[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> FK Construction Ltd v ISG Retail Ltd [2023] EWHC 1042 (TCC) (05 May 2023) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2023/1042.html Cite as: [2023] EWHC 1042 (TCC), 208 Con LR 82 |
[New search] [Printable PDF version] [Help]
BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES
TECHNOLOGY AND CONSTRUCTION COURT (KBD)
Fetter Lane London, EC4A 1NL |
||
B e f o r e :
____________________
FK CONSTRUCTION LIMITED |
Claimant |
|
- and - |
||
ISG RETAIL LIMITED |
Defendant |
____________________
Simon Hale (instructed by Mantle Law (UK) LLP) for the Defendant
Hearing date: 19 April 2023
____________________
Crown Copyright ©
This judgment was handed down remotely by email at 10.00 am on Friday 5 May 2023 by circulation to the parties or their representatives and released to the National Archives.
Mrs Justice Joanna Smith:
BACKGROUND
The Wood Decision
Other Adjudication Decisions relating to Project Barberry
a. The Shawyer Decision of 17 November 2022: this concerned FK's AFP 14 for the period July 2022 and thus preceded the Wood Decision. The Shawyer Decision determined that AFP 14 was valid, that a PLN served by ISG was invalid and that ISG must pay to FK the sum of £1,489,651.32 plus VAT together with interest. ISG has not paid this sum, but it has issued Part 8 proceedings ("the Barberry Part 8 Proceedings") alleging breach of natural justice and contending that AFP 14 did not constitute a valid payee's notice or default payment notice because it was not a notification given "in accordance with the contract" as required by section 110B(4) of the 1996 Act ("the s.110B(4) Issue"). The Barberry Part 8 Proceedings are due to be heard on 13 and 14 June 2023 and are listed to be heard together with another set of Part 8 proceedings on another project involving the same parties to which I shall return in a moment. It is common ground that the s.110B(4) Issue also arises in connection with the Wood Decision.
b. The Ribbands Decision of 7 March 2023: this concerned FK's AFP 13 for the period June 2022. The Ribbands Decision determined that ISG had failed to issue either a valid PN or a valid PLN in respect of AFP 13 and accordingly that ISG must pay £1,558,641.17 plus VAT together with interest. However, this decision was made subject to the operative parts of the Shawyer and Wood Decisions not being complied with and "if not paid, subsequently declared unenforceable by the English Courts". It is common ground that the Ribbands Decision is therefore conditional upon the outcome of the Barberry Part 8 Proceedings.
c. The Molloy Decision of 14 April 2023: this decision only became available very shortly before the hearing and after preparation of the skeleton arguments. It concerned a request by ISG for a gross valuation of the Sub-Contract as at 28 February 2023. The Molloy Decision determined a gross valuation of £3,736,679.72 and split the costs of the adjudication between the parties, with ISG to pay 60% and FK to pay 40%. Taken at face value, and given that ISG has already paid £2,829,941.55 in respect of the Sub-Contract works, this would suggest that FK's further entitlement from ISG is £906,738.20. The timing of the Molloy Decision led to both parties making new submissions at the hearing which had not been entirely foreshadowed in their skeleton arguments.
Project Triathlon
a. The Aeberli Decision of 20 March 2023, pursuant to which it was decided that ISG was entitled to terminate FK's employment under the Triathlon Sub-Contract (which it did by notice on 7 October 2022) and that ISG was entitled to be indemnified by FK in the sum of £763,428.28. FK says that it intends to challenge the Aeberli Decision on jurisdictional grounds by way of Part 8 proceedings but it has not yet issued any such proceedings.
b. The Ribbands (Triathlon) Decision of 30 March 2023 which decided (amongst other things) that ISG was entitled to the sum of £105,011.53 payable by FK to ISG by 12 April 2023. FK accepts that this decision is enforceable but has not yet paid the sum due.
c. The Jensen Decision of 5 April 2023 which decided that FK was entitled to a payment of £801,819.13 from ISG by 12 April 2023. ISG has not yet made any payment pursuant to this decision. No jurisdictional challenges were made to the adjudicator and none has been intimated subsequently.
