[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Freeborn & Anor v Marcal (t/a Dan Marcal Architects) [2019] EWHC 454 (TCC) (27 February 2019) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2019/454.html Cite as: [2019] EWHC 454 (TCC) |
[New search] [Printable PDF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
(1) MR PHILIP FREEBORN (2) MRS CHRISTINA GOLDIE |
Claimant |
|
- and - |
||
MR DANIEL ROBERT De ALMEIDA MARCAL (Trading as DAN MARCAL ARCHITECTS) |
Defendant |
____________________
Mr Thomas Ogden (instructed by Caytons Law) for the Defendant
____________________
Crown Copyright ©
Martin Bowdery QC :
(1) Introduction;
(2) The Defendant's Retainer;
(3) The Evidence Relating to the "Key Dispute" or "Main Dispute";
(4) The issues of alleged breach by the Defendant;
(5) The loss and damage allegedly caused by the alleged breaches;
(6) The answers to the list of issues prepared by the Claimant;
(7) Conclusions, Findings and Orders.
1 INTRODUCTION
i) hibernating the swimming pool;
ii) constructing the "glass box on legs" cinema room and staircase in the Pool House;
iii) partial installation of the audio-visual equipment in the cinema room;
iv) installing a wooden support for the new flooring to the Pool House (the plan was for it to serve as a function room);
v) electrical, lighting and joinery works to the Pool House;
vi) replacement of the window casements in the Main House;
vii) decorating works to the Main House.
i) Accomod8: constructed the staircase and other bespoke carpentry for the Claimants;
ii) Advanced Pool Services ("APS"): installed submersible sump pumps to the pool basin as part of the hibernation of the pool;
iii) Connect Construction Services ("Connect"): installed (i) a damp-proof membrane around the existing pool and (ii) a timber structure to support the new floor for the Pool House;
iv) DKD: decorating works in the Main House;
v) Ridlands: detailed design and construction of the cinema box and stairs. Ridlands retained Malishev Engineers to provide structural engineering and design services;
vi) Olive Audio Visual ("Olive Audio"): supplied and installed audio equipment;
vii) Routley & Lemon ("Routley"); electrical works to the cinema box and the Pool House:
viii) Tubridy Builders ("Tubridy"): replacement of the window casements in the Main House.
The Claimants called:
- Christina Goldie
- Philip Freeborn
- Matthew Rogers
- Jason Bayford
- John Routley (he also gave a witness statement to the Defendant).
The First and Second Claimants were impressive witnesses. Despite a robust and thorough cross-examination from Mr Ogden their evidence was clear and concise. They avoided exaggeration and speculation. The Claimants' remaining factual witnesses were truthful and helpful even if their involvement in the major disputes was somewhat limited.
The Defendant called:
- Daniel Marcal
- Donald McDermott
- Jeremy Murphy
- Robert Tubridy.
The Defendant's evidence is analysed in some detail in Section 3 of this judgment. Whilst the Defendant did his best to assist the Court his recollection of key events was confused and not convincing, he gave the impression of being somewhat disorganised in his approach to this project. The Defendants' remaining factual witnesses were also truthful and helpful even though their involvement in the key disputes was extremely limited.
- The architectural experts were John Perry for the Claimants and Ian Salisbury for the Defendant. The quantity surveying experts were John Wood for the Claimants and John Farrow for the Defendant. There was also a jointly appointed audio-visual expert Christopher Adair.
i) The primary basis for the duties owed by an architect is the contract pursuant to which he is engaged[1];
ii) It is common ground that the Defendant owed the Claimants a duty to provide the services he supplied with reasonable care and skill (s.13 of the Supply of Good and Services Act 1982);
iii) The standard of reasonable care and skill is not a standard of perfection. It does not make an architect the insurer or guarantor that the work has been properly done. It is not sufficient to prove an error to show that there has been a failure to exercise reasonable skill and care. A claimant must establish actual negligence[2];
iv) An architect is entitled to recommend to a client that the client appoint a third party with the requisite knowledge to carry out work which requires that specialist knowledge. Ordinarily the architect will carry no legal responsibility for the work to be done by the specialist which is beyond the capability of an architect of ordinary competence[3];
v) An architect's obligation to supervise or inspect works will depend on various factors including the terms of the retainer, the nature of the works and his confidence in the contractor[4];
vi) The Claimants are only entitled to recover any loss and damage caused by the Defendant's negligence and which they have sought to mitigate;
vii) The damage ordinarily recoverable where a building suffers from defects consequent upon the negligence of an architect is the cost of rectification.[5]
"The key dispute between the parties is whether or not Mr Marcal redesigned the cinema box without telling the Claimants and arranged for the construction of a cinema box which they had not approved."
.2 THE DEFENDANT'S RETAINER
"Dear Christina,
Hope this email finds well. Further to our discussions earlier this week, I would be very happy to work on developing and managing a scheme to reconfigure your swimming pool area and connecting space.
In terms of a way forward we can split the works in to the following:
1. I will survey the existing building and draw up on CAD.
2. I will develop scheme options and a brief: We can go for a Bronze, Silver and Gold approach ie budget conscious to high end options. This will be represented as a series of drawings which I can present to you.
3. Go out to tender: We can obtain 2 to 3 prices from different contractors, and see which will be most suitable. Contractors can work under a JCT Minor Works contract, which protects all parties and will allow us to formalise a programme, scope of work and budget.
I have contractors I would like to put forward who work on similar jobs, for example 'City Basements' who specialise in below ground works.
