[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Hoyle v BAK Building (Contracts) Ltd [2018] EWHC 2802 (TCC) (23 August 2018) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2018/2802.html Cite as: [2018] EWHC 2802 (TCC) |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
BUSINESS AND PROPERTY COURTS
TECHNOLOGY AND CONSTRUCTION COURT
Strand London WC2A 2LL |
||
B e f o r e :
____________________
CHARLES DAVID HOYLE |
Claimant |
|
v |
||
B.A.K. BUILDING (CONTRACTS) LTD |
Defendant |
8th Floor, 165 Fleet Street, London, EC4A 2DY
Tel No: 020 7404 1400 Fax No: 020 7404 1424
Web: www.epiqglobal.com/en-gb/ Email: [email protected]
(Official Shorthand Writers to the Court)
____________________
MR M HIRST (instructed by Napthens LLP) appeared on behalf of the Claimant
The Defendant was not represented and did not appear.
____________________
Crown Copyright ©
"Please note that they did not realise that there was a different timetable as they are not legally trained. We were not aware of the hearing date otherwise instructions would have been left as regards the procedure if this was received but as we did not know the hearing was taking place this was unable to be done."
"We can confirm that the hearing date in particular is difficult for the firm as both the site manager and the director who would be able to comment more fully and provide statements are on annual leave and do not return to the office until 3rd September 2018."
As I said, the defendant proceeded to ask for extensions for the filing of further evidence and for the re-listing of the hearing on a more convenient date in September.
"We would confirm that we have not agreed to recognise the adjudication and do not agree to be responsible for any fees in this matter. Our reasons for this are as follows: (1) Mr Charles David Hoyle had no written contract with ourselves for the carrying out of works. He was contracted as a sub-contractor and provided a weekly time sheet and was paid for hours worked on site which was not always eight hours per day and, in any event, would have included an unpaid lunch break. (2) The surveyor who was dealing with this matter on behalf of Mr Hoyle we understand is his son and therefore there is a clear conflict of interest and any analysed and valued work assessed by the claimant is not agreed. Mr Hoyle did not, during the whole of the time contracted on the site dispute the time sheets or the payments made until he left the site by mutual agreement. Mr Hoyle was not satisfied at having the money withheld until disputes on the site were resolved and we were not happy with the standard of work which had been good in parts but then some work had been sub standard."
The letter then made further points which all related to the dispute between the parties as to what Mr Hoyle should be paid.
"With regard to BAK's confirmation that it has not agreed to recognise the adjudication, et cetera, of 23 January 2018, I will make the following observations:
(1) Mr Hoyle's entitlement to refer to Adjudication is not dependent upon Mr Hoyle having a written contract with BAK. Such requirements for a written contract do not apply to the Housing Grants Construction and Regeneration Act 1996 as amended by the Local Democracy, Economic Development and Construction Act 2009.
(2) The fact that Mr Charles David Hoyle is represented in these proceedings by his son, Andrew, is irrelevant. I see no 'conflict of interest' as suggested by BAK. I am not aware of any requirement for impartiality between a Party to adjudication and its representative."
Mr Conway was, in my view, entirely right in the views that he expressed in those two paragraphs.
"At no point throughout any of the proceedings have we dealt with or heard from CDH. Even through the arbitration, the person responding was Andrew Hoyle, not CDH. Therefore, as we did not see any authority or any indication of an authority from CDH that authorised his son to deal with this matter, the adjudicator was not directly instructed."
Those points are, in my view, utterly ill-conceived. Mr Hoyle made it clear at the outset of the adjudication that he was going to be represented by his son who was a chartered quantity surveyor. The letter of 5 January to BAK, which enclosed his notice of adjudication, says precisely that. Adjudication is not a court process and it is entirely open to somebody involved in the adjudication to be represented by someone whom they wish to represent them. It is not necessary for them to provide any written form of authority or enter into any other formal arrangement and the fact that the adjudicator may have received submissions from Mr Andrew Hoyle has no impact on his jurisdiction whatsoever.