THE APPLICATION
The Applicable Legal Principles
a. The general position is that adjudicators' decisions which direct the payment of money by one party to the other are to be enforced summarily and expeditiously unless there is a valid jurisdictional or natural justice ground which renders enforcement inappropriate. No set off or withholding against payment of that amount should generally be permitted (YCMS Ltd v Grabiner [2009] EWHC 127 (TCC) at [63] and Thameside Construction Co Ltd v Stevens [2013] EWHC 2071 per Akenhead J at [24(c)]). As Jackson J observed in Interserve Industrial Services Ltd v Cleveland Bridge UK Ltd [2006] EWHC 741 (TCC), a case in which he held that there was no entitlement on the facts to a set off, at [43]:
"…Where parties to a construction contract engage in successive adjudications, each focused upon the parties' current rights and remedies, in my view the correct approach is as follows. At the end of each adjudication, absent special circumstances, the losing party must comply with the adjudicator's decision. He cannot withhold payment on the ground of his anticipated recovery in a future adjudication based upon different issues…".
b. The rationale for the approach taken by Jackson J in Interserve may be found in [46] of his judgment, where he observed that the "bizarre consequence" of the argument that set offs were appropriate where there was a series of consecutive adjudications between the same parties would be that:
"no adjudicator's decision is implemented; each award simply takes its place in the running balance between the parties. Such an outcome is plainly contrary to the policy of the 1996 Act".
c. There are, however, at least three limited exceptions to this general position:
i. a first, "relatively rare", exception will be where there is a specified contractual right to set off which does not offend against the statutory requirement[3] for immediate enforcement of an adjudicator's decision (Thameside at [24(d)]). This exception will be rare because, as Mantell LJ made clear in Ferson Contractors Ltd v Levolux AT Ltd [2003] BLR 118 at [30], the contract must be construed so as to give effect to the intention of Parliament (as set out in the 1996 Act) rather than to defeat it; if the set off provision offends the requirement for immediate enforcement of the adjudicator's decision it should be struck down as unenforceable (see also BexHeat at [69]);
ii. a second exception may arise where it follows logically from an adjudicator's decision that the adjudicator is permitting a set off to be made against the sum otherwise decided to be payable (see Thameside at [24(e)] and Balfour Beatty Construction v Serco Limited [2004] EWHC 3336 (TCC) per Jackson J at [53]). This will require an analysis of the decision itself (see Thameside at [16] and [24(d)]), but if an adjudicator has decided that a certain sum must be paid by one party to another, it is difficult to see how there could be room for an allowable set off (see the analysis in Thameside at [23] of Squibb Group Ltd v Vertase FLI Ltd [2012] BLR 408). However, where an adjudicator is simply declaring that an overall amount is due or is due for certification, rather than directing that a balance should actually be paid, a legitimate set off or withholding may be justified when that amount falls due for payment or certification in the future (Thameside at [24(d)]);
iii. a third exception may arise in an appropriate case and at the discretion of the court, where there are two valid and enforceable adjudication decisions involving the same parties whose effect is that monies are owed by each party to the other (HS Works Ltd v Enterprise Managed Services Ltd [2009] EWHC 729 (TCC) per Akenhead J at [40]; and JPA Design and Build Limited v Sentosa (UK) Limited [2009] EWHC 2312 (TCC)).
"did not consider that the fact that a Third Decision has been reached which on its face allows to the defendants a net recovery is a special circumstance which justifies departing from the general rule that valid adjudicator's decisions should be enforced promptly. Things might be different if there were effectively simultaneous adjudications and decisions".
"(a) First, it is necessary to determine at the time when the court is considering the issue whether both decisions are valid; if not or if it cannot be determined whether each is valid, it is unnecessary to consider the next steps.
(b) If both are valid, it is then necessary to consider if, both are capable of being enforced or given effect to; if one or other is not so capable, the question of set off does not arise.
(c) If it is clear that both are so capable, the court should enforce or give effect to them both, provided that separate proceedings have been brought by each party to enforce each decision. The court has no reason to favour one side or the other if each has a valid and enforceable decision in its favour.
(d) How each decision is enforced is a matter for the court. It may be wholly inappropriate to permit a set off of a second ?nancial decision as such in circumstances where the First Decision was predicated upon a basis that there could be no set off".
"(a) Both adjudicators' decisions are valid and enforceable.
(b) The parties and the court are required to give effect to both decisions."
"it would be pointless, at least administratively, for Enterprise to hand over the net sum (allowing for the belated payment) due pursuant to the First Adjudication decision to be followed by HSW having to hand back all or the bulk of what had just been paid to it to Enterprise".