The following areas of work can be given to separate contractors who specialise in specific trades:
- Below ground works where swimming pool currently exists: In effect we will be creating a basement which will be fully waterproofed and warranted. This will accommodate a cinema room, WC (option), storage and connecting corridor. A new floor will be constructed over the existing swimming pool to allow for a function room at ground level.
- Fit out works: To include all electrical (lighting, AV, power, data), plumbing, joinery, decorations etc to all areas. This includes newly formed below ground areas, new function room where swimming pool exists, adjoining room where mezzanine level exists.
- Helical staircase: There are companies who can make staircases off site and install thereafter. This offers a very high standard of finish, and can be carried out in the most economical manner. We can decide on finishes when I present some options to you.
- Skylight Replacement: We can look in to producing more architectural features with new glazed skylights installing new drylining beneath to create crisp detailing.
We can add omit or change any of these areas as we proceed at design stage.
In terms of my role I would like to design and project manage through to completion. This will include all Building Control matters, site visits etc. Because the works are internal planning will most likely not be required, however if an application is required, I can deal with this also. How does this sound?
I can firm up a programme and fee if you are happy on this basis. Because the works are stage based, we have hold points where we can review my input accordingly and you can decide what suits you best.
Hope you have a great weekend, and please do not hesitate to contact me should you have any queries."
"That all sounds great. My husband is due back tonight so I would like to show him your email and get back to you on Monday if that is ok.
Have a great weekend."
"Dear Dan,
Hope you had a good weekend. We would like to go ahead and I am really pleased that you will be able to design and project manage the whole thing. Let me know what happens next.
Best wishes
Christina"
"012 Handover Meeting Notes
Meeting held 09/07/2015 (evening) at 3 Horseshoe Lane
Notes 10/07/2015
Attendees
Christina Goldie
Philip Freeborn
Daniel Marcal
1. I propose to handover my responsibilities to Christina further to Christina allowing Jason / Darren to complete works without my knowledge.
2. Decoration works to cinema box: Christina brought her own trade (Darren) on to do the works despite my having instructed another decorator to carry out works.
3. Christina explained she was unaware I had instructed another decorator. I explained I had been communicating and agreeing scope with Philip directly hence the confusion!
4. Decoration works to function room: as above
5. Philip has requested that I stay on the project to focus on completing the cinema. Agreed.
6. All other works are being managed by Christina who is allowing Jason to complete the following:
- Pool
- New sub-floor
- Dinesen floor
- Re-plastering raked ceiling local to front elevation of cinema box"
i) no written contract;
ii) no written brief for the project or any part of the project;
iii) no minutes of any meetings with the Claimants and/or the contractors for the Claimants to agree or disagree;
iv) no progress or planning reports;
v) no interim accounts or valuations for the works.
the Defendant to explain what he thought happened had to rely upon this "tumble dryer of information" which when analysed in any detail could not be readily understood let alone relied upon in the absence of supporting contemporaneous document evidence.
As the Claimants explained in Appendix 4 of their Written Closing Submission:
"Various questions were put to Mr Marcal which were very relevant to his continued involvement after 9th July, and which prove the inaccuracies of his account of the 9th July meeting, and indirectly demonstrate that the note dated 10th July could not have been written on that date for the reasons set out by Mr Freeborn in his statement at Paragraph 65. However the cross examination which led to him to admit, more than once, that the 10th July typed note could not have been written until later relied on the following six points in particular.
They relate to Point 6 of the note which says:
"All other works are being managed by Christina who is allowing Jason to complete the following:
Pool
New Sub floor Dinesen floor
Re-plastering raked ceiling local to front elevation of cinema box"
There are six of them. All are a more detailed version of the reasons which Mr Freeborn testifies to at Paragraph 65 of his first witness statement:
Point 1
Claimants did not know and were not told on or before 10 July that any more work needed to be done to the pool so there would be no discussion of Jason doing work in the pool
Point 2
No question of Jason being involved in the new subfloor in July 2015. The Defendant is still in correspondence with VA Hutchison until November 2015 about sub-flooring quotes, and much of that correspondence was put to the Defendant
Point 3
No question of Jason being involved in the Dinesen floor in July 2015
Hutchison were shown as doing it in the documents
Point 4
Raked ceiling local to front elevation had not been plastered in July 2015, so no need to replaster it
Point 5
The need to replaster raked ceiling local to front elevation only became known at end of September 2015, when Ridlands found that the glass did not fit
Point 6
CJ Plastering, not Jason, was doing the plastering of the raking ceiling in July, and carried on doing the plastering of the raking ceiling in July, and were down to do the replastering on programmes long after this"
"The precise scope of Mr Marcal's retainer is less important to the determination of this case than it might appear from the statement of case."
It was then accepted at paragraph 17 and 18 of the Defendant's Written Closing Submissions that:
"17. Mr Marcal accepts that he produced the architectural design for the cinema room on legs and that he was responsible for that design meeting the requirements (such as they were) provided by the Claimants. He also accepts that he agreed to co-ordinate contractors and inspect the cinema room works. He accepts that he was obliged to carry out that work with reasonable skill and care.
18. The main dispute between the Claimants and Mr Marcal is whether his design met their requirements and whether they agreed to it. Mr Marcal does not dispute that he was responsible for producing the concept design. He was not responsible for the structural engineering drawings but it does not appear that that allegation is being made against him."
.3 THE EVIDENCE RELATING TO THE "KEY DISPUTE" OR "MAIN DISPUTE"
- on the 6th November 2014
- on the 11th November 2014
- on the 17th March 2015
- on the 19th March 2015
- on the 8th May 2015
and the industrial look with six rather than four columns was included in the drawings emailed to the Claimants on the 8th May and which were approved by the Claimants.
