[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Drax Energy Solutions Ltd v Wipro Ltd [2023] EWHC 1342 (TCC) (09 June 2023) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2023/1342.html Cite as: [2023] EWHC 1342 (TCC), 210 Con LR 80, [2023] BLR 537 |
[New search] [Printable PDF version] [Help]
BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES
TECHNOLOGY AND CONSTRUCTION COURT (KBD)
B e f o r e :
____________________
DRAX ENERGY SOLUTIONS LIMITED (Formerly Haven Power Limited) |
Claimant |
|
-and- |
||
WIPRO LIMITED |
Defendant |
____________________
(instructed by Milbank LLP, Solicitors) for the Claimant
ALEX CHARLTON KC and DANIEL GOODKIN (instructed by Clyde & Co LLP, Solicitors)
for the Defendant
Hearing date: 9 February 2023
____________________
Crown Copyright ©
(1) SOW 1-3 would be entered into on 17 January, 10 February and 10 March 2017 and they addressed the design, build, test and implementation of the Oracle-based software modules to include software licences for 5 years;
(2) SOW 4 would be entered into on 19 April 2017 for a 4-year period in respect of Application Management Services and a further 4 years for Data Centre Costs, Meter to Cash, and Oracle Cloud Application Maintenance Costs;
(3) SOW 5 would be entered into on 24 January 2017, for 5 years, for WAN Network Services;
(4) SOW 6 would be entered into on 19 April 2017 for a design for software encryption
and all of these comprised the "Planets" suite of programs.
(1) SOW1: £4.8 million;
(2) SOW2: £2.2 million;
(3) SOW3: £250,000; and
(4) SOW4: £858,000.
(1) Year 2: £840,404;
(2) Year 3: £992,404;
(3) Year 4: £983,404, and
(4) Year 5: £608,644.
Introduction
(1) Misrepresentation Claim;
(2) Quality Claims;
(3) Delay Claims; and
(4) Termination Claims.
Misrepresentation
Quality Claims
Delay Claims
Termination Claims
Claims Analysis
(1) Quality: £9.8 million;
(2) Delay: £9.7 million;
(3) Termination: £12 million; and
(4) Misrepresentation: £31 million.
"33. LIABILITY
33.1 Subject to clauses 33.5 and 33.6, the Supplier's liability to the Customer, whether in contract, tort (including negligence) for breach of statutory duty or otherwise, for loss or damage to tangible property arising out of or in connection with this Agreement (including all Statements of Work) shall be limited to £20 million per event or series of connected events.
33.2 Subject to clauses 33.1, 33.3, 33.5 and 33.6, the Supplier's total liability to the Customer, whether in contract, tort (including negligence), for breach of statutory duty or otherwise, arising out of or in connection with this Agreement (including all Statements of Work) shall be limited to an amount equivalent to 150% of the Charges paid or payable in the preceding twelve months from the date the claim first arose. If the claim arises in the first Contract Year then the amount shall be calculated as 150% of an estimate of the Charges paid and payable for a full twelve months.
33.3 The Supplier's total aggregate liability arising out of or in relation to this Agreement for any and all claims related to breach of any provision of clause 21 whether arising in contract (including under an indemnity), tort (including negligence), breach of statutory duty, laws or otherwise, shall in no event exceed 200% of the Charges paid or payable in the preceding twelve months from the date the claim first arose or £20m (whichever is greater).
33.4 Subject to clauses 33.5 and 33.6, the Customer's total liability to the Supplier, whether in contract, tort (including negligence), for breach of statutory duty or otherwise, arising out of or in connection with this Agreement (including all Statements of Work) shall be limited to the Charges payable under this Agreement (including all Statements of Work) in respect of Services properly performed by the Supplier at the point the claim is made.
33.5 Subject to clause 33.6, neither party will be liable to the other party for any indirect, consequential or special loss including but not limited to any loss of profits or loss of goodwill arising out of, or in connection with, this Agreement or any Statement of Work.
33.6 Nothing in this Agreement or any Statement of Work shall exclude or limit:
33.6.1 either party's liability for death or personal injury caused by its (or its agent's or sub-contractor's) negligence or for fraud or fraudulent misrepresentation;
33.6.2 the Supplier's liability, whether categorised as direct or indirect losses, to the Customer arising out of a breach of clause 4.2.4 (Compliance with Laws), clause and/or where the Supplier has indemnified the Customer in clause 19 (IPR Indemnity), and/or arising out of a breach of clause 26 (Confidentiality and Announcements) and/or clause 37 (Anti corruption);
33.6.3 the Supplier's liability for wilful misconduct or abandonment; or
33.6.4 either party's liability that cannot, as a matter of law, be limited or excluded."
(1) Issue 1: On a true construction, does clause 33.2 of the MSA provide for a single aggregate cap which applies to the Defendant's liability for the Claimant's claim; or multiple caps with a separate financial limit applying to each of the Claimant's claims?
(2) Issue 2: If there are multiple caps, what are each of the Claimant's claims to which the cap applies?
