![]() |
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | |
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Bam Glory Mill Ltd v Balicrest Ltd & Anor [2018] EWHC 3926 (TCC) (3 October 2018) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2018/3926.html Cite as: [2018] EWHC 3926 (TCC) |
[New search] [Printable PDF version] [Help]
BUSINESS AND PROPERTY COURTS
OF ENGLAND AND WALES
TECHNOLOGY AND CONSTRUCTION COURT (QBD)
Royal Courts of Justice
B e f o r e :
____________________
BAM GLORY MILL LIMITED | Claimant | |
- and - | ||
(1) BALICREST LIMITED | ||
(2) McGEE CIVIL ENGINEERING LIMITED | Defendant |
____________________
MS C. PIERCY (instructed by Birketts LLP) appeared on behalf of the Defendants.
____________________
Crown Copyright ©
WARNING: reporting restrictions may apply to the contents transcribed in this document, particularly if the case concerned a sexual offence or involved a child. Reporting restrictions prohibit the publication of the applicable information to the public or any section of the public, in writing, in a broadcast or by means of the internet, including social media. Anyone who receives a copy of this transcript is responsible in law for making sure that applicable restrictions are not breached. A person who breaches a reporting restriction is liable to a fine and/or imprisonment. For guidance on whether reporting restrictions apply, and to what information, ask at the court office or take legal advice.
This Transcript is Crown Copyright. It may not be reproduced in whole or in part other than in accordance with relevant licence or with the express consent of the Authority. All rights are reserved.
MR JUSTICE WAKSMAN:
"The drawing is obviously a trial pit/borehole location plan which is meaningless. Can you confirm back to me which of the two situations is applicable? Is it a set of locations that you want to do for trial pits or boreholes, i.e. they were merely intended, or a plan of trial pits/boreholes of recent investigations? It turned out to be the latter. If this is true, you will need to send me the results of the trial pits and boreholes for me to ascertain what the problem, if any, may be. At the moment, what you have given me does not supply any evidence of breach of my contract."
"...the obligation in good and workmanlike manner to demolish all buildings and importantly remove all underground structures, services obstructions, foundations, and tanks at the site."
Then there was an obligation to come back if the claimant had found such obstructions.
"...designed and executed the works relating to the adopted drains, associated infrastructure, and site remediation in a good and workmanlike manner."
"The claimant is not yet in a position to allocate responsibility for the failure to remove each underground structure as between the two defendants."
Mr Goodkin, in argument, sought to row back from that somewhat by saying that as presently advised, the case was against both of them.
"If West LB decides not to pursue the claim, there will be no need for Nomura to pursue the Nomura claim and significant costs will be avoided."
"...the key question must always be whether or not, at the time of issuing ... the claimant was in a position properly to identify the essence of the tort or breach of contract complained of and if given appropriate time to marshall what it knew, to formulate Particulars of Claim. If the claimant was not in a position to do so, then the claimant could have no present intention of prosecuting proceedings, since it had no known basis for doing so. Whilst therefore the absence of present intention to prosecute proceedings is not enough to constitute an abuse ... without the additional absence of known valid grounds ... the latter carries with it, as a matter of necessity, the former. If a claimant cannot do that which is necessary to prosecute the claim by setting out the basis of it, even in a rudimentary way [and I emphasise those words], a claimant has no business to issue ... [the claim] ...'in the hope that something may turn up'. ...in such circumstances ... the ... claimant hopes ... to stop the limitation ... and ... deprive the defendant of a potential limitation defence. The ... claimant thus, unilaterally, by its own action, seeks to achieve for itself an extension of the time allowed by statute for the commencement of an action, even though it is in no position properly to formulate a claim against the relevant defendant. That must ... be an abuse of process."
(1) Whether it is alleged that that defendant is in breach of contract in relation to that item; and
(2) All facts and matters relied upon in support of that allegation.
CERTIFICATE Opus 2 International Ltd. hereby certifies that the above is an accurate and complete record of the proceedings or part thereof. Transcribed by Opus 2 International Ltd. (Incorporating Beverley F. Nunnery & Co.) Official Court Reporters and Audio Transcribers 5 New Street Square, London EC4A 3BF Tel: 020 7831 5627 Fax: 020 7831 7737 [email protected] ** This transcript is subject to Judge's approval ** |