TAKING EACH MEETING IN TURN
the 6th November 2014
the 19th November 2014
the 17th March 2014
the 19th March 2014
i) at that date the 800 drawings had not been completed. In cross-examination the Defendant accepted that the most useful drawings in the 800 series showing the appearance of the scheme post-date the 8th of May 2015;
ii) they were construction drawings and were never intended for discussion of any changed brief.
"The case asserting a critical meeting on the 8th May is another attempt to build a case retrospectively from scant hints in the notes of Mr Marcal."
i) I find that those pictures generally do not show an industrial feel and this case can only be based on one picture of a theatre in Manchester;
ii) I accept Ms Goldie's evidence that she had little or no interest in the pinterest photographs;
iii) I accept her evidence that it was never explained to her that the eventual design could be based upon an industrial look, let alone based upon a photograph of a theatre in Manchester.
However, on one ancillary issue which the architectural experts differed on, I will make findings which, given my findings of fact that the final design was never shown to the Claimants let alone agreed to by them, may not be strictly necessary.
"5. I am an Architect. I obtained my BA in Architecture (RIBA Part 1) from Manchester University in 2001. I then obtained a first class (with commendation) Diploma in Architecture (RIBA Part 2) from the Bartlett School of Architecture, University College, London in 2004, and completed my RIBA Part 3 (with Merit) at London Southbank University in 2006. I am a member of the ARB."
"5.1.9 Mr Dan Marcal is registered with the Architect's Registration Board ("ARB") under registration number 072365G. Please see http://www.architects-register.org.uk/search/name/marcal.
5.1.10 Such registration entitles Mr Marcal to use the protected title "Architect". This title has the meaning given to it by the Architects Act 1997 http://www.legislation.gov.uk/ukpga/1997/22 /pdfs/ukpga 19970022 en.pdf. To gain this title a particular level of training and experience is required. A person registered with ARB is required to abide by the ARB's code of practice. I include a copy of the Code current at the time of Mr Marcel's work in this matter at Appendix 3 to this report. This Code may be referred to as the ARB 2010 Code of Conduct ("ARB 2010").
5.1.11 In my opinion the conduct of Mr Marcal stands to be judged against the standards set out in ARB 2010.
5.1.12 I set out below a copy of sections 4.4 to 4.7 of ARB 2010:
"4.4 You are expected to ensure that before you undertake any professional work you have entered into a written agreement with the client which adequately covers:
- the contracting parties;
- the scope of the work:
- the fee or method of calculating it;
- who will be responsible for what;
- any constraints or limitations on the responsibilities of the parties;
- the provisions for suspension or termination of the agreement;
- a statement that you have adequate and appropriate insurance cover as specified by the Board;
- your complaints-handling procedure (see Standard 10), including details of any special arrangements for resolving disputes (e.g. arbitration).
4.5 Any agreed variations to the written agreement should be recorded in writing.
4.6 You are expected to ensure that your client agreements record that you are registered with the Architects Registration Board and that you are subject to this Code; and that the client can refer a complaint to the Board if your conduct or competence appears to fail short of the standards in the Code.
4.7 You should make dear to the client the extent to which any of your architectural services are being subcontracted."
i) the initial brief not to be recorded in writing;
ii) any design development or changes not to be recorded in writing.
Relying on sample boards, mood boards or pinterest pictures is not sufficient for both architect and client to have clarity as to what has been designed and what was to be built. Having considered the expert evidence of John Perry and Ian Salisbury on this topic, I prefer the evidence of John Perry.
i) no written agreement;
ii) no written brief.
"5.1.21 For such work in my opinion a competent architect would agree a brief in writing with his client(s). I have seen no such written brief in this matter. In the absence of a written brief it was unclear to the claimants what the final design should achieve in terms of accommodation, cost, level of finish and operational requirements.
5.1.22 Equally there is no record of what the architect was trying to achieve for his clients."
"Q. Now, you presumably also accept, Mr Perry, that what an architect is required to do depends on what he has agreed to do with his client, and what the client has asked him to do?
A. Yes, it's commonly called a "brief".
Q. And as part of that, you need to look at both what it was that passed between the parties - so, any discussions, emails or anything written down.
A. Well, what I look for, as an architect, is a brief. A set of instructions agreed between the client and the architect and then a written brief which sets out the basis on which design - for which the design should aim. A brief may change over time, but the brief will be updated over time to reflect how that design was to change.
Q. Well, you are answering a slightly different question. What I am - what I am asking ---
A. I'm sorry.
Q. --- about is a brief, at its most simple, a brief simply reflects the client's requirements, would you agree with that?
A. I agree.
Q. And a client can express those requirements in a number of different ways, would you agree with that?
A. I wou --- I would, yes.
Q. And the purpose of establishing a brief is so that both client and architect understand what the client is requiring?
A. I agree.
Q. And so what you are aiming for is for them to be in agreement?
A. The client and the architect and the brief to be in agreement?
Q. Well, client and architect to agree as to what ---
A. The brief is.
Q. --- the client - exactly. Now, you can then, if you wish, put that in writing, but it does not change the fact that it - that the clai - the client and the architect have already agreed what is to be done.
