[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> ISG Retail Ltd v FK Construction Ltd [2024] EWHC 878 (TCC) (18 April 2024) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2024/878.html Cite as: [2024] EWHC 878 (TCC), 213 Con LR 182, [2024] TCLR 65 |
[New search] [Printable PDF version] [Help]
KING'S BENCH DIVISION
BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES
TECHNOLOGY AND CONSTRUCTION COURT
Fetter Lane, London, EC4A 1NL |
||
B e f o r e :
____________________
ISG RETAIL LIMITED |
Claimant |
|
- and - |
||
FK CONSTRUCTION LIMITED |
Defendant |
____________________
Simon Hargreaves KC and James Frampton (instructed by Addleshaw Goddard LLP) for the Defendant
Hearing date: 15th February 2024
____________________
Crown Copyright ©
NEIL MOODY KC:
Introduction
Part 8
a. The Part 8 procedure is to be used where the Claimant seeks the Court's decision on a question which is unlikely to involve a substantial dispute of fact: CPR 8.1(2);
b. The Court may at any stage order the claim to continue as if the Claimant had not used the Part 8 procedure and, if it does so, the Court may give any directions it considers appropriate: CPR 8.1(4);
c. The Part 8 procedure is designed for the determination of relevant claims without elaborate pleadings: White Book 8.0.1; ING Bank NV v Ros Roca SA [2012] 1 WLR 472.
The Sub-Contract
9. Progress and Practical Completion
…
(2) The Sub-Contractor shall contact ISG's Site Representative 14 days prior to each anticipated start on site date for the Works and each section thereof to confirm these dates. ISG may instruct that the Works and/or any section(s) thereof are started on site on a later date, in which event the Sub-Contractor shall be entitled to claim an extension to the Completion Date for the Works and/ or the relevant section(s) of the Works but shall not be entitled to claim any additional payment (whether pursuant to any term of this Sub-Contract or as damages) in respect thereof.
(3) After commencing the Works and each section thereof in accordance with the above provisions, the Sub-Contractor shall proceed with the Works and each section thereof regularly and diligently and shall achieve practical completion of the Works and each section thereof on or before the Completion Date relevant thereto. The Works and each section thereof are to be carried out diligently and in such order, manner and time as ISG may reasonably direct.
(4) The Sub-Contractor shall notify ISG forthwith in the event it becomes aware that progress of the Works is being or is likely to be delayed and/or that it may achieve practical completion of the Works or any section thereof after the Completion Date relevant thereto, together with details of the cause of the delay and the date upon which the Sub-Contractor considers it will achieve practical completion of the Works and/or the relevant section.
Without limiting the Sub-Contractor's obligations hereunder and at no cost to ISG, in such event ISG may instruct the Sub-Contractor to accelerate its performance of the Works and/or any section(s) except where the Sub-Contractor has been delayed by one of the events set out in clause 9(5)(a) to (d) below.
(5) If the Sub-Contractor shall be delayed in the practical completion of the Works and/or any section thereof:
(a) by any circumstance or occurrence (other than a breach of this Sub-Contract by the Sub-Contractor) entitling ISG to an extension of time under the Principal Contract; or
(b) by the ordering of any variation to the Works as defined in clause 18(2); or
(c) by any breach or act of prevention on the part of ISG; or
(d) by a valid suspension by the Sub-Contractor of performance of its obligations pursuant to clause 2(15)(b),
then in any such event the Sub-Contractor shall be entitled to a fair and reasonable extension to the Completion Date(s) for the Works and/or the section(s) of the Works affected by such delay provided that[1] the Sub-Contractor has given written notice to ISG of the circumstance or occurrence which is delaying him and details of the effects or likely effects of such delay with a best estimate of the continuing extent of such delay and its impact on practical completion of the Works and/or the relevant section within fourteen days of such circumstance or occurrence first occurring (or in the case of a variation, within the period specified in clause 18).
…
(7) The obligation of ISG to grant an extension to any Completion Date is also conditional upon the Sub-Contractor demonstrating to the reasonable satisfaction of ISG that the relevant delay will or is likely to delay practical completion of the Works and/or any section(s) beyond the Completion Date relevant thereto, the Sub-Contractor having used its best endeavours to prevent delay to practical completion of the Works and each section thereof and shall continue to do all that may reasonably be required to ISG's satisfaction to proceed with the Works and each section thereof. The Sub-Contractor shall not be entitled to an extension of any Completion Date to the extent that the practical completion of the Works and/or any section thereof is delayed by the Sub-Contractor's negligence or breach of this Sub-Contract.
