[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Boxxe Ltd v The Secretary of State for Justice [2023] EWHC 533 (TCC) (13 March 2023) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2023/533.html Cite as: 207 Con LR 159, [2023] EWHC 533 (TCC) |
[New search] [Printable PDF version] [Help]
KING'S BENCH DIVISION
BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES
TECHNOLOGY AND CONSTRUCTION COURT
Fetter Lane, London, EC4A 1NL |
||
B e f o r e :
____________________
BOXXE LIMITED |
Claimant |
|
- and - |
||
THE SECRETARY OF STATE FOR JUSTICE |
Defendant |
____________________
Mr Rupert Paines and Mr Oliver Mills (instructed by Government Legal Department) for the Defendant
Hearing date: 3rd March 2023
____________________
Crown Copyright ©
MR JUSTICE CONSTABLE:
Introduction
'The following table summarises your scores against the Successful Tenderer:
* The Successful Tenderer bid a price of £0 for storage service pricing. As this was the lowest priced bid, the Successful Tenderer scored the full 5% in accordance with the Further Competition Invitation. Your storage service price, using the calculation set out in the Further Competition Invitation was therefore scored as 0%.'
Ground 1: SCC's bid was non-compliant, in that it failed to comply with the requirement to provide a substantive storage cost and/or involved price manipulation. It should be noted that, in use of the word 'manipulation', Boxxe does not intend to imply anything underhand, nefarious or dishonest. It is said that on account of this, SoSJ was required to disqualify the bid and breached its duty by failing to do so.
Ground 2: described as 'undisclosed evaluation criteria', Boxxe allege that the pricing formula ought to have been applied to all of the bids with all of the bids (for storage) being scored 0, and thereby levelling the playing field.
Ground 3: SoSJ failed to award the Contract to the MEAT, but instead awarded the Contract to the higher priced bid, as a result of the manipulation of the scoring.
Ground 4: SoSJ manifestly erred in failing to award the contract to MEAT;
Ground 5: SSC's bid was an 'abnormally low tender'. SoSJ failed to conclude that this was the case as it would have done if the tender had been properly investigated. Following such inquiries, it would have been irrational and unlawful for SoSJ to take any step other than disqualify SCCP's bid on the grounds that it was non-compliant.
Ground 6. There was unequal treatment because SoSJ required Boxxe to provide a price for each element of the bid, even where the costs were notional only, and that SCC was not required to do so similarly.
Ground 7. SoSJ erred in including in the evaluation HDMCI to HDCI converters, which on Boxxe's design would be unnecessary.
(1) Is there a serious issue to be tried?;
(2) If so, would damages be an adequate remedy for Boxxe if the suspension were lifted and they succeeded at trial; is it just in all the circumstances that Boxxe should be confined to a remedy in damages?;
(3) If not, would damages be an adequate remedy for SoSJ if the suspension remained in place and it succeeded at trial?;
(4) Where there is doubt as to the adequacy of damages for either of the parties, which course of action is likely to carry the least risk of injustice if it transpires that it was wrong, that is, where does the balance of convenience lie?
Serious Issue to be Tried
'(1) This regulation limits the time within which proceedings may be started where the proceedings do not seek a declaration of ineffectiveness.
(2) Subject to paragraphs (3) to (5), such proceedings must be started within 30 days beginning with the date when the economic operator first knew or ought to have known that grounds for starting the proceedings had arisen '
23. Where, under some legislative provision, an act is required to be done within a fixed period of time "beginning with" or "from" a specified day it is a question of construction whether the specified day itself is to be included in, or excluded from, that period. Where the period within which the act is to be done is expressed to be a number of days, months or years from or after a specified day, the courts have held, consistently since Young v. Higgon (1840) 6 M. & W. 49 , that the specified day is excluded from the period; that is to say, that the period commences on the day after the specified day. Examples of such an "exclusive" construction are found in Goldsmith's Co. v. West Metropolitan Railway Co. [1904] 1 KB 1 ("the powers of the company for the compulsory purchase of lands for the purposes of this Act shall cease after the expiration of three years from the passing of this Act") and in In re Lympe Investments Ltd. [1972] 1 W.L.R. 523 ("the company has for three weeks thereafter neglected to pay"). In Stewart v. Chapman [1951] 2 K.B. 792 ("a person shall not be convicted unless within 14 days of the commission of the offence a summons for the offence was served on him") Lord Goddard C.J. observed, at pp. 798–799, that it was well established that "whatever the expression used" the day from which the period of time was to be reckoned was to be excluded.