A. In - in my experience, and in my opinion, if this - building design is a complex matter and if at that early stage what is agreed is not recorded in writing, I - I find it very difficult to see how a project can progress. I - I agree if it's agreed, it's agreed. What is difficult is to know what was agreed down the line because what you - what you do as an architect is you look back down the line to see what was agreed and you look to see how it was expressed in writing, in my experience, but I agree with you to make agreements. I agree with you, you can agree something without writing it down, but it doesn't help in two months' time when you want to know what was it we did agree."
I agree with those comments.
"… as often as not, clients don't know exactly what they want when they start off, except that they have a notion as to what they want, but don't know how to do it. So they go into a journey of exploration with the architect. That's quite normal and an essential part of the architect's duty…"
4 THE ISSUES OF ALLEGED BREACH BY THE DEFENDANT
(1) The scope of the Defendant's engagement
1.1 Whether as the Claimants contend the Defendant acted under an engagement to act as
a) architect and
b) project manager
to completion.
1.2 Whether, as the Defendant contends, the Defendant acted on an "ad hoc" basis:
a) architect and
b) project manager.
1.3 Whether as the Defendant contends, the Defendant's engagement changed to a more limited engagement following the meeting on 9th July 2015, in relation to his position as:
a) architect and
b) project manager.
(2) Issues related to the brief for the cinema design - was the brief properly prepared, documented, and agreed, and were the features which the Claimants dislike in fact approved by them?
2.1 Was there an agreed brief for 6 columns rather than 4?
2.2 Was there an agreed brief for the location and size of the columns?
2.3 Was there an agreed brief for an "industrial feel"?
2.4 Was there an agreed brief for the final form of the glass panelling?
2.5 Was there an agreed brief for visible spider bolts?
2.6 Was there an agreed brief for a wooden box, rather than glass walls?
2.7 Was there an agreed brief for a mechanical trapdoor dependent on electrical power?
2.8 Was there an agreed brief for the staircase up to the cinema?
2.9 Was it necessary to commit the brief to writing, or is the existence or non-existence of a written brief simply a matter of evidence?
2.10 Was the absence of an agreed brief in any of the respects set out above an error which fell below the standard of skill and care?
i) to illustrate;
ii) to record in writing;
iii) to explain;
iv) to seek approval for:
- the six columns rather than the four columns legitimately anticipated by the Claimants;
- the "industrious feel";
- the final form of glass panelling;
- the visable spider bolts;
- the wooden box;
- the mechanical trap-doors dependant on electrical power;
- the staircase up to the cinema.
"68 However, it is clear that the Claimants agreed to the as-built design of the cinema box which included six legs.
68.1 The cinema had been designed initially to be supported by four columns and this was the design included in the design concept drawings discussed with the Claimants in late 2014 and early 2015[6]
68.2 However, the Claimants wanted the cinema to be bigger and after it was re-resized it was necessary for it to be supported by six rather than four columns. These structural design drawings were prepared by Malishev Engineering; Ridlands had sub-contracted the work to Malishev. The Defendant and Ridlands prepared a "soft" programme based on six columns to present to the Claimants on 17 March 2015.
68.3 At a meeting at the Property on 17 March 2015 attended by Ms Goldie, the Defendant and Ridlands, Ms Goldie agreed to six columns and their location; at the meeting the Defendant and Ridlands paced out where the columns would be situated. The Defendant made a note of the meeting in his daybook."
68.4 At a meeting at the Property attended by Mr Freeborn and Ridlands on 19 March 2015 Mr Freeborn confirmed his agreement to the columns and requested that they be pushed as far as possible to the existing wall. The Defendant made a note of the meeting in his daybook.
68.5 Drawings which showed six columns and their location were emailed by the Defendant to Mr Freeborn on 20 March 2015.
68.6 The Claimants were heavily involved in the project, took a keen interest in its design and it was being built at their home. It is not credible for them to suggest that they did not know that six columns were being installed and it is telling that the Claimants made no contemporaneous complaint that there were six rather than four columns.
68.7 The design intent (i.e. the steel/glass aesthetic) was frequently discussed by the Defendant with the Claimants and Ms Goldie in particular. The Defendant created a Pinterest board with various images and the Claimants agreed to the aesthetic."
"One could multiply these examples, but in truth the only meeting which the Defendant continued to say was a meeting at which 6 columns were discussed and agreed was the meeting on 17th March. There are insuperable problems with that theory, apart from the problem that Ms Goldie denies that she was present while 6 columns were marked out in magic marker for her benefit [day 1, page 53]:
(a) the note does not show 6 columns at all. It shows 10, because the columns near the side walls were at that time contemplated as pairs of columns a few feet apart. So we are asked to believe that after objecting to columns she agreed not to 6 columns abut to 10 Q/6869-70, or that the marking out was of 6 columns though 10 are shown on the sketch [day 3, page 40, lines 28-43 line 27]
(b) the number of columns was still 10, and changed to 6 later on, so it was too early to discuss the final form of the columns;
(c) there is no email confirming any discussion of columns with Ms Goldie;
(d) The position and placing of the columns was still in flux for some time later, because the pile positions had to be discussed. Although the intention might have been to put them close to the footings, the precise position of the piles and columns could not be marked out on 17 March."
However, by this stage, the sleek modern design had long disappeared and the Claimants were at that time making the best of a very bad job on the insistence of the Defendant who hoped to persuade the Claimants to grow to like the unapproved industrial wonky design.