(8) If the Sub-Contractor is in breach of any of the foregoing provisions of this clause 9 then the Sub-Contractor shall not have any entitlement to an extension of time in relation to any delay to which such breach or breaches relates and without prejudice to ISG's other rights and remedies the Sub-Contractor shall without prejudice to and pending the final determination or agreement between the parties as to the amount of the loss or damage suffered or which may be suffered by ISG in consequence thereof forthwith pay or allow to ISG such sum in which event ISG shall be entitled to deduct such sum from any amount otherwise payable to the Sub-Contractor as ISG shall bona fide estimate as the amount of such loss or damage such estimate to be binding and conclusive upon the Sub-Contractor until such final determination or agreement. Such estimate may include without limitation a sum in respect of liquidated and ascertained damages paid or to be paid by ISG under the Principal Contract where ISG reasonably considers that the Sub-Contractor has caused or contributed to delay to practical completion of ISG's works under the Principal Contract.
….
20. Loss and/or Expense
(1) if in the execution of this Sub-Contract, the Sub-Contractor incurs or is likely to incur direct loss and/or expense for which the Sub-Contractor would not be reimbursed by a payment under any other provision in this Sub-Contract because the progress of the Works or any part of them has been or is likely to be materially affected by:-
(a) the ordering of any variation to the Works…
(b) any breach or act of prevention on the part of ISG; or
(c) any other circumstances or occurrence (other than a breach of this Sub-Contract by the Sub-Contractor) entitling ISG to loss and/or expense under the Principal Contract,
then the Sub-Contractor may make written application to ISG within 14 days of it having become, or when it should reasonably have become, apparent to the Sub-Contractor that the regular progress of the works has been or is likely to be materially affected.
(2) If the Sub-Contractor makes an application as referred to in clause 20(1), then save where this Sub-Contract provides that there shall be no addition to the Sub-Contract Sum or otherwise excludes the operation of this clause, then the amount of the direct loss and/or expense which has been or is being incurred shall be ascertained by ISG; provided always that the Sub-Contractor shall:
(a) make its application as soon as it has become, or should reasonably have become, apparent to the Sub-Contractor that the progress of the Works or any part of them has been or is likely to be affected;
(b) in support of its application submit to ISG upon request such information and details as ISG may reasonably require; and
(c) in addition to clause 20(2)(a) and (b), provide ISG with such notices, documents and other information as may be required in good time so as to enable ISG to claim loss and/or expense in accordance with the terms of the Principal Contract,
and provided always that no allowance shall be made as part of any ascertainment under this clause for any direct loss and/or expense for which the Sub-Contractor would be reimbursed under any other provisions of this Sub-Contract. The Sub-Contractor shall not be entitled to any loss and/or expense to the extent that it fails to comply with the provisions of clause 20(1) and/or 20(2) in respect of such direct loss and/or expense and/or such direct loss and/or expense is attributable to the Sub-Contractor's negligence or breach of this Sub-Contract.
[bold added]
The Relevant Factual Background
FK EARLY WARNING REPORT
Project: C3411 - CENTRAL PARK,
AVONMOUTH Created by: Alfie Eagle
Date & time: 2021-10-05 10:18:27 Ref: C3411/0005
Description of work:
Wall Cladding GL L Unit 8
Reason for early warning:
Due to heavy rain fall this has caused the ground on GL L to sink and also crack, ISG have been made aware of this and have asked a structural engineer to come to site, they have told us no plant is to go onto the elevation until this is rectified
Labour:
TBC
Plant:
TBC
Demurrage:
Delay to works starting
These Part 8 Proceedings
(1) On its express terms or as a matter of true construction, compliance with clause 9(5) of the Sub-Contract dated 28 September 2021 was a condition precedent to FK's entitlement to an extension of time.
(2) The Early Warning Notices issued by FK on various dates as listed in the Schedule to this Order ("the EWNs") and upon which FK relied to support its claim for a 188 day extension of time dated 16 June 2022, did not satisfy the requirements of clause 9(5) of the Sub-Contract.
(3) ISG did not waive, and is not estopped from relying upon, its right to insist upon compliance with clause 9(5). ISG is therefore not prevented from relying upon FK's failure to comply with clause 9(5) as a basis for refusing to award FK the extension of time it claimed on 16 June 2022.
(4) FK was therefore not entitled to the 188 day extension of time which the adjudicator declared it was entitled to, and his declaration number 2 in his Decision dated 14th April 2023 was wrong, is overturned, and shall not be enforced against ISG.
(5) The EWNs were not valid notices capable of forming part of any valid claim to an entitlement to any extension of time under clause 9(5) of the Sub-Contract.
The Parties' Submissions in Outline
Is clause 9(5) a condition precedent?
Breach
"In such instances [late handover by ISG] EWNs were not issued by FK, but we relied on the written email exchanges and/or progress reports and/or DABS meeting minutes as providing notice of delays pursuant to clause 9(5)."
