[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Triple Point Technology, Inc. v PTT Public Company Ltd [2018] EWHC 1398 (TCC) (07 June 2018) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2018/1398.html Cite as: [2018] EWHC 1398 (TCC) |
[New search] [Printable RTF version] [Help]
BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES
TECHNOLOGY AND CONSTRUCTION COURT (QB)
Strand, London, WC2A 2LL |
||
B e f o r e :
The Honourable Mr Justice Fraser
____________________
TRIPLE POINT TECHNOLOGY, INC. |
||
and |
||
PTT PUBLIC COMPANY LIMITED |
____________________
James Howells QC and Nicholas Maciolek (instructed by Watson Farley & Williams LLP) for the Defendant/Respondent
Hearing dates: 17 and 23 May 2018
Draft provided to parties: 30 May 2018
____________________
Crown Copyright ©
Mr Justice Fraser:
"For the avoidance of doubt, I do not make any extension of time for the making of any application to the Court of Appeal, but I observe that time should be treated as running from today since all consequential matters were adjourned until today."
That plainly meant, and in the absence of any further extension of time could only mean (and both parties correctly understood it to mean) that the 21 day period under CPR Part 52.12(2)(b) started to run from 4 October 2017. This is consistent with the notes at CPR 52.12.3 which refer to the decision of the Court of Appeal in Sayers v Clarke Walker [2002] EWCA Civ 645 and the dicta of Brooke LJ at [12] to [16]. This is that time starts to run from the decision of the lower court, and not from the date upon which the judgment or order of the court is sealed or perfected. Jefford J also reserved her decision on costs and interest, although as I have said Triple Point knew it would be ordered to pay further sums (and had conceded that it would be paying PTT's costs). The precise amount of the further sums was not however known, either to Triple Point or PTT.
"The learned trial judge found predominantly in favour of [PTT]. The exact sum to be paid is not known at the time of preparing this statement because the learned judge has not yet ruled on contended matters of interest and payment on account of costs. However, on [PTT's] case, the amount which the judge will order [Triple Point] to pay will likely be in excess of US$5,500,000 plus over £2,100,000 on account of costs. This should include the sum of US$692,000 already paid to [PTT] at the outset of the disputed project and held by it as performance security."
Mr Shirtcliff also dealt with the difficulties of enforcing judgments against companies in Thailand, maintained that there would be difficulties in recovering payment back to Triple Point from PTT in Thailand were the appeal to be successful and a stay of execution not granted, and drew attention to the accounts available for PTT which showed it had in excess of US$6 billion in cash alone, and assets of US$66 billion.
"and the following:
1. As a result of the judgment below, the Appellant will be ordered to pay the Respondent in the region of US $5.5m plus costs ("the Judgment Sum") to the Respondent (the exact sum will be known when the trial judge decides contested issues of interest and the payment on account of costs). Unless a stay is ordered, the Judgment Sum will be enforceable, regardless of the Appellant's pending appeal.
5. For the reasons set out above, the Appellant respectfully requests that the Court stay the enforcement of the Judgment Sum pending the determination of the appeal."
(emphasis added)
1. One dated 17 January 2018 dealing with the substantive judgment sum ("Order No.1");
2. The other, also dated 17 January 2018, dealing with interest and costs ("Order No.2").
The parties suggested two orders were drawn up, rather than the different elements being included in a single order, for reasons which do not matter.
"On consideration of the appellant's notice and accompanying documents, but without an oral hearing, in respect of an application for permission to appeal and a stay of execution
Decision:
Granted
Reasons:
This is not a straightforward case and the grounds of appeal are interlinked. The prospects of success are sufficient to warrant the grant of permission."
"That enforcement of the Judgment is not for the time being stayed or suspended, that the time available for its enforcement has not expired and that the Judgment is accordingly enforceable."
This form was dated the same date as the witness statement, namely 12 March 2018 and signed by Mr Prentki.
1. In footnote 1 "Enforcement of the Judgment Order has been stayed by the High Court pending appeal";
2. In footnote 2 "Under English law, the judgment for Costs, pursuant to the Costs Order, and Approved Judgment are final, conclusive and enforceable, and enforcement thereof has not been stayed by any court".
1. The propriety of the execution proceedings initiated in the US by PTT, using a certificate that should not have been obtained in reliance upon a statute and Part of the CPR that had no applicability to enforcement action in the US; and
2. The scope of the stay of execution in fact already granted by Jackson LJ.
There is a degree of overlap between the two issues because if the stay of execution already caught Order No.2, no execution could be embarked upon by PTT in any event without it being in contempt of court.