THE PROPOSED SET OFF IN THIS CASE
The Molloy Decision
a. Validity: In my judgment, ISG falls at the first hurdle of validity. I cannot determine on this application whether the Molloy Decision was valid and I was not asked to do so. Unlike HS Works, where the court had before it two sets of enforcement proceedings which it heard together, determining that each adjudication decision under consideration was valid and enforceable, I am concerned only with enforcement proceedings in relation to the Wood Decision. As is clear from the evidence, FK raised a jurisdictional challenge at the Molloy adjudication, which I was not invited to determine on this application[6], but which I understand it intends to pursue before the court (and given the timing of the Molloy Decision it is unsurprising that it has yet to take any steps in this regard). Whilst adjudicators' decisions will usually be enforced by the courts, that enforcement policy only applies to decisions that the adjudicator was authorised to reach (i.e. they were not vitiated by some material failure to comply with basic concepts of fairness). Accordingly, as is clear from Coulson on Construction Adjudication (2018 4th Ed) at 14.04 and from Alstom Signalling Ltd v Jarvis Facilities Ltd [2004] EWHC 1285 (TCC) per HHJ Humphrey Lloyd QC at [19], any right of enforcement of an adjudicator's decision is always qualified or contingent upon the validity of the decision itself. There is nothing in the 1996 Act which requires a party who wishes to challenge a decision of an adjudicator to comply with it before being able to advance its case. In all the circumstances, I cannot determine on this application that the Molloy Decision was valid and so there can be no question of any set off, or withholding. I expressly reject Mr Hale's submission that the potential for a jurisdictional challenge in due course does not preclude a set off, a submission which to my mind runs entirely contrary to the principles articulated by Akenhead J in HS Works at [40]; the clear rationale for those principles being the existence of certainty in respect of each party's financial entitlements pursuant to two adjudication decisions with which the court is dealing "simultaneously".
b. Enforceability/Effect: the second matter identified by Akenhead J for consideration is whether both decisions are "capable of being enforced or given effect to". Given my decision on validity, it is not strictly necessary for me to consider this (or indeed any of the other steps), but where I have heard full argument on it, I shall do so as briefly as possible. In HS Works, Akenhead J held that the second adjudication decision was enforceable, declaring after hearing the arguments that the proper valuation of the sub-contract works allowing for contra charges was capable of being enforced. He went on separately to consider the effect of the second adjudication decision finding, as I have said, that the parties were required by statute to comply with the "valid decision of any adjudicator" and that this must apply to the second adjudication decision such that if the parties were to give effect to it, a balancing payment would immediately be due. Similarly in Sentosa, the second adjudication was found to be enforceable by the court (see [25]). In this case, however, the court has not yet heard argument as to whether the Molloy Decision is enforceable and cannot determine the point for reasons already given. Equally it cannot give effect to a decision that is not yet enforceable. In all the circumstances, there is no need for me to consider further the arguments made by the parties as to the difference between a net and a gross valuation and whether the Wood Decision is "irreconcilable" with the Molloy Decision.
c. Separate Proceedings: it is common ground that there are no separate proceedings in respect of the Molloy Decision and so no scope for the court to determine (based on a properly articulated and pleaded case) whether the Molloy Decision is valid and enforceable and thus no scope for the court to enforce and/or give effect to the Molloy Decision. Once again, that seems to me to be an end to the matter. Mr Hale pointed out that, given the timescales, it has not been realistically practical to commence proceedings in time for this hearing. However, even had proceedings been urgently commenced, the court would not have been dealing with the two adjudication decisions simultaneously and is unlikely to have been in a position to determine (at today's hearing) whether the Molloy Decision is valid and enforceable. In my judgment, the existence of separate proceedings brought by each party to enforce each adjudication decision and determined together by the court was a key factor underlying Akenhead J's willingness to contemplate the exercise of the court's discretion in favour of a set off in HS Works. A similar situation existed in Sentosa (aside from the fact that there the argument for a set off also benefitted from the applicability of the second exception). In HS Works, Akenhead J expressly distinguished both Interserve and YCMS on the grounds that in neither case had the defendant sought to enforce the later adjudication decision by separate proceedings. Where separate proceedings have been brought and determined by the court at the same time, the questions of validity and enforceability can be properly addressed, leaving the court (if appropriate) to exercise its discretion as to how best to deal procedurally with the outcome. To my mind that is an entirely different situation from the one that arises in this case.
d. Discretion: In light of the analysis set out above, I reject the suggestion that I have any discretion to permit a set off or withholding – the facts of this case simply do not bring it within the territory of the exception envisaged in HS Works. However, even if I am wrong about that, I would not have been prepared to exercise my discretion in ISG's favour in this case, not least because (i) there is no suggestion in the Wood Decision that there might be a set off or withholding against the sum due; (ii) no payments are due or flowing from the Molloy Decision and ISG did not seek to allege any overpayment in the context of that adjudication, including in relation to amounts due and owing from previous adjudication awards; and (iii) in my judgment, an order in the terms sought by Mr Hale in this case would plainly undermine the policy of enforcement of adjudicators' decisions as developed and applied in the TCC over the last 20 years. It would also risk undermining the purpose of the 1996 Act. I accept Mr Mesfin's submission that the exercise of the court's discretion should not be used to frustrate the purpose of the 1996 Act or the Scheme, which were intended to provide for the expeditious treatment of disputes on an interim basis to secure cash flow pending final resolution of any issues between the parties.