24. Where, however, the period within which the act is to be done is expressed to be a period beginning with a specified day, then it has been held, with equal consistency over the past 40 years or thereabouts, that the legislature (or the relevant rule making body, as the case may be) has shown a clear intention that the specified day must be included in the period. Examples of an "inclusive" construction are to be found in Hare v. Gocher [1962] 2 Q.B. 641 ("if within [the period of two months beginning with the commencement of this Act] the occupier of an existing site duly makes an application for a site licence") and in Trow v. Ind Coope (West Midlands) Ltd. [1967] 2 Q.B. 899 ("a writ is valid for 12 months beginning with the date of its issue"). As Salmon L.J. pointed out in Trow v. Ind Coope (West Midlands) Ltd. , at p. 923, the approach adopted in the Goldsmith's Co. case [1904] 1 KB 1 and Stewart v. Chapman [1951] 2 K.B. 792 can have no application in a case where the period is expressed to begin on the specified date. He observed, at p. 924, that "I cannot accept that, if words have any meaning, 'beginning with the date of its issue' can be construed to mean the same as 'beginning with the day after the date of its issue.'"
'When we speak of the date on which anything is done, we mean the date by the calendar, such as: "The date today is May 2, 1967." We do not divide the date up into hours and minutes. We take no account of fractions of a date.'
Thus, the relevant date was simply September 10, 1966. In the present case, therefore, the time that the Decision Notice was received is not relevant. The relevant date is simply 13 December 2022. The key question is whether that date (as a whole) should be included, or excluded from the calculation of time. The second issue in Trow was a similar point. With Lord Denning MR dissenting, the Court of Appeal held that 'beginning with' means that the date is included in the 12 month period, and concluded that the service of the writ was therefore out of time. Salmon LJ concluded,
'I cannot, however, accept that, if words have any meaning, "beginning with the date of its issue" can be construed to mean the same as "beginning with the day after the date of its issue."
'
(d) in computing any period within which something must be done or by which something is to take effect a start date must be identified;
(e) where that start date is relative to the happening of an event, the fundamental question is likely to be whether the period starts on the day of the event or the day after the event;
(f) that will depend, in the context of a statutory provision, on the interpretation of the language in that provision and, in the context of a contract, lease, will or other legal document, on the construction of the language of the document; difficulties can arise if either the written material is completely silent on the point or there is no writing;
(g) where the statutory or contractual language means that the day of the event is to be included in the computation of the period, then time starts to run at the start of that day, irrespective as to the time of day that the event took place; the law takes no account of fractions of a day;
(h) where the statutory or contractual language means that the day of the event is not to be included, then time starts to run at the start of the following day, irrespective as to the time of day that the event took place, because, in this context also, the law takes no account of fractions of a day; '
'When a step has to be taken within a period described as "beginning with" a specified day, then that day is included in the period; but if the period is described as running "from" or "after" a specified day, then that day is not included in the [period]'
'Perhaps the most satisfactory of the authorities on this point is Marren v Dawson Bentley & Co.21 The claimant was injured in an accident at 13.30 on 8 November 1954, and the writ was issued on 8 November 1957. The question was whether time had expired at the end of 7 November 1957, and Havers J held that it had not. The day on which the cause of action accrues is to be disregarded in calculating the running of time. It therefore followed that time began to run at the first moment of 9 November 1954 and expired at the end of 8 November 1957.'
'The preceding paragraphs have dealt with calculation of time in connection with the issuing of process. In Trow v Ind Coope (West Midlands) Ltd the Court of Appeal had to resolve similar problems in connection with the service of a writ. The writ in this case was issued on 10 September 1965 and was served on 10 September 1966. The majority of the Court of Appeal, Lord Denning MR dissenting, held that the service was out of time. For the purpose of calculating the duration of a writ, the day on which the writ is issued is included. This is obviously in direct contradiction to the rule for the issuing of a writ and it is easy to sympathise with Lord Denning's view that there is no rational justification for the distinction. It nevertheless appears still to be good law.'