(3) Issues related to the defects in the cinema design clearly communicated to the client
3.1 Is the misalignment of the glass a defect?
3.2 Is the cause of the misalignment of the glass a matter of architectural design?
3.3 Is the misalignment of the steel frame a defect?
3.4 Is the absence of a means of changing the lights a defect?
3.5 Is the clash between the top corners of the glass and the roof of the building a defect?
3.6 Is the absence of a means of escape a defect?
3.7 Is the absence of a failsafe in the trapdoor a defect?
3.8 Is there a gap in the soundproofing and lightproofing of the cinema at the trapdoor, and is that gap inappropriate for a private cinema?
3.9 Is the absence of a balustrade protecting the hole over the trapdoor a defect?
3.10 Is the step near the trapdoor a defect likely to cause tripping?
3.11 Is the presence of a steel column close to the foot of the stair a defect?
3.12 Is the absence of a balustrade at the foot of the stair by the steel column a defect?
3.13 To the extent that there are any such defects are they the consequence of acts or omissions of the Defendant in relation to his design obligation?
3.14 Were any such acts or omissions errors which fell below the standard of skill and care?
Addressing these issues in the following order:
3.1 Is the misalignment of the glass a defect?
3.2 Is the cause of the misalignment of the glass a matter of architectural design?
3.3 Is the misalignment of the steel frame a defect?
i) The Claimants have not established that the glass and steel was out of tolerance despite numerous measurements and surveys having been taken. On this issue, I prefer the evidence of Ian Salisbury and his conclusion that the correct standards permit a deviation of 23mm plus an additional fabrication tolerance. Ian Salisbury's measurements clearly show the columns to be within tolerance;
ii) The Claimants have not established a case that the Defendant was responsible for the steel being installed out of tolerance given that:
- the structural designs were produced by Malishev;
- the steel and glass were installed by Ridlands.
3.4 Is the absence of a means of changing the lights a defect?
3.5 Is the clash between the top corners of the glass and the roof of the building a defect?
3.6 Is the absence of a means of escape a defect?
"Means of warning and escape
B1 The building shall be designed and constructed so that there are appropriate provisions for the early warning of fire and appropriate means of escape in case of fire from the building to a place of safety outside the building capable of being safely and effectively used at all material times."
Requirement B1 is followed by guidance. Mr Perry suggested that the guidance was mandatory but this is incorrect and Mr Clay appeared to accept that when cross-examining Mr Salisbury.
"as soon as the roof door was conceived, the intention was that the entire roof door is operable in the event of a fire. That is the premise of the fire escape strategy – that the entire roof door operates in the event of a fire. It's done – it does that by means of a battery back-up, whereby if the fire alarm to the general house or the pool room is activated, either by a person or a smoke detector, there is a link from the fire alarm system to the winch motor which tells the winch motor to open the trapdoor in its entirety in the event of a fire. The escape hatch – the inner hatch that is located in the trapdoor is there – is a means of assuring the occupants that there is another means of escape. It's like a third – it's like an additional safety factor, so the roof door is intended to be operable in the event of a fire, which means you can walk down the stairs freely."
He also thought Building Control might have approved the design because of the proximity of the bottom of the stairs and the final exit door.
I am not convinced that this system was either safe or compliant.
"The advice that's given in the approved document is that the secondary means of escape through an aperture to the place of safety has to be of a minimum size of 450 millimetres by 450 millimetres. In other words, so large that someone reasonably may be expected to obtain passage through it, in other words to pass through it. It is not stated that there should be an escape stair from every inner room. If it – if that were the case then you'd go to New Court or wherever it is that I've been going to see counsel, you would have a myriad of escape staircases coming down from the inner rooms and I was in one yesterday evening. From all the upstairs rooms which are inner rooms and this just does not happen. So, I don't agree with Mr Perry that there is a need under the building regulations for a protective staircase going down and I think that the reason that I say that this is sufficient, adequate, what might be expected and not in the same words as you're describing but reasonable for an architect to provide, that the occasion of a fire is sufficiently rare that the necessity for building that staircase is unnecessary because if it happens you will jump from a window and you will survive."
3.7 Is the absence of a failsafe in the trapdoor a defect?
3.8 Is there a gap in the soundproofing and light proofing of the cinema at the trapdoor, and is the gap inappropriate for a private cinema?
3.9 Is the absence of a balustrade protecting the hole over the trapdoor a defect?
3.10 Is the step near the trapdoor a defect likely to cause tripping?
3.11 Is the presence of a steel column close to the foot of the stair a defect?
3.12 Is the absence of a balustrade at the foot of the stair by the steel column a defect?
3.13 To the extent that there are any such defects are they the consequence of acts or omissions of the Defendant in relation to his design obligation?
3.14 Were any such acts or omissions errors which fell below the standard of skill and care?
Remaining Allegations of Alleged Defects
i) the design makes no provision for differential movement between the cinema box and the Pool House structure;
ii) the glass box is tightly enclosed into the ceiling makes it difficult to paint the ceiling soffit close to the top of the glass wall panels;
iii) there is a spider fixed directly to a steel member;
iv) there is no sealing to the arris junctions which allows in insects and dust which cannot be cleaned;
v) Mr Marcal instructed contractors to install mastic which has sealed in insects and dust; and
vi) wiring visible behind the gaps is unsightly.
In these circumstances, I make no findings in respect of these matters other than noting that they have been abandoned by the Claimants.
(4) Whether the swimming pool should have been waterproofed, and whether it was waterproofed
4.1 Was there water ingress into the swimming pool in 2015 in addition to that caused by the flood of late August 2015?
4.2 If there was such water ingress, was it caused by poor workmanship or failure to follow the design in penetrations installed by Connect, or by the absence of a sufficiently robust design to waterproof the swimming pool?
