![]() |
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | |
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Beck Interiors Ltd v Eros Ltd [2024] EWHC 2084 (TCC) (28 June 2024) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2024/2084.html Cite as: [2024] EWHC 2084 (TCC) |
[New search] [Printable PDF version] [Help]
BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES
TECHNOLOGY AND CONSTRUCTION COURT (KBD)
Rolls Building 7 Rolls Buildings Fetter Lane London EC4A 1NL |
||
B e f o r e :
____________________
BECK INTERIORS LTD |
CLAIMANT |
|
- and - |
||
EROS LTD |
DEFENDANT |
____________________
Tel: 01303 230038
Email: [email protected]
____________________
Crown Copyright ©
Number of folios in transcript | 123 |
Number of words in transcript | 8,845 |
Mrs Justice Jefford:
The injunction
1) The Defendant in an intended action, that is Eros Limited, be restrained from issuing any notice of adjudication against the Claimant unless the Defendant first obtains the permission of a judge authorised to sit in the Technology and Construction Court, and
2) That the Defendant must forthwith withdraw the notices of adjudications dated 17 May 2024, 21 May 2024, 28 May 2024 and 30 May 2024, initiated against the Claimant.
Factual background
Adjudication no. 1
Adjudication no. 2
"It is plain that any construction team in any law firm or any person who sits on the RICS panel will have more than one adjudication in play at any one time."
Eros has pointed to this statement, which reflects the statutory regime and common practice, as indicative of Beck's view as to multiple adjudications proceeding at one time.
"If your client does not respond in a positive manner by Tuesday 7 May [2024] and agrees to meet with BECK within the next 10 days, then BECK will have to consider its options with regard to issuing appropriate proceedings."
Adjudication no. 3
1) No dispute had crystallised. A letter of claim was only issued on 3 May 2024. Beck's solicitors replied pointing out deficiencies in the claim. There was no further response to that letter. Accordingly, no dispute had crystallised.
2) The claim was based on establishing that Beck had not achieved sectional completion dates and was therefore the same as the claim in adjudication no. 1.
3) The claim was an abuse of process and manifestly unfair and any decisions in Eros' favour would necessarily be reached in breach of natural justice.
Adjudication no. 4
"1. All the purported disputes claimed by Eros are sham claims and the numerous adjudications commenced by Eros are an abuse of process in an attempt to put adverse financial pressure on BECK;
2. Eros's claims have no legitimacy, and it is attempting to make an unfair financial gain by making conflicting and/or contrary claims against the other trade contractors and professional consultants engaged on this project; and
3. It will be an abuse of process and manifestly unfair and a breach of the rules of natural justice if BECK is not allowed a fair and reasonable period of time to respond to the Referral.
For all of the above reasons, we invite you to resign. As noted above, should you not resign, Beck's continued participation in the reference is entirely without prejudice to its position that you lack jurisdiction."
Adjudication no. 5
Adjudication no. 6
The context of the application
"20. This letter is as detailed as it reasonably needs to be to allow you to understand the claim made against you client and decide whether you accept, reject it or require further information. For the avoidance of doubt, this letter is not intended to serve as a Letter of Claim under the Pre-Action Protocol.
21. We invite you to confirm on an open basis, by no later than 5pm on 3 July 2024 whether your client accepts this claim, rejects it, or requires further information. If you have questions about the claim, or require further information, please set out these requests clearly and succinctly with the same timeframe so that this matter may be progressed expeditiously.
22. Please be advised that if the claim is disputed, our client reserves the right to commence an adjudication to recover the losses it has incurred by reason of your client's breaches of contract. If we do not hear from you, we will assume the claim is disputed and will proceed accordingly."
The statutory regime and the authorities
"A party to a construction contract has the right to refer a dispute arising under the contract for adjudication under a procedure complying with this section."
"To give notice at any time of his intention to refer a dispute to adjudication."
The words "at any time£ are central to the argument on this application.
"It will only be appropriate in rare cases for the TCC to intervene in an ongoing adjudication. It is important that, wherever possible, the adjudication process is allowed to operate free from the intervention of the Court."
"What these cases make clear is that although the Court has the necessary jurisdiction to grant an injunction in respect of an ongoing adjudication, it will only do so very rarely and in very clear cut cases."