'(1) An action under section 148 of the Building Safety Act 2022 shall not be brought after the expiration of 15 years from the date on which the right of action accrued.
(2) An action under section 149 of the Building Safety Act 2022 shall not be brought after—
(a)if the right of action accrued before the commencement date, the expiration of the period of 30 years from the date on which it accrued, and
(b)if the right of action accrued on or after the commencement date, the expiration of the period of 15 years beginning with the date on which it accrued.
(3) In a case where—
(a)a right of action under section 149 of the Building Safety Act 2022 accrued before the commencement date, and
(b)the expiration of the period of 30 years beginning with the date on which the right of action accrued falls in the year beginning with the commencement date,
subsection (2)(a) has effect as if it referred to the expiration of that year.
(5) No other period of limitation prescribed by Part 1 of this Act applies in relation to an action referred to in subsections (1) and (2).'
(emphasis added)
"Where a period expressed in days, weeks, months or years is to be calculated from the moment at which an event occurs or an action takes place, the day during which that event occurs or that action takes place shall not be considered as falling within the period in question."
'39 The objective of rapidity pursued by Directive 89/665 must be achieved in national law in compliance with the requirements of legal certainty. To that end, member states have an obligation to establish a system of limitation periods that is sufficiently precise, clear and foreseeable to enable individuals to ascertain their rights and obligations: see, to that effect, Commission of the European Communities v Federal Republic of Germany (Case C-361/88) [1991] ECR I-2567, para 24 and Commission of the European Communities v Grand Duchy of Luxembourg (Case C-221/94) [1996] ECR I-5669, para 22.'
Would damages be an adequate remedy for the Boxxe?
(1) The impact upon Boxxe's key sub-contractor, Involve;
(2) The alleged non-availability of Francovich damages for Boxxe;
(3) Difficulty in assessing damages for Boxxe.
The impact upon Boxxe's key sub-contractor, Involve
'It seems to me that these observations are pertinent to the present application and they reinforce my view that if a commercial undertaking chooses to carry out its operations through a series of special purpose vehicles, it cannot really complain if that carries disadvantages as well as advantages. Further, to answer Mr Coppel's threshold question, in my judgment it is the position of the Claimant that must be considered on this application, and not the position of the Circle Group or the Circle brand. No other Circle Group company is a party to this litigation. Ms McCredie did not really have a direct answer to this point: what she said was that "the world doesn't just look at the Claimant - it associates it with the group as a whole". I am prepared to accept in principle that this may be so, but it still requires the court to assess how this might affect the Claimant in the circumstances of this case and whether it will do so in a manner that cannot be compensated by damages.'
The alleged non-availability of Francovich damages for Boxxe
Difficulty in assessing damages for Boxxe
(1) There were a range of lawful options open to SoSJ and it may be unclear which one SoSJ would have taken. SoSJ might seek to argue that some of these might not have resulted in an award of the contract to the Claimant. If so, then it is said that it is likely to be very difficult to quantify the likelihood of SoSJ awarding the contract to Boxxe, and doing so would be an inherently speculative task, and may require extensive evidence about essentially counter-factual matters.
(2) The ITT set out indicative quantities but provided that "HMCTS does not commit to ordering those quantities and no minimum volumes will be included in the Contract." It is said that, given the absence of any minimum volume guarantee whatsoever, there is no concrete yardstick by which to measure the losses that Boxxe will suffer.
Adequacy of damages - finding
'Nevertheless, I consider that it is probably prudent for the court to go on and consider the balance of convenience in any event in case there is some factor that is so compelling that it ought to be taken into account in spite of the court's conclusion about the adequacy of damages as a remedy. I shall therefore follow that course.'
Would damages be an adequate remedy for SoSJ?
Balance of Convenience
(1) If the suspension is lifted, damages will an adequate remedy for Boxxe if it succeeds at trial, especially so given the undertaking offered by SoSJ in relation to the Francovich issue, and which I consider ought be provided;
(2) If the suspension is not lifted, with or without an expedited trial, SoSJ will sustain losses caused by the ongoing delays which are real and which cannot be compensated for by damages, as I have found above.
(3) it is correct that the public interest points, as it often does, in both directions – both for the implementation of the Competition as planned and as soon as possible, but also for SoSJ not overpaying for those services by reason (if Boxxe is right) of a flawed procurement process;
(4) SSC will be impacted adversely.