![]() |
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | |
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Counted4 Community Interest Company v Sunderland City Council [2015] EWHC 3898 (TCC) (18 December 2015) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2015/3898.html Cite as: [2015] EWHC 3898 (TCC) |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY & CONSTRUCTION COURT
Fetter Lane London EC4A 1NL |
||
B e f o r e :
____________________
COUNTED4 COMMUNITY INTEREST COMPANY | Claimant | |
- and - | ||
SUNDERLAND CITY COUNCIL | Defendant |
____________________
(a trading name of Opus 2 International Limited)
Official Court Reporters and Audio Transcribers
5 Chancery Lane, London EC4A 1BL
Tel: 020 7831 5627 Fax: 020 7831 7737
[email protected]
MR. S. TAYLOR (instructed by DAC Beachcroft LLP) appeared on behalf of the Defendant.
____________________
Crown Copyright ©
MRS. JUSTICE CARR:
Introduction
Summary of relevant facts
(a) the procurement was advertised by the issue of a notice in the Official Journal of the EU on 20th June 2015. The services in question are social care services and thus fall within s.7 of the Regulations which provides for flexibility over the manner in which authorities go out to tender. In particular, regulation 76 provides:
"Principles of awarding contracts
76(1) Contracting authorities shall determine the procedures that are to be applied in connection with the award of contracts subject to this section, and may take into account the specificities of the services in question.
(2) Those procedures shall be at least sufficient to ensure compliance with the principles of transparency and equal treatment of economic operators….".
(b) the Defendant issued an invitation to tender on 22nd June 2015;
(c) responses to the invitation to tender had to be submitted by 24th July 2015, the deadline having been pushed back. The Claimant submitted a bid by that revised deadline, doing so with three other consortia members through a special purpose vehicle company. Each member of the consortium committed to be liable under the proposed contract jointly and separately and thus underwrote the Claimant's financial standing, which was assessed as part of the overall bit evaluation;
(d) by letter dated 19th October 2015, the Claimant was informed by the Defendant that its bid had been unsuccessful and that the Defendant intended to award the new contract to NTW. The Claimant received a score of 78.14 and came fifth out of six. NTW had a total score of 87.50. There was a delay of some six eeks in the tender process, the Defendant submits as a result of the thoroughness and robustness of the exercise.
The Claimant's case
(a) in particular, by breaching regulation 24.1 of the Regulations and failing to take any measures to effectively prevent, identify and remedy the conflict of interest of a Mr. Seale, a member of the Defendant's evaluation panel. Mr. Seale was the Defendant's employee with responsibility for managing the existing contract at all times and whose competency in that role had repeatedly been challenged by the Claimant and indeed, as a result of those challenges and complaints, investigated internally by the Defendant;
(b) by failing in its scoring to follow the published award criteria and/or applying undisclosed criteria or methodologies and/or acting in a discriminatory manner and/or committing manifest errors in respect of the method statement questions. In particular, it is alleged that -
(i) the bid was marked inconsistently against the method statement questions;
(ii) the bid was marked inconsistently against the references to the specification;
(iii) the Defendant misunderstood or misinterpreted the bid; and
(iv) the Defendant ignored aspects of the bid.
The Claimant seeks, amongst other things, declarations that the Defendant acted unlawfully and an order that the new contract should be awarded to the Claimant and/or damages.
Application to lift the suspension
The Legal Framework
"Contract-making suspended by challenge to award decision
95....1) Where -
(a) a claim form has been issued in respect of a contracting authority's decision to award the contract,
(b) the contracting authority has become aware that the claim form has been issued and that it relates to that decision, and
(c) the contract has not been entered into,
the contracting authority is required to refrain from entering into the contract."
"Interim Orders
96. (1) In proceedings, the Court may, where relevant, make an interim order -
(a) bringing to an end the requirement imposed by
regulation 95(1);
(b) restoring or modifying that requirement;
(c) suspending the procedure leading to -
(i) the award of the contract, or
(ii) the determination of the design contest,
in relation to which the breach of the duty owed in accordance with regulation 89 or 90 is alleged;
(d) suspending the implementation of any decision or action taken by the contracting authority in the course of following such a procedure.
(2) When deciding whether to make an order under paragraph (1)(a) -
(a) the Court must consider whether, if regulation 95(1) were not applicable, it would be appropriate to make an interim order requiring the contracting authority to refrain from entering into the contract; and
(b) only if the Court considers that it would not be appropriate to make such an interim order may it make an order under paragraph (1)(a)."
"….. The basic principle is that the court should take whichever course seems likely to cause the least irremediable prejudice to one party or the other. This is an assessment in which, as Lord Diplock said in the American Cyanamid case [I975] AC 396, 408:
'It would be unwise to attempt even to list all the various matters which may need to be taken into consideration in deciding where the balance lies, let alone to suggest the relative weight to be attached to them'.
Among the matters which the court may take into account are the prejudice which the plaintiff may suffer if no injunction is granted or the defendant may suffer if it is; the likelihood of such prejudice occurring; the extent to which it may be compensated by an award of damages or enforcement of the cross-undertaking; the likelihood of either party being able to satisfy such an award; and the likelihood that the injunction will turn out to have been wrongly granted or withheld, that is to say, the court's opinion of the relative strength of the parties' cases."