(1) The charges payable in the first 12 months were, as we have seen, £7,671,118;
(2) 150% of that figure is £11,506,677;
(3) Rounded to £11.5 million, this is the maximum amount of loss for which Wipro can be made liable, in respect of all and any of the claims made against it;
(4) It follows that if Drax succeeded entirely, and in principle, Wipro was liable for £31.7 million of loss, Drax could only recover £11.5 million;
(5) To the extent necessary, Wipro also contends that the "claim" referred to in the Clause means the total liability established; or, alternatively, for the purposes of the Clause, there is only one claim which is the totality of the claims (if defined more narrowly) which succeeded; and
(6) In this regard, Wipro accepts and contends that for present purposes, the "claim" arose in the first contract year.
(1) one claim for Misrepresentation;
(2) 9 claims in respect of Quality;
(3) 4 claims in respect of Delay;
(4) one claim for repudiatory breach, and
(5) one claim in respect of the Exit Plan.
Contractual Interpretation Generally.
"i) The court construes the relevant words of a contract in their documentary, factual and commercial context, assessed in the light of (i) the natural and ordinary meaning of the provision being construed, (ii) any other relevant provisions of the contract being construed, (iii) the overall purpose of the provision being construed and the contract or order in which it is contained, (iv) the facts and circumstances known or assumed by the parties at the time that the document was executed, and (v) commercial common sense, but (vi) disregarding subjective evidence of any party's intentions – see Arnold v. Britton [2015] UKSC 36 [2015] AC 1619 per Lord Neuberger PSC at paragraph 15 and the earlier cases he refers to in that paragraph;
ii) A court can only consider facts or circumstances known or reasonably available to both parties that existed at the time that the contract or order was made - see Arnold v. Britton (ibid.) per Lord Neuberger PSC at paragraph 20;
iii) In arriving at the true meaning and effect of a contract or order, the departure point in most cases will be the language used by the parties because (a) the parties have control over the language they use in a contract or consent order and (b) the parties must have been specifically focussing on the issue covered by the disputed clause or clauses when agreeing the wording of that provision – see Arnold v. Britton (ibid.) per Lord Neuberger PSC at paragraph 17;
iv) Where the parties have used unambiguous language, the court must apply it – see Rainy Sky SA v. Kookmin Bank [2011] UKSC 50 [2011] 1 WLR 2900 per Lord Clarke JSC at paragraph 23;
v) Where the language used by the parties is unclear the court can properly depart from its natural meaning where the context suggests that an alternative meaning more accurately reflects what a reasonable person with the parties' actual and presumed knowledge would conclude the parties had meant by the language they used but that does not justify the court searching for drafting infelicities in order to facilitate a departure from the natural meaning of the language used – see Arnold v. Britton (ibid.) per Lord Neuberger PSC at paragraph 18;
vi) If there are two possible constructions, the court is entitled to prefer the construction which is consistent with business common sense and to reject the other – see Rainy Sky SA v. Kookmin Bank (ibid.) per Lord Clarke JSC at paragraph 2 - but commercial common sense is relevant only to the extent of how matters would have been perceived by reasonable people in the position of the parties, as at the date that the contract was made – see Arnold v. Britton (ibid.) per Lord Neuberger PSC at paragraph 19;
vii) In striking a balance between the indications given by the language and those arising contextually, the court must consider the quality of drafting of the clause and the agreement in which it appears – see Wood v. Capita Insurance Services Limited [2017] UKSC 24 per Lord Hodge JSC at paragraph 11. Sophisticated, complex agreements drafted by skilled professionals are likely to be interpreted principally by textual analysis unless a provision lacks clarity or is apparently illogical or incoherent– see Wood v. Capita Insurance Services Limited (ibid.) per Lord Hodge JSC at paragraph 13; and
viii) A court should not reject the natural meaning of a provision as correct simply because it appears to be a very imprudent term for one of the parties to have agreed, even ignoring the benefit of wisdom of hindsight, because it is not the function of a court when interpreting an agreement to relieve a party from a bad bargain - see Arnold v. Britton (ibid.) per Lord Neuberger PSC at paragraph 20 and Wood v. Capita Insurance Services Limited (ibid.) per Lord Hodge JSC at paragraph 11."
Interpretation of clauses which exclude or limit liability
"106…a further reason for giving the word "negligence" its straightforward and ordinary legal meaning is that clear words are necessary before the court will hold that a contract has taken away valuable rights or remedies which one of the parties to it would have had at common law (or pursuant to statute).
107 The approach of the courts to the interpretation of exclusion clauses (including clauses limiting liability) in commercial contracts has changed markedly in the last 50 years. Two forces have been at work. One has been the impact of the Unfair Contract Terms Act 1977, which provided a direct means of controlling unreasonable exclusion clauses and removed the need for courts to resort to artificial rules of interpretation to get around them:… The second force has been the development of the modern approach in English law to contractual interpretation, with its emphasis on context and objective meaning and deprecation of special rules of interpretation encapsulated by Lord Hofmann's announcement in Investors Compensation Scheme Ltd v West Bromwich Building Society [1998] 1 WLR 896, 912 that "almost all the old intellectual baggage of legal interpretation has been discarded".
