed as to the issue of two Letters of Intent one on 18 June 2009 and the other on 4 May 2010. The parties are also agreed that on 30 June 2010 Mr Goldstein's Architect issued a set of Contract Documents for Ellis to complete.
24. It is not disputed that Article 2 of those Contract Documents refers to a Contract Sum of £472,197.31 or such other sum as shall become payable under the Contract.
25. The disagreement arises because Mr Goldstein contends that the IBC incorporates the maximum financial cap as set out in his 4 May 2010 Letter of Intent.
26. However, the copy of the Contract provided at Referral Appendix 8 does not incorporate any such term or cross reference to the letter itself, and in response Mr Goldstein does not direct me to any alternative set of documents in which such a term or cross reference is set out.
27. It is thus clear to me that the Parties contracted firstly on the Letter of Intent dated 18 June 2009 second on the Letter of Intent dated 4 May 2010 and finally on the Contract Documents prepared by Mr Goldstein's Architect and handed to Ellis on 30 June 2010 for completion. These documents were completed by Ellis and returned to Mr Goldstein and they do not include any term or cross reference to a maximum financial value in the manner set out in the 4 May 2010 Letter of Intent and as contended by Mr Goldstein in this Adjudication."
"In making this Decision I have taken into account all submissions made whether or not specifically mentioned herein."
These Proceedings
The Law
"From this and other cases, I conclude as follows in relation to breaches of natural justice in adjudication cases:
"(a) It must first be established that the Adjudicator failed to apply the rules of natural justice;
(b) Any breach of the rules must be more than peripheral; they must be material breaches;
(c) Breaches of the rules will be material in cases where the adjudicator has failed to bring to the attention of the parties a point or issue which they ought to be given the opportunity to comment upon if it is one which is either decisive or of considerable potential importance to the outcome of the resolution of the dispute and is not peripheral or irrelevant.
(d) Whether the issue is decisive or of considerable potential importance or is peripheral or irrelevant obviously involves a question of degree which must be assessed by any judge in a case such as this.
(e) It is only if the adjudicator goes off on a frolic of his own, that is wishing to decide a case upon a factual or legal basis which has not been argued or put forward by either side, without giving the parties an opportunity to comment or, where relevant put in further evidence, that the type of breach of the rules of natural justice with which the case of Balfour Beatty Construction Company Ltd -v- The Camden Borough of Lambeth was concerned comes into play. It follows that, if either party has argued a particular point and the other party does not come back on the point, there is no breach of the rules of natural justice in relation thereto."
"The "without prejudice" rule is a rule governing the admissibility of evidence and is founded upon the public policy of encouraging litigants to settle their differences rather than litigate them to a finish. It is nowhere more clearly expressed than in the judgment of Oliver L.J. in Cutts v. Head [1984] Ch.290, 306:
"That the rule rests, at least in part, upon public policy is clear from many authorities, and the convenient starting point of the inquiry is the nature of the underlying policy. It is that parties should be encouraged so far as possible to settle their disputes without resort to litigation and should not be discouraged by the knowledge that anything that is said in the course of such negotiations (and that includes, of course, as much the failure to reply to an offer as an actual reply) may be used to their prejudice in the course of the proceedings. They should, as it was expressed by Clauson J. In Scott Paper Co v. Drayton Paper Works Ltd. (1927) 44 R.P.C. 151, 156, be encouraged full and frankly to put their cards on the table….The public policy justification, in truth, essentially rests on the desirability of preventing statements or offers made in the course of negotiations for settlement being brought before the court of trial as admissions on the question of liability".
20. "The issue is whether the adjudicator's knowledge of the fact that a 'without prejudice' offer had been made by Holystone to Volker meant that, however unconsciously, he was biased towards them. The relevant test is set out by the Court of Appeal in In Re Medicaments and Related Classes of Goods (No. 2) [2001] 1 WLR 700. Lord Phillips put it in this way:
"The Court must first ascertain all the circumstances which have a bearing on the suggestion that the Judge was biased. It must then ask whether those circumstances would lead a fair-minded and informed observer to conclude that there was a real possibility, or a real danger, the two being the same, that the tribunal was biased.
