![]() |
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | |
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Manor Co-Living Ltd v RY Construction Ltd [2022] EWHC 2715 (TCC) (27 October 2022) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2022/2715.html Cite as: 205 Con LR 226, [2022] EWHC 2715 (TCC) |
[New search] [Printable PDF version] [Help]
BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES
TECHNOLOGY AND CONSTRUCTION COURT (KBD)
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
MANOR CO-LIVING LIMITED |
Claimant |
|
- and - |
||
RY CONSTRUCTION LIMITED |
Defendant |
____________________
James Frampton (instructed by Sheridan Gold LLP) for the Defendant
Hearing date: 19 October 2022
____________________
Crown Copyright ©
Introduction
(1) that by declining to consider, and excluding from his consideration, the Claimant's case that it had had a lawful entitlement to terminate the Contract (for which it did in fact terminate the Contract); the Adjudicator deprived the Claimant of a potential Defence to the Dispute and thereby acted in breach of the requirements of natural justice;
(2) in consequence, the Decision is invalid and of no effect;
Background
'A result of your failure to proceed regularly and diligently, and your failure to remedy the defaults stated in the Notice of Default this letter should be considered Notice that the Contract is terminated with immediate effect in accordance with clause 8.4.2 of the Contract.'
'We acknowledge receipt of an email from Smithers Purslow yesterday, 1 December 2021, at 13:01 enclosing an electronic copy of a letter of 30 November 2021 also from Smithers Purslow, in which amongst other things they purported to give us notice that "the Contract is terminated with immediate effect in accordance with clause 8.4.2 of the Contract".
Any such notice would only be effective if and when it was either delivered by hand or by recorded, signed for or special delivery post, pursuant to clauses 8.2.3 and 1.7.4 of the contract. We have not received a hard copy of the letter delivered in this way, and therefore any such termination pursuant to clause 8.4.2 has not yet occurred.
We would also highlight that any such notice of termination given pursuant to clause 8.4.2 is supposed to be given by you, the employer, not the contract
administrator. We therefore do not believe that Smithers Purslow's email and letter could amount to a valid notice in any event.
Despite these points, when our men attended site this morning they discovered that you have changed the locks and we are now unable to get onto site to carry out the works. Smithers Purslow effectively confirmed this in its email of yesterday when they said "the client has arranged for security to take possession of the site, please do not attempt to gain access without prior arrangement". For the reasons explained above, your and Smithers Purslow's actions are premature, in breach of the contract, and you preventing us access to carry out the works in this way amounts to a repudiatory breach of the contract on your part.
In short, there is no factual basis for you to terminate the contract pursuant to clause 8.4.2, and therefore notwithstanding the procedural points made above, your purported termination is invalid in any event, and as a result also amounts to a repudiatory breach of the contract.
In the circumstances, with us having been locked out of the site, and you clearly no longer wanting us to work on the project, we have no alternative but to inform you that in light of your repudiatory breaches of the contract outlined above, you have brought the contract to an end with immediate effect.
'... Further, even if our client was in repudiatory breach (which is denied), you have not challenged the underlying entitlement to terminate. Our client was always entitled to terminate and would have done so. Your client has therefore suffered no loss because our client's termination can be justified at common law (those rights being expressly reserved: JCT Condition 8.3.1); and, separately, because our client was entitled to and would have terminated the contract in any event. Your client has not claim for damages, because it would never have been permitted to complete the works…'
The Adjudication
'10. For the avoidance of doubt, the only issue that RYC is referring to adjudication is whether MC-L correctly served its notice of termination and/or otherwise complied with the notice requirements contained in clause 8.4 of the Contract, and, if not, the effect of this.
11. The Adjudicator will not be asked to consider whether there were substantive grounds for MC-L to terminate RYC's employment, the substantive content of the notices that MC-L served, or any other procedural irregularities in relation to MC-L purporting to terminate RYC's employment. These other issues will not form part of the dispute that is being referred to adjudication; and RYC reserves the right to refer these issues to adjudication separately in due course.'
a) [MCL] purported to terminate RYC's employment under the Contract prematurely, before the expiry of 14 days from RYC's receipt of notice specifying alleged defaults,
b) in addition, or in the alternative, [MCL] did not otherwise comply with the notice requirements contained in clause 8.4 of the Contract,
c) as a result, [MCL]'s purported termination was wrongful and invalid,
d) [MCL] acted in breach of contract in (i) purporting to terminate RYC's employment and doing so wrongfully, and/or (ii) preventing RYC from accessing site to carry on with the Works, and/or (iii) appointing others to complete the Works in place of RYC,
e) some or all of these actions by [MCL]amounted to repudiatory breaches of the Contract, which were accepted by RYC expressly or impliedly, bringing the Contract to an end.
