[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Associated Newspapers Ltd v Buckingham Group Contracting Ltd (Cost Budgeting) [2022] EWHC 2767 (TCC) (02 November 2022) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2022/2767.html Cite as: [2022] Costs LR 1659, [2022] EWHC 2767 (TCC) |
[New search] [Printable PDF version] [Help]
BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES
TECHNOLOGY AND CONSTRUCTION COURT (KBD)
Rolls Building London, EC4A 1NL |
||
B e f o r e :
Sitting as a Deputy High Court Judge
____________________
ASSOCIATED NEWSPAPERS LIMITED |
Claimant |
|
- and – |
||
BUCKINGHAM GROUP CONTRACTING LIMITED |
Defendant |
|
And Between: |
||
BUCKINGHAM GROUP CONTRACTING LIMITED |
Part 20 Claimant |
|
-and- |
||
AMTRUST EUROPE LIMITED |
Third Party |
|
-and- |
||
ZURICH INSURANCE PLC |
Fourth Party |
|
-and- |
||
LAVENHAM UNDERWRITING LIMITED SAMPFORD UNDERWRITING LIMITED GAI INDEMNITY LIMITED Being members of LLOYDS SYNDICATE 2468 |
Fifth Party |
|
-and- |
||
LIBERTY MUTUAL INSURANCE EUROPE SE |
Sixth Party |
____________________
Ben Patten KC (instructed by Weightmans LLP) for the Defendant and Part 20 Claimant
Neil Hext KC (instructed by Womble Bond Dickinson LLP) for the Third Party (in relation to "insurance matters")
Simon Henderson (instructed by Keoghs LLP) for the Third to Sixth Parties (in relation to "Collier Defence matters")
Robert Stokell (instructed by DAC Beachcroft LLP) for the Fourth to Sixth Parties (in relation to "insurance matters")
Hearing date: 7 October 2022
____________________
Crown Copyright ©
Mr Roger ter Haar KC :
Background
The Parties
The contracts, ownership of the Site, and the Works
The Alleged Defects
These Proceedings
(1) In breach of the terms of the Building Contract and / or negligently, BGCL:
(a) failed to properly investigate the ground conditions at the site;
(b) failed to obtain and / or properly consider or follow recommendations and advice in relation to ground conditions;
(c) failed to include in its design piling measures or to take other steps (such as ground strengthening measures) that were necessary to prevent excessive settlement given the ground conditions of the Site.
(2) Alternatively, the defects at the Site (or certain of them) arise from workmanship failures by BGCL.
(3) As designed and constructed by BGCL, and in breach of express and implied terms of the Building Contract, the external parts of the Works are not fit for purpose.
(4) BGCL is liable to ANL in damages for inter alia the costs of certain temporary repair works and a permanent remedial scheme, which ANL is to set out in a Schedule of Loss to be served on the other parties within 28 days of the CCMC.
(1) BGCL accepts that some differential settlement has occurred but says that it is not as severe as ANL suggests, and that any future differential settlement will be minimal.
(2) BGCL accepts that repairs are required to the Works but denies that the Works are unfit for their intended purpose.
(3) BGCL does not positively aver that its design for the external elements of the Works was competent, but disputes ANL's allegations as to what precisely the design for the external portion of the Works should have included in order to discharge BGCL's design obligations under the Building Contract.
(4) BGCL says that a limited remedial scheme would be sufficient to remedy any defects in the Works.
(5) BGCL contends that ANL's claim is statute barred.
(1) The Collier Insurers say that there was a breach of the duty of fair presentation. The Third Party says that but for that breach it would have included in its contract with Collier an exclusion in respect of any claim arising out of the Collier Appointment. The Fourth to Sixth Parties say that they would not have entered into their insurance contracts at all but for that alleged breach, alternatively that they would have entered on different terms.
(2) The Collier Insurers say that at the inception of their respective insurance contracts, Collier was aware of circumstances giving rise to BGCL's claim, and that that claim is excluded.
(3) The Third Party says that Collier failed to notify the Third Party of its claim within the time required by its contract with Collier, and that Collier is not entitled to an indemnity under that contract as a result. The Third Party and the other Collier Insurers also say that Collier's notification may have been insufficient to encompass BGCL's claim.
Representation
Costs Budgets of BGCL and the Collier Insurers
Applicable principles
(1) Where costs budgets have been filed and exchanged the court will make a costs management order unless it is satisfied that the litigation can be conducted justly and at proportionate cost in accordance with the overriding objective without such an order being made: CPR 3.15(2).
(2) The court may not approve costs incurred before the date of any costs management hearing, but may record its comments on those costs and take those costs into account when considering the reasonableness and proportionality of budgeted costs: CPR 3.17(3).
(3) A costs management order must record the extent to which the budgeted costs are agreed between the parties. In respect of the unagreed budgeted costs, it must record the court's approval after making appropriate revisions: CPR 3.15(2)(a)-(b).
(4) When reviewing unagreed budgeted costs, the court will not undertake a detailed assessment in advance, but rather will consider whether the budgeted costs "fall within the range of reasonable and proportionate costs": CPR PD3E, paragraph 12.
(5) A costs management order concerns the totals allowed for each phase of the budget, and while the underlying detail in the budget for each phase used by the party to calculate the totals claimed is provided for reference purposes to assist the court in fixing a budget, it is not the role of the court in the costs management hearing to fix or approve the hourly rates claimed in the budget: CPR 3.15(8).