4.3 Did the Defendant undertake any design or inspection obligations in relation to the swimming pool?
4.4 Were such obligations as the Defendant undertook in relation to the swimming pool discharged by the employment of (i) APS, the swimming pool specialists, or (ii) Connect, the contractors who built a support structure within the pool
4.5 Should the Defendant have specified waterproofing and waterproof fixings for the pool?
4.6 Should the Defendant have identified the poor workmanship of Connect in installing penetrations to the pool?
4.7 Should the Defendant have revised the design in 2015 in the light of the leaks in the swimming pool?
4.8 Were the works undertaken by JBR successful in mitigating the water ingress, in whole or in part?
4.9 If so, are the costs spent on JBR recoverable as costs spent in reasonable mitigation?
4.10 If (the pool is not restored to working condition) is further work (in the amounts agreed by the Quantum experts) necessary to waterproof or ventilate the pool before finishes are laid on the new structure put in by JBR?
1 In October 2014, APS chemically cleaned the pool, tapped into the sump and installed two fully submersible sump pumps and a leak detection system. APS was a specialist swimming pool contractor. The purpose of the sump pump was to remove any water that accumulated in the pool;
2 In around December 2014, Connect installed (i) a damp-proof membrane around the perimeter of the existing pool and (ii) a timber structure comprising tanalised wood to support the new floor for the Pool House.
i) It was reasonable for the Defendant to rely upon the experience and expertise of APS and Connect to carry out the works they did carry out. No further services were required to be deployed by the Defendant to augment these works whether in respect of the high water table or at all;
ii) When the pool was drained, there is no evidence that the Defendant either knew or should have known that the pool was leaking;
iii) What caused the water ingress is far from clear but neither expert suggested that it was caused by any bolts drilled through the bottom of the pool;
iv) If any bolts were drilled through the bottom of the pool, it is clear that the Defendant neither instructed any such drilling or could reasonably be aware of any such drilling;
v) Once the problem arose, the Defendant suggested various solutions, none of which were pursued by the Claimants.
4.1 Was there water ingress into the swimming pool in 2015 in addition to that caused by the flood of late August 2015?
4.2 If there was such water ingress, was it caused by poor workmanship or failure to follow the design in penetrations installed by Connect, or by the absence of a sufficiently robust design to waterproof the swimming pool?
"First it is not clear that bolts were drilled into the bottom of the pool. After being taken to his email dated 30 November 2016 Mr Marcal thought that maybe one bolt had been connected to the bottom of the pool but he was not sure. However,
1 Mr McDermott, of Connect, gave evidence that there was no bolt connections to the bottom of the pool;
2 Mr McDermott was unsure whether the picture at J/116/4475 or J/116/4479 showed knots in the wood or bolts but gave evidence that [if] it was a metal fixing it would have been used to screw to [two] bits of timber together and would not have gone through the pool surface;
3 There are no pictures of any holes in the pool after JBR removed the Connect structure and the experts did not inspect the pool before JBR installed the new structure.
Secondly, even if one or more bolts were drilled into the bottom of the pool by Connect (or someone else) neither expert expressed the view that any water ingress was caused or continues to be caused by a fixing inserted into the bottom of the pool."
4.3 Did the Defendant undertake any design or inspection obligations in relation to the swimming pool?
4.4 Were such obligations as the Defendant undertook in relation to the swimming pool discharged by the employment of (i) APS, the swimming pool specialists, or (ii) Connect, the contractors who built a support structure within the pool
4.5 Should the Defendant have specified waterproofing and waterproof fixings for the pool?
"He passed Connect's work for payment and he had ample opportunity to inspect it."
They have not established on the balance of probabilities that any fixings were put through the base of the pool, let alone that the Defendant acted negligently in failing to identify any such alleged defect.
4.6 Should the Defendant have identified the poor workmanship of Connect in installing penetrations to the pool?
4.7 Should the Defendant have revised the design in 2015 in the light of the leaks in the swimming pool?
4.8 Were the works undertaken by JBR successful in mitigating the water ingress, in whole or in part? And
4.9 If so, are the costs spent on JBR recoverable as costs spent in reasonable mitigation?
i) chose not to accept the advice of the Defendant;
ii) elected to use JBR who did not have the appropriate experience and expertise.
I consider that it is unreasonable to expect the Defendant to fund those works which failed, irrespective of the fact that no act or omission of the Defendant's whether negligent or otherwise caused the works which have failed to be carried out.
4.10 (if the pool is not restored to working condition) Is further work (in the amounts agreed by the Quantum experts) necessary to waterproof or ventilate the pool before finishes are laid on the new structure put in by JBR?
(5) Whether the Defendant failed properly to specify and supervise work to the windows in the main house
5.1 (if not resolved under engagement issues above) Did the Defendant undertake duties to specify the work to the windows?
5.2 (if not resolved under engagement issues above) Did the Defendant undertake duties to inspect the work to the windows?
5.3 How many of the defects in the window schedule which are not common ground between the experts are defects?
5.4 Are the defects in the window schedule matters which the Defendant would have prevented of corrected in 2015 if he had acted with ordinary skill and care in specifying or inspecting the work carried out by Tubridy Builders, and/or DKD the decorators?
5.5 Alternatively are the defects: (1) either matters which have arisen since 2015, or (2) matters which an ordinary architect exercising skill and care would not have prevented or corrected?
Taking each in turn:
5.1 (if not resolved under engagement issues above) Did the Defendant undertake duties to specify the work to the windows?
5.2 (if not resolved under engagement issues above) Did the Defendant undertake duties to inspect the work to the windows?