'RYC also disputes that there were substantive grounds for MC-L to terminate. The grounds cited by MC-L were RYC's failure to progress the works regularly and diligently, and to comply with its obligations under the CDM Regulations; but the CA acknowledged that RYC was entitled to an extension of time to the end of March 2022 [Tab 2 / 3 and 45], and RYC obtained an independent report on health and safety matters at the beginning of November 2021, and actioned the one minor issue identified. RYC also disputes that the notices that the CA issued in relation to the termination were sufficiently clear to be valid. However, this adjudication is not concerned with these substantive issues; the Adjudicator is not asked to consider these; and RYC reserves the right to refer these issues to adjudication separately in due course.'
'5. As explained below, the termination was valid as the exercise of the contractual right under Condition 8.4. In any event MCL is entitled in law to justify that that termination, as an accepted repudiation at common law. Where, as here, the rights consequent upon each method of termination are the same, the same notice (even if expressed to be given under the contractual mechanism) will be capable of operating to terminate both in the exercise of the contractual right, and as an acceptance of a repudiatory breach.
6. The notice of adjudication (in para. 10) purports to confine the scope of this adjudication to the issue of compliance with Condition 8.4. It thereby attempts to preclude the Adjudicator from considering whether (if Condition 8.4 was not operated properly) MCL is entitled to justify the termination as the acceptance of a repudiatory breach. It cannot confine the adjudication in that way.'
'9. The third declaration sought in this adjudication, is that MCL's termination was wrongful and invalid, and amounted to a repudiatory breach. The Adjudicator cannot reach that conclusion without considering whether MCL had any lawful entitlement to terminate, and whether it exercised that right. The issues in this adjudication, therefore, concern not simply the meaning and procedural requirements of Condition 8.4, but the substantive entitlement to terminate and whether that has been properly effected on any basis.'
(1) was MCL entitled to terminate, whether on a ground specified by Condition 8.4, or because RYC had repudiated the Contract? ("the Substantive Entitlement")
(2) did MCL properly terminate RYC's employment under the Contract, in accordance with Condition 8.4? ("the Condition 8.4 Termination Issue")
(3) if not, did the termination amount to an acceptance of a repudiatory breach? ("the Repudiation Issue")
'66. To terminate at common law, the claimant must establish: (i) that the defendant was in repudiatory breach of the contract, and (ii) a communicated decision to bring the contract to an end, i.e. his acceptance of the repudiation.'
'2.2 if RYC is correct on point 2.1 above, then MC-L failed to comply with the requirements for a valid termination of RYC's employment under the Contract and MC-L was itself in repudiatory breach. RYC is therefore entitled to the relief sought by RYC in this adjudication, subject only to the second issue. The second issue is that MC-L contends that if MC-L failed to operate the clause 8 provisions correctly, its termination letter received on 1 December 2021 may be justified as constituting the acceptance of a repudiatory breach by RYC. RYC's position is that that is not so as a matter of fact and law, without it being necessary to investigate whether there was in fact any repudiatory breach;
2.3 repudiatory breach and the substance of MC-L's contention that RYC was in repudiatory breach (which is not within the scope of the adjudication but is in any event denied);'
'38. It is clear from DACB's letter dated 25 March 2022 (see paragraph 31 above) that as at the date of 25 March MCL had not accepted what it claims to be RYC's repudiatory breach(es) of contract as the letter confirms that MCL
"... was always entitled to terminate and would have done so. Your client has therefore suffered no loss because our client's termination can be justified at common law (those rights being expressly reserved: JCT Condition 8.3.1); and, separately, because our client was entitled to and would have terminated the contract in any event." [Emphasis Added]
39. I consider that in its submissions MCL recognises that there was (and is) no express acceptance of what it claims to be RYC's repudiatory breaches as at paragraph 5 of the Response it says:
'As explained below, the termination was valid as the exercise of the contractual right under Condition 8.4. In any event MCL is entitled in law to justify that that [sic] termination, as an accepted repudiation at common law. Where, as here, the rights consequent upon each method of termination are the same, the same notice (even if expressed to be given under the contractual mechanism) will be capable of operating to terminate both in the exercise of the contractual right, and as an acceptance of a repudiatory breach.'
'52. Applying the test as set out in Vannin, it is my view and I so find that the reasonable recipient of the letter dated 11 November 2021 from Smithers Purslow would have understood, as expressly stated by the letter itself, that it was a notice given in accordance with clause 8.4 of the Contract (Termination by Employer) and no more.
53. As noted above, I have not been directed to any formal acceptance of what MCL now alleges to be RYC's repudiatory breaches (other than as now advanced in the submissions in this adjudication).
…
57. Therefore, in respect of MCL's reservation as to my having jurisdiction, I consider that nothing has been brought to my attention that would lawfully deprive me of jurisdiction to decide this dispute.