"ISG held daily, weekly and monthly progress meetings to review and coordinate the works where it was made clear the requirements of both the preceding and proceeding trades. Dates were agreed which in turn led to works being programmed in with the following trades. FK continually failed to meet the agreed dates and durations and, in an attempt to mitigate further delays, disruption and abortive costs to follow on trades ISG were left with no alternative but to allow follow on trades to proceed when they were left with no other option."
Waiver/ Estoppel
"In general Part 8 proceedings are wholly unsuitable for the trial of an issue of estoppel. Once such a claim is disputed, save in exceptional cases, the proceedings will cease to comply with CPR r 8.1(2)(a), since they will cease to be proceedings in which the parties do not seek the court's decision only on questions which are 'unlikely to involve a substantial dispute of fact'. A disputed claim of estoppel should be carefully pleaded."
"(i) It is not enough that the common assumption upon which the estoppel is based is merely understood by the parties in the same way. It must be expressly shared between them.
(ii) The expression of the common assumption by the party alleged to be estopped must be such that he may properly be said to have assumed some element of responsibility for it, in the sense of conveying to the other party an understanding that he expected the other party to rely on it.
(iii) The person alleging the estoppel must in fact have relied upon the common assumption, to a sufficient extent, rather than merely forming his own independent view of the matter.
(iv)That reliance must have occurred in connection with some subsequent mutual dealing between the parties.
(v) Some detriment must thereby have been suffered by the person alleging the estoppel, or benefit thereby have been conferred upon the person alleged to be estopped, sufficient to make it unjust or unconscionable for the latter to assert the true legal (or factual) position."
"It is well established that if a party to a contract who is entitled to receive performance of an obligation by a stipulated date represents to the other that he is willing to accept performance out of time and the other relies on that representation, he cannot insist on performance by the date originally stipulated. If the representation is made before the time for performance has come, the waiver will operate by way of equitable estoppel. If it is made after the time for performance is past it may also take effect as an election to affirm the contract."
a. First, ISG by its conduct at the time of the delays arising on site, and in particular its engagement with FK in identifying delays and providing new access dates was, in the light of the relevant factual context, to be regarded as having waived the obligation to provide notification of delay, or was estopped from insisting on clause 9(5) notices in respect of those delays over and above the documents and information which FK did provide;
b. Second, FK issued 106 EWNs and ISG never disputed their use. ISG never complained that FK's forecasts of delay were not best estimates. FK's Managing Director, Paul Bentley, says (para [52]) that:
"To the best of my knowledge and belief, ISG did not and has never claimed (at least up until the date of the Molloy Adjudication), that FK was in breach of clause 9(5) of the subcontract (or any other clause) because of failings/ inadequacies in the EWNs… FK issued over 100 of these notices and [ISG] therefore had ample opportunity to point this out to FK upon receipt if they believed this to be the case. Further I had numerous conversations with [ISG's] Martin Melges (commercial manager), Paul Jones (commercial director), Martin Fletcher (operations director), Mark Cesnek (managing director) during the course of the works and nobody ever questioned or disputed the practice of notifying of delays or potential delays via EWNs. On that basis, the position on the EWNs that ISG took in the Molloy Adjudication and now in these proceedings is entirely contrived; there was simply no issue with FK using EWNs to notify ISG in a timely manner of delays and potential delays at that time."
FK say that ISG engaged with the EWNs, starting with AFP9 in February 2022. FK relied upon ISG's "EWN Response Schedule" which was regularly updated.
c. Third, (echoing the argument made in the adjudication) FK's formal extension of time claim was issued in May 2022, ISG's response was issued on 7 September 2022, but ISG did not then say that FK's claim was precluded by a failure to comply with clause 9(5). ISG, by taking no point on the absence of notices when responding to FK's formal extension of time claim, is to be regarded as having waived the obligation to provide notification of delay and ought to be estopped from insisting on clause 9(5) notices in respect of those delays.
d. Fourth, ISG by stating in its Payless Notice that the prolongation costs were "Not agreed; Full review to be undertaken once works completed" was to be regarded as having waived the 14 day obligation in clause 9(5) notices.
a. ISG received the EWNs and engaged with them. ISG addressed issues of delay on site. ISG did not complain about the EWNs or say they were non-compliant until the adjudication. ISG therefore behaved in such a way as to lead FK to believe that they were waiving the defect in the EWNs. They behaved and conducted themselves in such a way that they had foregone reliance on clause 9(5);
b. Alternatively there was a convention that ISG would engage with FK and ask for further information as if the clause had been complied with;
c. In the further alternative there was an estoppel by representation which arose from ISG's conduct and by FK "going off to do more work on the causes of delay".
Is it permissible to seek the final determination of one aspect of an adjudication by Part 8 proceedings?
Conclusion and Disposal
Note 1 In this Judgment I refer to the following words as ‘the proviso’. [Back]