5.3 How many of the defects in the window schedule which are not common ground between the experts are defects?
5.4 Are the defects in the window schedule matters which the Defendant would have prevented of corrected in 2015 if he had acted with ordinary skill and care in specifying or inspecting the work carried out by Tubridy Builders, and/or DKD the decorators?
5.5 Alternatively are the defects: (1) either matters which have arisen since 2015, or (2) matters which an ordinary architect exercising skill and care would not have prevented or corrected?
(6) Competitive Tendering
6.1 (If not resolved under engagement issues above) did the Defendant undertake to seek 3 tenderers?
and
6.2 (if not resolved under engagement issues above) or did the Defendant, as the Defendant contends, receive instructions to obtain work by negotiation with a single contractor?
6.3 Are there trade contractors who were tendered competitively other than Tubridy builders?
6.4 (In the event that the Claimants are not entitled to wasted costs in any event) are the Claimants entitled to the saving they should have received from negotiated tenders?
6.5 In assessing the amount of any such saving should the 10 to 15% "rule of thumb" agreed by the expert quantity surveyors be reduced further to take account of costs of tender?
(7) Dinesen flooring
7.1 Was the Dinesen flooring poorly stored at the premises of Hutchison?
7.2 (If not resolved under engagement issues above) was the ordering and delivery of the Dinesen flooring within the duties undertaken by the Defendant?
7.3 Was the poor storage of the Dinesen flooring the consequence of an error which fell below the standard of skill and care of an architect project managing the project?
7.4 (In the event that the Claimants are not entitled to the cost of the Dinesen flooring, less salvage value, as wasted cost in any event what is the figure which properly represents the damage caused by poor storage of the Dinesen flooring?
Taking each issue in turn:
7.1 Was the Dinesen flooring poorly stored at the premises of Hutchison?
7.2 (If not resolved under engagement issues above) was the ordering and delivery of the Dinesen flooring within the duties undertaken by the Defendant?
7.3 Was the poor storage of the Dinesen flooring the consequence of an error which fell below the standard of skill and care of an architect project managing the project?
7.4 (In the event that the Claimants are not entitled to the cost of the Dinesen flooring, less salvage value, as wasted cost in any event) what is the figure which properly represents the damage caused by poor storage of the Dinesen flooring?
(8) Other Minor Claims
8.1 Skylights: should the Defendant have appreciated that if there was to be a mezzanine or cinema in the pool hall, there was no reason to replace all four skylights?
8.2 What is the cost of the two extra skylights?
8.3 Delay issues: adjourned at PTR.
8.1 Skylights: should the Defendant have appreciated that if there was to be a mezzanine or cinema in the pool hall, there was no reason to replace all four skylights?
8.2 What is the cost of the two extra skylights?
8.3 Delay issues : adjourned at PTR
(9) The Pool House Works
.5 TIME LOSS AND DAMAGE ALLEGEDLY CAUSED BY THE BREACHES
i) the additional sums they say they spent because the works were not tendered: £150,900[8];
ii) the additional sums they say they spent on design changes caused by Mr Marcal's negligence: £97,497.36[9].
i) the cost of carrying out remedial works to the windows in the main house: £50,000;[10]
ii) the costs of the works carried out by JBR to the swimming pool: £21,099.60[11]
iii) damages for distress and inconvenience: £10,000.
(9) The Claimants' decision to demolish the cinema room.
9.1 Given the Claimants intend to demolish the cinema room, is the reason that it contains features not agreed as part of the brief, and contains defects, or is it, as the Defendant contends, a change of mind on their part?
(1) Did the Claimants agree to the design of the as-built cinema room?
a) If the answer is "yes", then the Claimants are not entitled to any damages in respect of the design claim;
b) If the answer is "no", then the question for the Court is whether the difference was caused by Mr Marcal's negligence. If the answer to that is "yes", then the Court needs to decide whether the cinema room can be made into the design agreed by the Claimants and whether the cost of doing so is reasonable;
(2) Are there any defects in the cinema room? If so, have those defects been caused by the negligence of Mr Marcal? If so, have those defects caused the Claimants a loss? If so, what is the sum of that loss?
"We were promised precision bespoke and high end. This looks cheap and thrown together." (See K/131/5071)
Escape with staircase | £45,600 |
Balustrade | £4,700 |
Trapdoor | £4,200 |
Installing up to date Olive equipment | £58,765 |
Total | £151,065 |
i) redecorate where the corner digs into the plaster at the soffit;
ii) complete the incomplete work;
iii) in relation to the look – just get used to it.
I consider and so find that that approach to mitigation of loss is unreasonable.
(10) Whether the Claimants can recover their wasted costs, and costs of returning to the position they were in at the outset
10.1 In the light of the answers under headings 2, 3, and 9 above, were the Claimants' costs of the cinema project wasted?
10.2 What are the Claimants' wasted costs when they carry out their intention to demolish the cinema? (this issue includes the audio-visual equipment costs which are dealt with by the single joint expert)
(1) £465,625.47 (the sums including 75% of the £140,553.38 paid to Olive Audio Visual said to have been spent in Annexure 1 to the Particulars of Claim);
(2) plus £5,733 (adjustments agreed in the Joint Statement to 1.04, 1.05 and 1.05);
(3) less £29,889.72 withheld by Mr Freeborn from Ridlands;
(4) less £10,710 which is the residual value of the AV equipment;
(5) Total : £430,758.75.
10.3 What is the cost of Option A, returning the pool hall to a working pool?
(1) £74,000 for the removal of the cinema;
(2) £68,000 for repairing the pool house windows; and
(3) £453,000 for the re-instatement of the pool.
