[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Triuva Kapitalverwaltungsgesellschaft v Galliford Try Construction Ltd [2017] EWHC 275 (TCC) (23 February 2017) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2017/275.html Cite as: [2017] EWHC 275 (TCC) |
[New search] [Printable PDF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
TRIUVA KAPITALVERWALTUNGSGESELLSCHAFT |
Claimant |
|
- and - |
||
GALLIFORD TRY CONSTRUCTION LIMITED |
Defendant |
____________________
Mr Piers Stansfield QC and Mr Crispin Winser (instructed by Pinsent Masons LLP) for the Defendant
Ms Clare Dixon (instructed by RPC) for the Third Party
Hearing dates: 10 February 2017
____________________
Crown Copyright ©
Mrs Justice O'Farrell :
Test to be applied
"it is satisfied that, if the claim went to trial, the claimant would obtain judgment for a substantial amount of money (other than costs) against the defendant from whom he is seeking an order for an interim payment "
i) whether the court is satisfied that Triuva would obtain judgment on at least part of its claim for damages;ii) if so, whether the court is satisfied that Triuva would be awarded substantial damages in respect of the claim;
iii) whether the court should exercise its discretion and order an interim payment;
iv) if so, what level of interim payment should be ordered; and
v) whether the same or any similar order should be made against Alumet.
The Claimant's Evidence
i) water ingress to the structurally glazed system and the pressure plate and cap system;ii) inadequate fire stopping;
iii) incorrectly fire-rated alucobond panels;
iv) structural defects; and
v) inadequate thermal performance.
i) Water ingress has been caused by the following defects, which are contrary to the Alumet drawings:a) absence or incorrect installation of the EPDM membrane and missing clip and sealant so as to provide a vapour barrier in the pressure plate and cap system;b) defects in the gaskets, seals, and the spacing of fixings and toggles so as to hold the glass firmly in place;c) incorrect position of the deflector block and/or blockage of the drainage holes preventing water drainage; andd) absence of the concertina membrane in the structural glazing system and defective mastic.ii) The fire stopping at the floor slab compartment lines is not as shown on the Alumet drawings in that there are gaps and the fire stopping is not adequately compressed.
iii) The Alucobond flashing panels are Class 1 instead of Class 0 for surface spread of flame and therefore not in accordance with the relevant Building Regulations (Part B 2000).
iv) There are structural defects in that the fixings on the panels are badly installed (slotted holes wrong size or orientation for bolts, screws not properly fixed) and no anti-rotation pins have been installed.
v) Insulation is missing or discontinuous, contrary to the Alumet drawings, resulting in cold bridging.
a | Preliminaries for the 12 week original remedial works programme | £150,980 |
b | Hose testing the cladding system | £1,225 |
c | Original survey, inspections and benchmarking by Clear Line | £93,150 |
d | Extended survey by Clear Line | £105,159 |
e | Making good fire stopping defects | £34,838 |
f | Replacement of incorrectly fire-rated Alucobond panels | £577,940 |
g | Replacement of defective pressed metal copings | £161,666 |
h | Making good the structural integrity defects | £108,355 |
i | Making good defects to the deflector blocks and blocked drainage holes | £5,355 |
J | Remedying defects in the EPDM membrane | £12,150 |
£1,250,818 |
Defendant's Evidence
i) There is insufficient clarity as to the technical literature, standard details or advice from Schüco (the proprietor of the glazing systems) applicable to the weatherproofing issues.ii) Mr Murray does not address the gaps in the fire stopping.
iii) The adequacy of the use of the Alucobond panels depends on the approach of Building Control. The approved documents provide practical guidance for the purpose of the relevant Building Regulations but they are not mandatory and there may be alternative ways of achieving compliance.
iv) There is insufficient clarity as to the technical literature, standard details or advice from Schüco applicable to the fixings and anti-rotation pins. A structural assessment is required as to the adequacy of the same.
v) The degree of insufficiency and non-compliance, and the consequences of any shortfall in the insulation require clarification and further investigation.
Liability
Damages
i) item f) the cost of replacement of the Alucobond panels (on the ground that the relevant defect is not pleaded and there is an arguable defence) andii) item g) the cost of replacement of the pressed metal copings (on the ground that they are not relied on for the purpose of this application),
the claimed cost of and associated with the established defects is £511,212.
i) In respect of item a) preliminaries (£150,980), he has expressed his opinion that the time-related preliminary items should not significantly exceed £100,000.ii) In respect of item b) original survey (£93,150), he notes that this is the same as the contract sum allowance but that he needs to verify that this was carried out.
iii) In respect of item c) extended survey (£105,159), he notes that this was a lump sum quoted by Clear Line but would require further details.
iv) In respect of item h) structural remedial works (£108,355) and the other discrete items (c.£53,000), he has provided his breakdown of the costs and identified costs that appear to be duplicated or for which no explanation has been provided.
Discretion
Amount of Interim Payment
GTC's claim against Alumet
Conclusion
i) GTC shall pay to Triuva the sum of £300,000 by way of interim payment on account of any damages which the court may hold GTC liable to pay by 5 pm on 3 March 2017.ii) Alumet shall pay to GTC the sum of £300,000 by way of interim payment on account of any damages which the court may hold Alumet liable to pay by 5 pm on 3 March 2017.
iii) The fact and amount of the interim payments must not be disclosed to the trial judge until all questions of liability and quantum have been determined.