"…It must be legitimate, in considering "all interests likely to be harmed", to have regard to whether, if the lifting of the suspension is ordered, the complaining claimant tenderer is still left with a remedy and that must include an effective remedy. Article 2(1)c) does require that review procedures provide a power to award damages. If there is no ready or easily proved entitlement to damages, that must be a factor which the Court should take into account."
Evidence on the application
"91. Obviously the issuing of these proceedings has meant a delay in the commencement of the mobilisation required for the new contract. As stated above, it is estimated that at the very least, mobilisation will take around three months. Every day delayed is a day lost, hence the urgency of the application made. However, I can confirm that the contract documentation has been finalised and collated and is ready for signature. The Council has received confirmation from NTW that it is ready to sign the contract as soon as possible and has made resources available over the Christmas period in order to ensure that no further time is lost. NTW has a meeting with its partners, scheduled for 18 December 2015. I have been informed that mobilisation can and will be the focus of that meeting if the suspension is lifted prior to that time. If not, that opportunity to progress mobilisation will be lost. I can also confirm that although I have annual leave booked over the Christmas period, I have committed to cancel my plans in order to assist in ensuring that timescales are met. Another member of the team has also been allocated to this task over the Christmas break.
……….
92. For the reasons I have explained above, the award of the contract to the preferred bidder is now a matter of very considerable urgency. Every day that we have to wait for the contract to be awarded is another day on which service users are unnecessarily put at risk. I am genuinely concerned about the level of service currently being provided to service users and must accept that service users' lives are being put at risk, as well as the safety of the residents of Sunderland. I maintain that the Council has done all it can to make the Existing Arrangements work. However, whose fault this is no longer matters and in reality, all parties involved must share some of the blame."
Serious issue
"But in the ordinary procurement case, where there may be points to be made on both sides, it will often be unproductive for the parties (and a waste of judicial resources) to spend a good deal of time arguing about the merits or otherwise of the underlying claim. The threshold is, after all, a low one: see The Newcastle upon Tyne NHS Foundation Trust v Newcastle Primary Care Trust [2012] EWHC 2093 (QB)…."
"….in cases where there are clear issues arising out of individual scores, it will be difficult for the court to conclude that there is no serious issue to be tried; and, second, that this difficulty arises, at least in part, because the relevant documents have yet to be disclosed."
(a) the Defendant has supported Mr. Seale at all times and considers that he was simply doing his job in managing the contract in difficult circumstances. Thus, there can be no personal interest which could compromise the impartiality within the meaning of regulation 24;
(b) there is no reason to believe and no evidence to demonstrate that Mr. Seale's impartiality was undermined. Indeed, he made no objection to the Claimant's past performance during the evaluation stage;
(c) reliance is placed on the fact that the Claimant recently named Mr. Seale as a referee on another tender in which the Claimant is bidding, which, it is said, indicates that the Claimant does not consider Mr. Seale's impartiality to be an issue. It suggests, in the context of this hearing, that any tensions which could have undermined Mr. Seale's impartiality are in the past. (This, in my judgment, is a bad point. The naming of Mr. Seale by the Claimant in a bid was made as recently as last week and as part of an identification process of the Claimant's past work for a new contract. It is in no way indicative of the absence of the tensions existing either now or, more relevantly, at the time of the procurement exercise);
(d) Mr. Seale was an obvious candidate to assist with evaluation given his detailed experience of the services and the needs of the new services. He was but one of a panel of four evaluators with others;
(e) the evaluation process followed was rigorous and thorough and allowed no scope for any one member unduly to influence the scores. All scores, it is said (although again not evidenced), were arrived after the group read the method statement response together, agreeing on a score by consensus and noting contemporaneously the features and shortcomings of the response.
"Conflicts of interest
24. (1) Contracting authorities shall take appropriate measures to effectively prevent, identify and remedy conflicts of interest arising in the conduct of procurement procedures so as to avoid any distortion of competition and to ensure equal treatment of all economic operators.
(2) For the purposes of paragraph (1), the concept of conflicts of interest shall at least cover any situation where relevant staff members have, directly or indirectly, a financial, economic or other personal interest which might be perceived to compromise their impartiality and independence in the context of the procurement procedure."
Balance of convenience
"In summary, the existing arrangements provide a service to the people of Sunderland which attempts to address as best it can the issue of substance misuse. I do not want anyone who is contemplating using the service to think that it cannot help. Most of the staff on the ground continue to do their best in the difficult circumstances. However, it can be much improved and the new contract will ensure that the current risks associated with having a number of providers in place are addressed."
"Counted4 and its clinical staff, including myself as Medical Director, are best placed to assess the safety and robustness of the treatment system. The system as it stands is safe and is now in fact more secure than it has been since the existing contract was signed, as best practice is well embedded across all key functions…Based on my professional opinion and years of experience in substance misuse treatment, a change of provider is an exceptionally disruptive stage which can lead to the loss of clients and the need for extensive re-engagement down the line…"
"The system is still not safe/responsive and there is still much to do."
The Defendant also referred to a press report in March 2015 quoting Mr. Devitt as saying that:
"It was like going back to the Dark Ages."
Conclusion