(1) £26,000 for the removal of the cinema;
(2) £50,000 for repairing the pool house windows; and
(3) £466,000 for the re-instatement of the pool.
"I have included a comparison of the budgets at Appendix C. Major differences are due to the following:
High quality finishes to the pool house as existed before the works commenced;
Provision of a new integrated spa to replace the unit removed as part of the Works;
Professional fees to help ensure that the design and works are properly designed and constructed;
Inflation on-costs. My estimate was based on costs at 2015 price levels."
(1) I consider that the Claimants would, on any view, be entitled to high quality finishes;
(2) The Claimants are entitled to a new spa to replicate what was previously there;
(3) Professional fees should be incurred for this project;
(4) I consider that Mr Wood's prices from 2015 plus inflation are more appropriate than Mr Farrow's figures based on a 2018 pricing book which does not capture the high quality work the Claimants are entitled to expect. Mr Wood's figures are based on the cost of the 2015 project.
Accordingly, I find that the Claimants should recover in respect of Option A, £542,000, the costs identified by Mr Wood in his Second report at paragraph 2.1.10 (C147/1652).
However, I consider that the option to restore the pool cannot be described as a realistic option flowing from or having been caused by the breaches of duty the Defendant is responsible for. Furthermore, the Claimants' evidence was that they wanted to replace the swimming pool with a function room to entertain their friends and family. The Claimants are entitled to recover the wasted costs of the cinema room and the costs necessary for the function room to be completed. The recovery of the costs to reinstate the swimming pool would not only be unreasonable but would also totally ignore the Claimants' own decision that they wanted to convert the swimming pool into a function room for parties and to entertain their friends and family."
10.4 What is the cost of Option B, hibernating the pool and completing the pool hall as a party room or function room?
(1) £74,000 for the removal of the cinema;
(2) £68,000 for re-pairing the pool house windows; and
(3) £23,500 for the waterproofing, dehumidifying and ventilation.
(1) Mr Woods has corrected the figure of £74,000 to £26,000:
(2) Mr Wood has corrected the figure of £68,000 to £50,000 but that figure only applies to the window works to the main house and is therefore not relevant to the sum claim under Option 2;
(3) Mr Farrow thought the figure of £23,500 was too high. Mr Farrow's figures were £14,000 to £18,000. On this claim, I would wish to err on the side of caution and support the figure of £23,500. On any view, the difference is not unreasonable for the nature of these works.
So, the total for Option B appears to be:
Removal of Cinema £26,000
Waterproofing, de-humidifying and ventilation £23,500
£49,500
The Defendant is only responsible for £26,000 out of the £49,500.
This is the option which the Defendant is responsible for as a result of the negligence in respect of the design and development of the cinema.
10.5 In respect of costs incurred in the past (principally the wasted costs) are the Claimants entitled to interest pursuant to the Senior Courts Act section 35A?
10.6 Are the Claimants entitled to general damages for distress and inconvenience?
(11) Whether the Claimants can only recover damages on some much more limited basis?
11.1 Is the decision to demolish the cinema a failure to mitigate on the part of the Claimants?
11.2 If the Claimants should have mitigated their loss by keeping the cinema, what steps in mitigation (short of demolition of the cinema and reinstatement of the pool house as it was before), should they have taken to complete the cinema and mitigate their loss?
11.3 If the Claimants should mitigate their loss by completing the cinema, what is the cost of the steps which they should take instead of demolition?
11.4 If the cinema is not demolished, are the Claimants entitled to recovery in respect of:
a) the allowance for lack of competitive tendering costs set out above
11.4 (b) If the cinema is not demolished, are the Claimants entitled to recovery in respect of the damage to the Dinesen floor, set out above?
11.4 (c) If the cinema is not demolished, are the Claimants entitled to recovery in respect of the costs of remedying defects in the waterproofing of the pool, set out above?
11.4 (d) If the cinema is not demolished, are the Claimants entitled to recovery in respect of the costs paid to JBR to mitigate the consequences of the water in the pool and the damage to the structure?
11.4 (e) If the cinema is not demolished, are the Claimants entitled to recovery in respect of the costs required to remedy admitted defects?
11.4 (f) If the cinema is not demolished, are the Claimants entitled to recovery in respect of the costs to remedy aesthetic and other defects not admitted by the Defendant?
11.5 Should the remedies for defects short of demolition (where remedies are put forward) follow the suggestions of Mr Salisbury or those of Mr Perry?
a) means of escape, hatch only for the figure agreed by the QS experts, or door with outside staircase, £46,000;
b) trapdoor, complete the existing design, or replace with a new configuration, £39,000;
c) clash with ceiling soffit, redecorate, or replace the glass for £39,000;
d) balustrade (figure agreed by experts £4,700 to £5,700 C/39/1332)
Note 1 Jackson & Powell on Professional Liability, 8th Edition, para 9-013 [Back] Note 2 Jackson & Powell on Professional Liability, 8th Edition, para 9-119 [Back] Note 3 Investors in Industrial Commercial Properties v South Bedfordshire DC; Ellison & Partners and Hamilton Associates (Third Parties) [1986] 1 All E.R 787 CA [Back] Note 4 Jackson & Powell on Professional Liability, 8th Edition, para 9-220 [Back] Note 5 Jackson & Powell on Professional Liability, 8th Edition, para 9-177, 9-180 and 9-183 [Back] Note 6 [DM1/138-145], [A21]; [F/2976] [Back]