"9. The Costs Budgeting regime has led to disagreement about the extent of detailed argument that is appropriate when considering Precedent Hs. Experience in the TCC has shown that most costs budgeting reviews can and should be carried out quickly and with the application of a fairly broad brush. Only exceptionally will it be appropriate or necessary to go through a Precedent H with a fine tooth-comb, analysing the makeup of figures in detail. For reasons which will become apparent, however, this is an exceptional case which justifies a more detailed approach. The justification lies in the fact that the aggregate sum being put forward for approval is so disproportionate to the sums at stake or the length and complexity of the case that something has clearly gone wrong. The court's interest in maintaining a robust and just approach to costs management requires an investigation into what has gone wrong for two reasons. First, to enable it to reach a figure which it prepared to approve; and, second, so that the court's determination to exercise a moderating influence on costs is made clear.
"10. The parties are agreed that the approach adopted by Coulson J in CIP Properties (AIPT) Ltd v Galliford Try Infrastructure Ltd [2015] EWHC 481 (TCC) is applicable in the circumstances of this case. I also agree, though Coulson J's approach may better be seen as a guide rather than a straightjacket. On the facts of that case, he considered:
"i) The Proportionality of claimant's Costs Budget [37-45];
"ii) The Reasonableness of the claimant's Costs Budget [46-82];
"iii) Summary of Options [83-95];
"iv) Conclusions on the Available Options [96-98].
"I shall follow his lead."
"The final vice [in the judgment under appeal], which is apparent from what I have already said, is that the process of setting the budget, and then the question at a detailed assessment of comparing how the budget was spent, becomes something which is being micromanaged by the court. That is something to be avoided. Paragraph 7.3 of the Practice Direction indicates that the ultimate aim is to arrive at budgeted costs which fall within the range of reasonable and proportionate costs. None of that means, of course, that it is not appropriate for the Master, when setting the budget and approving the figures, to look at the constituent parts. Indeed, it is impossible to see how a Master can sensibly come to figures without looking to see how they have been calculated by the party putting them forward. In so doing, the Master should use his or her experience as to how much time should be spent, the type of people who should be doing the relevant work, and his or her experience of hourly rates. However, all of those matters feed in to a finding as to the specific number of hours which are to be spent in the future, or a finding as to [a] specific figure for disbursements to be incurred in the future."
"In deciding the reasonable and proportionate costs of each phase of the budget the court will have regard to the factors set out at Civil Procedure Rules 44.3(5) and 44.4(3) including a consideration of where and the circumstances in which the work was done as opposed to where the case is heard."
"Costs incurred are proportionate if they bear a reasonable relationship to –
"(a) the sums in issue in the proceedings;
"(b) the value of any non-monetary relief in issue in the proceedings;
"(c) the complexity of the litigation;
"(d) any additional work generated by the conduct of the paying party; and
"(e) any wider factors involved in the proceedings, such as reputation or public importance."
"The court will also have regard to –
"(a) the conduct of all the parties, including in particular –
"(i) conduct before, as well as during, the proceedings; and
"(ii) the efforts made, if any, before and during the proceedings in order to try to resolve the dispute;
"(b) the amount or value of any money or property involved;
"(c) the importance of the matter to all the parties;
"(d) the particular complexity of the matter or the difficulty or novelty of the questions raised;
"(e) the skill, effort, specialised knowledge and responsibility involved;
"(f) the time spent on the case;
"(g) the place where and the circumstances in which work or any part of it was done; and
"(h) the receiving party's last approved or agreed budget."
The Claimant's Proposed Costs Budget
ANL | BCGL |
Third Party | Fourth/Fifth/Sixth Party | |
Pre-action | 198,434.10 | 140,594.78 | 0 | |
Issue / SoC | 326,200.10 | 131,499.30 | 71,249.50 | 82,161.00 |
CMC | 90,812.25 | 23,003.50 | 37,464.00 | 15,353.50 |
Disclosure | 284,733.25 | 138,090.00 | 24,745.50 | 39,678.00 |
Witness S | 152,749.00 | 57,415.50 | 12,720.00 | 16,070.00 |
Experts | 671,381.63 | 328,426.00 | 43,650.00 | 33,615.00 |
PTR | 85,135.00 | 24,900.00 | 25,440.00 | 10,895.00 |
Trial Prep | 665,330.00 | 514,033.00 | 401,025.00 | 136,884.00 |
Trial | 597,275.00 | 316,585.00 | 133,580.00 | 142,810.00 |
ADR / Settlement | 109,108.00 | 103,215.50 | 20,680.00 | 30,390.00 |
Contingent A | 0 | 96,046.00 | 0 | 0 |
Contingent B | 0 | 0 | 0 | |
254,271.15[2] | 762,813.45[3] | |||
Total | 3,181,158.17 | 1,873,808.58 | 1,024,825.15 | 1,270,669.95 |
Fee Earner Grade | ANL | BCGL | Third Party | Fourth/Fifth/Sixth Party |
Guideline |
Partner Grade A |
£801 | £215 | £295 | £365 | £512 |
Senior Associate Grade B |
£648 | £180 | £265 | £280 | £348 |
Senior Associate Grade C |
£499.50 | £160 | £245 | £180 | £270 |
Associate Solicitor Grade C |
£360 | £160 | £245 | £180 | £270 |
Trainee Grade D |
£216 | £150 | £140 | £186 | |
Paralegal Grade D |
£203 | £110 |
ANL | BGCL's offer | |
Disclosure | 231,880.00 | 138,090.00 |
Witnesses | 151,680.00 | 67,750.00 |
Experts | 559,500.00 | 298,500.00 |
PTR | 85,135.00 | 41,925.00 |
Trial Prep | 665,330.00 | 455,250.00 |
Trial | 597,275.00 | 227,750.00 |
ADR / Settlement | 109,108.00 | 68,358.00 |
Total | 2,399,908.00 | 1,378,658.00 |
Note 1 The Third Party is the primary layer insurer. The Fourth to Sixth Parties are the excess layer insurers. [Back]