![]() |
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | |
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> RGB Plastering Ltd v TAWE Drylining and Plastering Ltd [2020] EWHC 3028 (TCC) (13 November 2020) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2020/3028.html Cite as: 193 Con LR 237, [2020] EWHC 3028 (TCC) |
[New search] [Printable PDF version] [Help]
BUSINESS AND PROPERTY COURTS IN WALES
TECHNOLOGY AND CONSTRUCTION COURT (QBD)
2 Park Street, Cardiff, CF10 1ET |
||
B e f o r e :
Sitting as a judge of the High Court
____________________
RGB PLASTERING LIMITED |
Claimant |
|
- and - |
||
TAWE DRYLINING AND PLASTERING LIMITED |
Defendant |
____________________
Ms Annie Sampson (instructed by DJM Solicitors) for the defendant
Hearing dates: 5 November 2020
____________________
Crown Copyright ©
HH JUDGE JARMAN QC :
"1. The Sub-Contractor shall submit to RGB applications for payment which accurately reflect the sums due to it on the Interim Application Date refer payment schedule...
2. Application for payment must be cumulative and should specify the amount of payment claimed to be due, how that amount is calculated and to what the amount relates. Measurements and substantiation should be produced in support of any application for payment.
3. Should the Sub-Contract[or] submit an application for payment after the relevant Interim Application Date… the interim application will not be considered and no payment will become due to be made by RGB on the Final Date for Payment."
"1. Nothing contained in any approval or consent given by or on behalf of RGB in connection with the Sub-Contract Works shall prejudice or modify or affect or otherwise relieve the Sub-Contractor for any of its obligations under this Sub-Contract.
2. No purported waiver or amendment to these provisions by RGB's management on Site or other project personnel shall be construed as an amendment to these terms and conditions. The Sub-Contractor shall comply with these conditions strictly notwithstanding."
"1. All applications are to be submitted on or before the 'Subcontractor issues application' date, but valued up to the 'RGB-Subcontractor valuation date.'
2. Any applications received after the 28th of each month, will not be considered and will be administered with the following month's payments, unless by formal agreement with the Commercial Manager/Di.
4. All applications must be submitted electronically via the email address [email protected] – It is advisable that where possible a hard copy is also issued via post."
"But it seems to me that, if contractors want the benefit of these provisions, they are obliged, in return to set out their interim payment claims with proper clarity. If the employer is to be put at risk that a failure to serve a payless notice at the appropriate time during the payment period will render him liable in full for the amount claimed, he must be given reasonable notice that the payment period has been triggered in the first place."
"I consider that the document relied upon as an Interim Application must be in substance, form and intent an Interim Application… stating the sum considered by the Contractor as due at the relevant due date and it must be free from ambiguity… If there are to be potentially serious consequences flowing from it being an Interim Application, it must be clear that it is what it purports to be so that the parties know what to do about it and when."
"The interim payment provisions in the Contract reflect the requirements of s. 110A and s. 111 of the Act. Their effect is to require an employer at periodic intervals to pay "the notified sum" by a final date for payment, irrespective of whether or not that sum in fact represents a correct valuation of the work to date. If an employer fails to give relevant notice, irrespective of whether this is by mistake, administrative oversight or any other reason, then a sum for which the contractor has applied becomes immediately contractually payable, even if it is wrong in valuation terms."
"(1) A construction contract shall, in relation to every payment provided for by the contract— …(b) require the payee to give a notice complying with subsection (3) to the payer or a specified person not later than five days after the payment due date.
(3) A notice complies with this subsection if it specifies— (a) the sum that the payee considers to be or to have been due at the payment due date in respect of the payment, and (b) the basis on which that sum is calculated."
"The requirement for "form", "substance" and "intent" has often been repeated in the authorities (see for example Token Construction v Charlton Estates [1973] BLR 48). In construing the document or documents relied upon, the exercise is to assess it against its contextual setting how it would have informed a reasonable recipient - see Mannai Ltd v Eagle Star Ass. Co. Ltd [1997] AC 749 (per Lord Steyn at 772H)."
"There are instances where it can be found that an employer has waived the need for contractor compliance with strict contractual requirements and/or that an estoppel by convention has arisen between the parties. A useful summary of the well-known requirements for an estoppel by convention to exist can be found in The Law of Waiver, Variation and Estoppel (3rd Ed 2012 Wilken & Ghaly) at paragraph 10.01:
"(i) It is not enough that the common assumption upon which the estoppel is based is merely understood by the parties in the same way. It must be expressly shared between them.
(ii) The expression of the common assumption by the party alleged to be estopped must be such that he may properly be said to have assumed some element of responsibility for it, in the sense of conveying to the other party an understanding that he expected the other party to rely on it.
(iii) The person alleging the estoppel must in fact have relied upon the common assumption, to a sufficient extent, rather than merely forming his own independent view of the matter.
(iv)That reliance must have occurred in connection with some subsequent mutual dealing between the parties.
(v) Some detriment must thereby have been suffered by the person alleging the estoppel, or benefit thereby have been conferred upon the person alleged to be estopped, sufficient to make it unjust or unconscionable for the latter to assert the true legal (or factual) position."