58. In respect of RYC's request for me to provide my non-binding views on MCL's 'substantive case as to alleged repudiatory breach' I consider that such is not a defence to the matter in dispute and therefore is as stated by RYC to be 'outwith the scope of this adjudication.'
(1) The Adjudicator engaged substantively with the question of whether there had been an effective communication of acceptance of repudiatory breach, the second of the two necessary elements identified by MCL as a basis of establishing common law termination.
(2) He concluded in terms that there was no effective communication.
(3) He therefore concluded that there could be no common law repudiation (and thus no defence of common law repudiation).
(4) On the basis that common law repudiation was not a 'defence' to the matter in dispute, he considered that it was 'outwith the scope of this adjudication'.
'86. Given my decision as to the extent of my jurisdiction I cannot and do not make any findings as to the grounds upon which MCL claim to support the allegation of repudiatory breach on the part of RYC. However, that leaves open the issue as to whether MCL's purported termination of RYC's employment under the Contract is to be equated to acceptance of (what is alleged to be) RYC's repudiatory breaches?
87. I have noted above paragraph 6-121 of Keating, the relevant part states:
It may, however, depend on the order in which the alternatives are effected. An acceptance of repudiation followed in the alternative by a contractual determination expressed to be without prejudice to the acceptance of repudiation might achieve the contractual determination if there was held to have been no repudiation to accept ...
88. It seems to be as a matter of principle that if an ineffective acceptance of repudiation followed in the alternative by a contractual determination can provide a lawful acceptance, then (in the absence of any authority being provided by the parties or found by me) it seems reasonable and logical that an ineffective contractual determination followed by acceptance of repudiation can also provided a lawful acceptance, but subject to "... words or conduct which [properly] amount to a renunciation": paragraph 27-049 of Chitty.
89. Paragraph 27-050 of Chitty states:
The renunciation must be "made quite plain". In particular, where there is a genuine dispute as to the construction of a contract, the courts may be unwilling to hold that an expression of an intention by one party to carry out the contract only in accordance with his own erroneous interpretation of it amounts to a breach which entitles the other party to terminate performance of the contract; and the same is true of a genuine mistake of fact or law. Even the giving of notice of rescission, or the commencement of proceedings by one party claiming rescission of the contract, does not necessarily amount to a breach which entitles the other party to terminate further performance of the contract, since such action may be taken in order to determine the respective rights of the parties, and so not evince an intention to abandon the contract. On the other hand, it is, generally, no defence for a party who is alleged to have committed a breach which entitles the other party to terminate the contract to show that he acted in good faith. The courts have struggled to reconcile the latter proposition with their reluctance to conclude that a party who has acted in good faith but was mistaken has thereby committed a breach which entitles the other party to terminate the contract.
[He then quotes from RYC's emails of 9 November and letter of 11 November 2021]
…
92. I do not read RYC's e-mail dated 9 November and letter of 11 November 2021 as exhibiting an absolute refusal to continue with the Works and in many respects the correspondence shows that in circumstances where RYC considered it is entitled to extensions of time9 (and possibly payment for loss and expense) it cannot be said that RYC was not trying to adhere to the Contract.
93. Accordingly, I find that even if MCL was entitled to determine the contract by reliance on the invalid contractual termination letter dated 11 November 2021, it cannot be said, in my view, that RYC was in repudiatory breach on the ground relied on by MCL at paragraph 71 of its Response.
(3) Was MCL's action of taking / re-taking possession of the site on 1 December 2021 an act of repudiation?
94. As noted on the chronology above, with the CA's letter dated 30 November 2021 (but sent by e-mail and hand delivered to RYC on 1 December 2021) the CA's accompanying e-mail confirmed that:
'The client has arranged for security to take possession of the site, please do not attempt to gain access without prior arrangement. We can organise a convenient time over the coming days for tools and belongings to be collected and a meeting to discuss the final account.'
95. The clear intent of the CA's e-mail noted above was to bar RYC from the site, thus rendering impossible any further performance by RYC.'
(1) In relation to 14(a), that MCL sought prematurely, that is before the expiry of the 14-day period in clause 8.4.2, to terminate the Contract;
(2) In light of his decision at (1) above, that such a finding as requested by RYC at 14(b) was not necessary;
(3) In relation to 14(c), that MCL's purported termination of the Contract, for the reason that it was premature, was of no effect.
(4) In relation to 14(d), that MCL wrongly and in breach of contract prevented RYC from accessing the site to carry out the Works.
(5) In relation to 14(e), that MCL's breach of contract noted in 4 above was repudiatory and which was accepted by RYC.