"The court's starting point is that adjudicator's decisions should be enforced subject to any issues of jurisdiction, breach of the rules of natural justice or other exceptional circumstances. The existence of the Part 8 claim for declaratory relief…is not a ground for delaying the determination of an adjudication enforcement claim, particularly where the Part 8 claim has been listed for a later date and would involve material delay to the Part 7 claim".
The Triathlon Decisions
a. The Aeberli Decision is subject to jurisdictional challenges by FK which cannot be determined by this court. Indeed, although Mr Aeberli reached a non-binding decision that he had jurisdiction to hear ISG's claim, he also made it clear that "it might be that on reflection ISG will consider it best, given the sums involved, to restart this Adjudication to avoid any jurisdictional uncertainty and potential wasted costs". ISG chose not to take this advice and it is perhaps unsurprising that FK's evidence confirms that it now intends to challenge the Aeberli Decision by way of Part 8 proceedings. In the circumstances, I cannot determine that the Aeberli Decision is valid or enforceable and neither can it be given effect to by way of set off. This is enough to put an end to the set off argument arising in respect of the Triathlon Decisions because it wipes out the small credit on ISG's side of the balance.
b. No separate proceedings have been issued in respect of any of the Triathlon Decisions.
c. As I have already said, there is nothing in the Wood Decision which was predicated on the basis that there could be a set off.
d. Finally, and as an entirely stand-alone point, it is accepted on both sides that the suggestion that an adjudication decision in relation to one construction project can be set off against an adjudication decision in relation to another construction project is entirely novel. ISG points to the fact that the two sub-contracts contain a cross-contract set off provision, but reliance upon this would appear to offend against the statutory requirement for immediate enforcement of an adjudicator's award. Further and in any event, it is common ground that both HS Works and Sentosa (which did not concern contractual set off provisions) were concerned with adjudication decisions arising in connection with the same project. This is a point of some interest, but given the conclusions I have already reached, I do not need to determine it on this application.
CONCLUSION
Note 1 See the Local Democracy, Economic Development and Construction Act 2009. [Back] Note 2 See also 23(2) of the Scheme. [Back] Note 3 See section 108 of the 1996 Act and 30.1 of the Scheme. [Back] Note 4 Although couched in terms of a ‘set off’, ISG’s proposal is not really for a set off (in the sense of a balancing between a sum owed by one party against a sum owed by another), but rather for a withholding of part of the amount that it owes FK pursuant to the Wood Decision. ISG effectively invites the court to accept that the figure identified in the Wood Decision overstates the position having regard to the Molloy Decision, such that it should be reduced accordingly. [Back] Note 5 GV of £3,736,679.72 - £2,829,941.55 = £906, 738.20 (i.e. the sum that remains owing to FK from ISG pursuant to the Molloy Decision). Deducting this figure of £906,738.20 from the figure due pursuant to the Wood Decision (of £1,691,679.94) leaves £784,941.70. I note that during the hearing a figure of £888,000 odd was identified by Mr Hale, but as things stand I cannot see how this had been arrived at. In any event, in light of my decision, the exact figure is of no real importance. [Back] Note 6 It is difficult to see how FK’s jurisdictional challenge to the Molloy Decision could sensibly have been determined in the time allotted for the hearing (as Mr Hale acknowledged) and in circumstances where neither party’s skeleton arguments addressed the point in any detail. In any event, it was Mr Hale’s contention that there was no need for the court to determine the jurisdictional issue. [Back] Note 7 For completeness I should add that it is FK’s case that ISG’s strategy under both the Barberry and Triathlon Projects has been to avoid making any further payments to FK for as long as possible and that FK has had no option other than to refer outstanding disputes to adjudication. However, there is no need for me to arrive at any view as to the respective merits of the parties’ opposing submissions as to the approach that has been taken by FK in respect of referring disputes to adjudication. [Back] Note 8 FK’s evidence confirms a healthy order book and a financially robust company. [Back]