"…it is only in very rare cases that the Court will interfere in the adjudication process by way of injunctive relief…"
"The issue here, therefore, is whether this referral to adjudication has been brought unreasonably and oppressively. I would emphasise that these two requirements are disjunctive. A referral to adjudication may be unreasonable (for example, if deliberately delayed until shortly before Christmas) without necessarily being oppressive. Alternatively, it may prove to be oppressive, perhaps because unknown to the referring party, the relevant personnel within the responding party have just been posted abroad - without having been unreasonably started. Both elements must be present and, in my judgment, to a fairly high degree.
69 …In my view, the starting point must be the statutory right to refer a dispute to adjudication "at any time" pursuant to section 108 of the Housing Grants Construction and Regeneration Act 1996. In this context, the authorities support the following propositions.
(i) The fact that a referral to adjudication is brought in parallel with existing litigation restraining the same issue is not in itself a ground for restraining the referral…
(ii) The mischief at which the 1996 Act is aimed is the delays in achieving finality in arbitration or litigation…
(iii) The right to refer a dispute to adjudication at any time confers a commercial advantage on the referring party and this must be taken to have been known by Parliament when the 1996 Act was passed: see Camden London Borough Council v Makers UK Ltd [2009] EWHC 605 (TCC) at paragraph 32. One aspect of this advantage is the fact that the responding party will in most cases incur irrecoverable costs in defending the adjudication, and this can operate as a bargaining lever in favour of the referring party.
(iv) A party should not be prevented from pursuing its right to refer a dispute to adjudication, save in the most exceptional circumstances, see Makers at paragraph 35."
"In saying this I do not underestimate the difficulties in which Twintec and its experts have been placed by VFL's decision to refer this dispute to adjudication at this particular juncture. Undoubtedly, if the referral were to proceed it would put Twintec and its advisers under great pressure, but in my judgment that pressure is not of itself sufficient to amount to an exceptional circumstance so as to justify the court in restraining VFL from further pursuit of the referral…"
"The court's power under section 37 may be exercised… (b) where one party to an action has behaved, or threatens to behave in a manner which is unconscionable. The court's jurisdiction extends to a power to grant an injunction restraining a party from commencing or continuing an adjudication that is unreasonable and oppressive, although the fact that a claim is being pursued by way of adjudication rather than litigation may affect the court's view as to whether or not it amounts to unreasonable and oppressive behaviour…"
"35. The court has power to grant an injunction to restrain the second adjudication if it is established that it is unreasonable and oppressive. Such power will be exercised where the adjudicator does not have jurisdiction (such as where the dispute has already been decided in an earlier adjudication), where the referring party has failed to comply with the adjudication agreement (such as failures to pay awards or costs from earlier adjudications), or where the further adjudication is vexatious (such as serial adjudications in respect of the same claim).
36. …The court will not intervene unless the further reference is both unreasonable and oppressive. In this case, the substance of the claims remains the same and therefore, Jacobs will be entitled to rely in large part on its prepared response. Although there is new material, including new quantum expert evidence, it was anticipated that there might be new arguments raised by Skanska following Jacobs' response; hence the indication that Jacobs would seek the right to submit a rejoinder. The inconvenience and additional costs suffered by Jacobs as a result of the second adjudication are not so severe or exceptional so as to warrant intervention by the courts by way of injunctive relief."
Beck's argument
"The final reason why I have concluded that I should not grant the declaration sought this morning is that my refusal at this stage does not leave the Claimant without a remedy. Assume that this adjudication proceeds and leads to a result which the Claimant does not like, which result the Claimant ascribes to specific breaches of natural justice that occurred during the adjudication process. The Claimant will be entitled to rely on such breaches, if they can be made out, to resist enforcement, subject of course to the usual rules and as to the demonstration of prejudice and the like. On that occasion, the Judge will be in a much better position to see whether or not any breaches of the rules of natural justice have actually taken place and if so, whether they have caused real prejudice to the Claimant. That is an exercise which, because of the pre-emptive nature of this application, I am unable to take today."
Further discussion
(proceedings continue)
Indemnity costs
(proceedings continue)
Summary assessment