21. I am in no doubt that a fair-minded and informed observer would not reach any such conclusion here, and any suggestion to the contrary is entirely unrealistic. The adjudicator's letter of 19th July 2010, and his written decision, made clear that he was wholly unconcerned with the fact that an offer had been made. On the face of both documents, the adjudicator treated his knowledge of the fact of the offer as irrelevant. There is other evidence that supports that conclusion. On 14th July, that is to say at a time before the adjudicator was aware that an offer had been made, he noted that "many elements of the decision have been decided". That suggests, therefore, that the bulk of the decision had indeed been produced before he was aware of the fact of the offer. Moreover, the nature of the decision itself also leads to the conclusion that his knowledge had no effect: as Ms Parkin correctly points out, in his decision the adjudicator went through each item of claim, and each defence to that item of claim, in painstaking detail, explaining how and why he had reached the view he had done.
22. Looking at the position rather more widely, I simply cannot see how the adjudicator's knowledge could suggest even unconscious bias. In any construction dispute, the adjudicator, just like a TCC judge, would tend to expect that negotiations had taken place between the parties, and that offers had been made. It is a very rare case in which negotiations or offers do not occur. Accordingly, so it seems to me, the adjudicator would have been unsurprised by the fact that an offer had been made by the responding party. Indeed, in this case, I would go one stage further and observe that, since liability had already been decided by the first adjudicator, and since Mr Holloway was dealing solely with what, if anything, was due to Volker as a result of their valid termination, he would probably have been amazed if he had been told that no offer of any kind had been made by Holystone. In a dispute where the only issue was the quantification of the consequences of termination, the party who has unsuccessfully contested the validity of the termination must almost always expect to pay something, and will therefore make an offer to protect its position on costs sooner rather than later.
23. More generally, I also ought to note this. It is not so long ago that, in arbitration, a white envelope containing the without prejudice offer would be formally presented to the tribunal and reside on the arbitrator's desk for the duration of the hearing. The arbitrator never knew if the without prejudice offer was for £1 million or a penny, but it was never suggested in those circumstances that in some way the arbitrator was unconsciously biased as a result of his knowledge of the fact of an offer. On the contrary, doubtless to convey the impression of reasonableness on their part, it was often the respondent who insisted on the public presentation of the envelope.
"The Court has then to decide whether, on an objective appraisal, the material facts give rise to a legitimate fear that the judge might not have been impartial…The material facts are not limited to those which were apparent to the applicant. They are those which are ascertained by the court."
It should be appointed out that in both the Volker Stevin and Specialist Ceiling cases representations were made to the adjudicator about the submission of without prejudice material to him.
(a) Obviously, such material should not be put before an adjudicator. Lawyers who do so may face professional disciplinary action.
(b) Where an adjudicator decides a case primarily upon the basis of wrongly received "without prejudice" material, his or her decision may well not be enforced.
(c) The test as to whether there is apparent bias present is whether, on an objective appraisal, the material facts give rise to a legitimate fear that the adjudicator might not have been impartial. The Court on any enforcement proceedings should look at all the facts which may support or undermine a charge of bias, whether such facts were known to the adjudicator or not.
Discussion
(a) No objection was made by Mr Goldstein or his solicitors in the five days between the service of the Reply and the issue of the decision. Three of those days were working days. There is no evidence that suggests that they could not have challenged the introduction of the "without prejudice" letter within that time scale.
(b) The adjudicator did expressly say at the end of his decision that he had "taken account of all submissions made whether or not specifically mentioned" in the decision. This type of statement is not uncommon in adjudication decisions and may well reflect a desire to demonstrate that the adjudicator has considered everything which has been put before him or her.
(c) It is equally clear however that the adjudicator did not base his decision at least openly on the contents of, the fact of or inferences drawn from what was or was not in the "without prejudice" letter.
Decision