The Parties' contentions
(1) The relief sought by RYC included declarations which went beyond merely the validity of the contractual termination. They required a determination of whether MCL was itself in repudiatory breach by its actions (see in particular relief sought at paragraph 14(d) and (e) of the Notice of Adjudication);
(2) In order to determine whether MCL was in repudiatory breach of contract, it was necessary in light of the defence raised to consider not just whether it had successfully terminated the contract under the contract provisions, but also whether it had successfully terminated the contract at common law;
(3) The inclusion of this latter issue could not be excluded by RYC, either by the way the Notice of Adjudication was framed, or by subsequent requests purporting to withdraw relief;
(4) At RYC's invitation, and for tactical reasons, the issue of whether MCL had a substantive entitlement to terminate was deliberately not decided by the Adjudicator;
(5) Although the Adjudicator rejected the contention that the Termination Notice amounted in fact to a communication of acceptance of repudiatory breach, he did go on explicitly to accept that the subsequent retaking of possession demonstrated a clear intention to bar RYC from site, which amounted to a valid acceptance of repudiatory conduct. Having done so, he failed to consider the preceding issue of substantive repudiatory conduct, because he had wrongly determined that that question was outside of his jurisdiction (at the tactical invitation of RYC);
(6) Whilst MCL accepts that the Adjudicator rejected the 'renunciation' case advanced by MCL on its substantive merits, this contrasts with the failure to have considered the substantive repudiation case;
(7) Had the substantive defence been considered, it could have provided a complete defence to the declarations (d) and (e) that he granted, and his deliberate decision not to do was a serious and material breach of natural justice.
(1) At the correct level of abstraction, and fairly construed, the Adjudicator determined what was asked of him in relation to MCL's alternative case, namely whether they had successfully terminated at common law. He concluded that they had not. The complaint made relates to sub-issues or reasoning and is not a proper basis for a conclusion that natural justice has been breached;
(2) A fair reading of the Decision is that he dealt with both the repudiation case and the renunciation case;
(3) The Adjudicator did not make any finding that MCL's conduct amounted to acceptance of repudiatory conduct, or if he did, it was subject to the issue of a preceding renunciation (which he substantively rejected);
(4) The case of conduct constituting acceptance (as opposed to the Notice of Termination) was not a case run in the adjudication, and any failure on the part of the Adjudicator to appreciate the case or fail to deal with common law repudiation on this basis was (a) inadvertent and/or (b) a failure caused by MCL's failure to take the point, and as such cannot amount to a breach of natural justice.
The Legal Principles
'i) A referring party is entitled to define the dispute to be referred to adjudication by its notice of adjudication. In so defining it, the referring party is entitled to confine the dispute referred to specific parts of a wider dispute, such as the valuation of particular elements of work forming part of an application for interim payment.
ii) A responding party is not entitled to widen the scope of the adjudication by adding further disputes arising out of the underlying contract (without the consent of the other party). It is, of course, open to a responding party to commence separate adjudication proceedings in respect of other disputed matters.
iii) A responding party is entitled to raise any defences it considers properly arguable to rebut the claim made by the referring party. By so doing, the responding party is not widening the scope of the adjudication; it is engaging with and responding to the issues within the scope of the adjudication.
iv) Where the referring party seeks a declaration as to the valuation of specific elements of the works, it is not open to the responding party to seek a declaration as to the valuation of other elements of the works.
v) However, where the referring party seeks payment in respect of specific elements of the works, the responding party is entitled to rely on all available defences, including the valuation of other elements of the works, to establish that the referring party is not entitled to the payment claimed.
vi) It is a matter for the adjudicator to decide whether any defences put forward amount to a valid defence to the claim in law and on the facts.
vii) If the adjudicator asks the relevant question, it is irrelevant whether the answer arrived at is right or wrong. The decision will be enforced.
viii) If the adjudicator fails to consider whether the matters relied on by the responding party amount to a valid defence to the claim in law and on the facts, that may amount to a breach of the rules of natural justice.
ix) Not every failure to consider relevant points will amount to a breach of natural justice. The breach must be material and a finding of breach will only be made in plain and obvious cases.
x) If there is a breach of the rules of natural justice and such breach is material, the decision will not be enforced.'
(1) the Court must assess the correct level of abstraction at which to consider the question the adjudicator was required to determine (whether by way of referred claim or proffered defence), and should not be distracted by minor sub-issues. However, failure to consider a critical or fundamental element of a defence (even if it may properly be described as a sub-issue) may make the decision unenforceable;
(2) the Court must bear in mind the distinction between (a) considering an asserted defence and concluding it is not tenable and (b) deciding not to consider an asserted defence at all. The former is unlikely to be a breach of natural justice whereas the latter may well be;
(3) the distinction between a deliberate or conscious decision to exclude consideration of a defence and an inadvertent omission is a relevant consideration, but it is not determinative. Of much more importance is the gravity of the omission;
(4) whilst a relevant factor may also be whether an error was brought about by tactical manoeuvring by the claiming party, this will usually be at most a secondary consideration;
(5) it is necessary to look at the substance of the decision rather than the form.
Was there a breach of natural justice?