The enforcement proceedings commenced in Connecticut on 17 April 2018
The stay of execution granted by Jackson LJ
"285. Issue 13 (and subject to issue no. 14):
(i) PTT is entitled to be paid the cost of procurement of an alternative system in the sum of US$10,574,756.78.
(ii) PTT is entitled to recover wasted costs in the sum of US$630,000.
(iii) PTT is entitled to recover damages under Article 5 in the sum of US$3,459,278.40
286. Issue no. 14: PTT's claim in respect of (i) and (ii) above is, however, limited by the terms of Article 12.3 to the total sum of US$1,038,000.
287. Issue no. 15: TPT is not entitled to recover at least the sum of US$2,312,361,52 in respect of services provided to PTT.
288. Issue no. 16: TPT claimed the repayment of the amount of a performance bond, provided pursuant to Article 11 and paid to PTT. TPT accepted that this issue turned on the decision as to repudiatory breach. Since I have found that PTT was not in repudiatory breach, the sum does not fall to be repaid.
289. Issue no. 17: TPT claimed to be entitled to an indemnity under Article 13 against claims by Accenture who acted as sub-consultants. Article 13 provided an indemnity against loss, damages liability and claims arising out of the performance of the Contract "provided that such losses, damages, liabilities and claims shall occur as a consequence of the errors, omissions, negligence or wilful misconduct of the indemnifying party". No such basis for an indemnity arises here and TPT are not entitled to the indemnity.
290. Under issue no. 18, PTT sought declarations as to the meaning of Articles 15.4.2 and 15.4.4. Only the declaration in respect of Article 15.4.2 was pursued. Article 15.4.2 contains an obligation to assign rights and duties to the extent required by PTT in the event of termination. PTT's case was that that must include an obligation to inform PTT of any rights and duties which PTT might require to be assigned."
" .application for permission to appeal and a stay of execution
Decision:
Granted
could mean was, absent further words, that it was payment of the substantive judgment amount alone that was stayed. This amounts to a submission that on every consideration for a stay of execution, the Lord or Lady Justice must always state on the face of the order "granted, in respect of a stay of execution for the substantive sum, and interest and payment on account of costs" or similar words, otherwise the grant of a stay of execution would not impact upon the two latter items, as they would be in different paragraphs of the relevant order. I do not accept that can be right.
"Without prejudice to rule 83.7(1), a party against whom a judgment has been given or an order made may apply to the court for-
(a) a stay of execution of the judgment or order; or
(b) other relief;
on the grounds of matters which have occurred since the date of the judgment or order, and the court may by order grant such relief, and on such terms, as it thinks just."
"The exact sum to be paid is not known at the time of preparing this statement because the learned judge has not yet ruled on contended matters of interest and payment on account of costs. However, on [PTT's] case, the amount which the judge will order [Triple Point] to pay will likely be in excess of US$5,500,000 plus over £2,100,000 on account of costs."
(emphasis added)
"As a result of the judgment below, the Appellant will be ordered to pay the Respondent in the region of US $5.5m, plus costs ("the Judgment Sum") to the Respondent (the exact sum will be known when the trial judge decides contested issues of interest and the payment on account of costs)."
(emphasis added)
Therefore interest was implicitly part of the "Judgment Sum" as defined; and costs was expressly part of the same defined term. The phrase "plus costs" is expressly included in the Judgment Sum as defined in the appellant's notice itself; an approximate figure is given to include interest; and the fact that the exact figure is not yet known is also identified.
"13.6 The costs of the trial and interest on the judgment to be determined by the Court of Appeal or remitted to Mrs Justice Jefford".
"The Respondent be restrained from continuing or prosecuting or assisting in the prosecution of any enforcement proceedings commenced by the Respondent directed to executing upon the Orders of Mrs Justice Jefford dated 17 January 2018, until the determination of the present appeal, reference number A1/2017/2912."
Appendix A: The 18 issues dealt with in the substantive judgment of 23 August 2017
A. TPT's Claim To Payment of Software Licence Fees
1. Whether payment (in the aggregate sum of US$4,942,000) in respect of TPT's software was to be made on the dates set out in one Order Form dated 31 January 2013 and two dated 30 April 2013 or whether TPT was only entitled to payment under the CTRM Contract according to the milestones set out in Article 18 of the CTRM Contract.
2. If the answer to Issue 1 is that payment was to be made on the dates set out in the Order Forms, whether in any event no payment is due to TPT because, as alleged by PTT, PTT has suffered a total failure of consideration in respect of the supply of TPT's software.