108. The modern view is accordingly to recognise that commercial parties are free to make their own bargains and allocate risks as they think fit, and that the task of the court is to interpret the words used fairly applying the ordinary methods of contractual interpretation. It also remains necessary, however, to recognise that a vital part of the setting in which parties contract is a framework of rights and obligations established by the common law (and often now codified in statute). These comprise duties imposed by the law of tort and also norms of commerce which have come to be recognised as ordinary incidents of particular types of contract or relationship and which often take the form of terms implied in the contract by law. Although its strength will vary according to the circumstances of the case, the court in construing the contract starts from the assumption that in the absence of clear words the parties did not intend the contract to derogate from these normal rights and obligations."
"18. In my judgment the underlying rationale for the principle that, if necessary to resolve ambiguity, exclusion clauses should be narrowly construed has nothing to do with the identification of the proferens, either of the document as a whole or of the clause in question. Nor is it a principle derived from an identification of the person seeking to rely upon it. Ambiguity in an exclusion clause may have to be resolved by a narrow construction because an exclusion clause cuts down or detracts from the ambit of some important obligation in a contract, or a remedy conferred by the general law such as (in the present case) an obligation to give effect to a contractual warranty by paying compensation for breach of it. The parties are not lightly to be taken to have intended to cut down the remedies which the law provides for breach of important contractual obligations without using clear words having that effect:…
19. This approach to exclusion clauses is not now regarded as a presumption, still less as a special rule justifying the giving of a strained meaning to a provision merely because it is an exclusion clause. Commercial parties are entitled to allocate between them the risks of something going wrong in their contractual relationship in any way they choose. Nor is it simply to be mechanistically applied wherever an ambiguity is identified in an exclusion clause. The court must still use all its tools of linguistic, contextual, purposive and common-sense analysis to discern what the clause really means. In the Seadrill Management case Moore-Bick [LJ] described the principle as, 'essentially one of common sense; parties do not normally give up valuable rights without making it clear that they intend to do so…
21. For those legal reasons I approach the issue as to the construction of clause 5.1 upon the basis that there remains a principle that an ambiguity in its meaning may have to be resolved by a preference for the narrower construction, if linguistic, contextual and purposive analysis do not disclose an answer to the question with sufficient clarity."
"The natural meaning of the language is by no means so clear as to preclude serious consideration of the commerciality or otherwise of rival interpretations or, for that matter, to preclude recourse to the principle that ambiguous exclusion clauses should be construed narrowly."
"(b) the aggregate liability of either party under the Contract for all Defaults, other than those
governed by sub-clause 8.1.2 (a) above, shall not exceed the amount stated in schedule G to be the
limit of such liability."
"…The aggregate liability of the Contractor in accordance with sub-clause 8.1.2 paragraph (b) shall not exceed:
9.2.1 for any claim arising in the first 12 months of the term of the Contract, the Total Contract Price as set out in section 1.1; or
9.2.2 for claims arising after the first 12 months of the Contract, the total Contract Charges paid in the 12 months prior to the date of that claim."
Introduction
The Language of the Clause
Language of the other provisions
"35.1.1 employers liability insurance for a maximum amount of cover of £10 million on a per occurrence and an annual aggregate basis;
35.1.2 professional indemnity insurance for a minimum amount of cover of £20 million on a per occurrence and an annual aggregate basis;
35.1.3 public liability insurance for a minimum amount of cover of £30 million on a per occurrence and an annual aggregate basis; and
35.1.4 product liability insurance for a minimum amount of cover of £30 million on a per occurrence and an annual aggregate basis."
Conclusions on the language used
Commercial Considerations
Triple Point Considerations
Conclusion on Preliminary Issue 1
"It is important to note that what makes a "a new claim" as defined in Section 35(2) is not the newness of the claim according to the type or quantum of remedy sought, but the newness of the cause of action which it involves. The formula employed in Section 35(2)(a) and (5) is "a claim involving … the addition or substitution of a new cause of action". And Order 20, Rule 5(5) refers not to a claim but to"[a]n amendment the effect of which is to add or substitute "a new cause of action". Diplock LJ's widely accepted definition of a cause of action in Letang v. Cooper [1965] 1 QB 232 , CA, at 242–3, as "simply a factual situation the existence of which entitles one party to obtain from the court a remedy against another person", as distinct from "a form of action … used as a convenient and succinct description of a particular category of factual situation", is of importance. It makes plain that a claim and a cause of action are not the same thing. It follows, as Mr Croally argued, that an originally pleaded "factual situation" may disclose more than one cause of action, although one of them may not be individually categorized as such or the subject of a claim for a separate remedy. However, as Mr Browne-Wilkinson submitted, it does not follow that a claim so categorizing it and/or seeking a remedy for it made for the first time by amendment is the addition of a new cause of action so as to render it a new claim."
(1) The Misrepresentation Claim;
(2) The Quality Claim;
(3) The Delay Claim, and
(4) The Termination Claims
as set out in paragraph 5 (q)-(t) of the Further Information.