3. Whether, as TPT alleges, the sum of US$330,000 in respect of annual maintenance services for software fell due and payable on 15 January 2015 (being the date stated in an order Form dated 30 April 2013) and is therefore owed to TPT.
B. The CTRM Contract
4. Whether there should be implied into the CTRM Contract:
a. A term to the effect that TPT was required to carry out the agreed Services under the CTRM Contract only in the event that PTT made payment in respect of TPT's software on the dates indicated on the Order Forms.
b. A term to the effect that the parties would co-operate to permit one another to perform the CTRM Contract.
C. Delay to the Project
5. Whether the delay to and/or ultimate failure of the project was caused by:
a. On TPT's case, additional requirements for the CTRM System demanded by PTT after the conclusion of the CTRM Contract, and PTT's iterative approach to feedback which prevented TPT from completing the business process documentation in a timely manner; or
b. On PTT's case, TPT's negligent failure to plan, programme or manage the project; its failure to provide sufficient numbers of suitably qualified staff; its negligent failure to conduct adequate business analysis and production of business blueprints required under the terms of the CTRM Contract; and/or its negligent failure to follow appropriate or internationally recognised and applied methodologies for the design, development and implementation of the software.
D. Suspension
6. Whether, on TPT's case, the parties entered into an express and/or implied agreement (whether by variation to the CTRM Contract or collateral or supplemental agreement by conduct or otherwise) to the effect that:
a. The timeframes by which the Claimant was to provide the Implementation Services under the CTRM Contract were suspended;
b. The Implementation Services for the CTRM Contract were subject to further negotiation and agreement; and
c. The CTRM Contract did not therefore contain the agreed scope of the Implementation Services
E: Force Majeure
7. Whether the state of civil unrest in Thailand from November 2013 to May 2014 constituted an event of force majeure pursuant to Article 16 CTRM Contract such as to suspend TPT's contractual obligations during the period of unrest.
F: Termination
8. Whether TPT was in breach of contract such as to entitle PTT to terminate the CTRM Contract under its terms or at common law by reason of its negligent failure to follow appropriate or internationally recognised and applied methodologies for the design, development and implementation of the software; its negligent failure to conduct adequate business analysis and/or produce adequate business blueprints so as to address inadequacies in the functionality of the proposed CTRM system to meet PTT's requirements in respect of functional integration and/or invoicing functionality and/or interfaces between CTRM and SAP and/or reporting functionality; its failure to provide adequate staff resources and/or its negligent failure to manage the project and/or the resultant delay to the Project.
9. Whether TPT's refusal to perform the CTRM Contract from May 2014 constituted a repudiation of the CTRM Contract.
10. Whether PTT's refusal to pay licence fees or maintenance fees in respect of TPT's software on the date set out in the Order Forms amounted to a renunciation of the CTRM Contract or (on TPT's case) any separate contract(s) contained in the Order Forms.
11. Whether PTT's notices to remedy breach of 5 September 2014 and/or 16 February 2015 and/or its notice of termination of 23 March 2015 constituted repudiatory breaches of the CTRM Contract.
12. In the light of the findings made in respect of Issues 8, 9, 10 and 11, the means by which the CTRM Contract was terminated.
G: Damages & Quantum
13. Whether PTT is entitled to recover damages in respect of all or any of:
a. The cost of maintaining its TCS System in the sum of US$1,053,075 or at all.
I note that this claim is now withdrawn.
b. Costs in relation to the procurement of an alternative system to be designed and developed to meet PTT's requirements in the sum of US$15,691,875 or at all; and/or
c. costs alleged to have been wasted in the sum of US$3,080,121.21 or at all; and
d. liquidated damages for delay under Article 5 CTRM Contract in the sum of US$3,459,278.40 or at all.
14. Whether PTT's claim to damages is limited by the terms of Article 12.3 of the CTRM Contract.
15. Whether TPT is entitled to the sum of at least US$2,312,261.52 in respect of services provided to PTT.
16. Whether TPT is entitled to repayment of the performance bond paid to PTT by cheque dated 31 January 2013 pursuant to Article 11 of the CTRM Contract in the amount of US$692,000.
17. Whether TPT is entitled to an indemnity in respect of claims by third parties such as its sub-contractor, Accenture, pursuant to Article 13 of the CTRM Contract, alternatively, pursuant to an implied right to an indemnity.
18. Whether PTT is entitled to the declarations sought as to the meaning of Article 15.4.2 and/or Article 15.4.4 of the CTRM Contract.