[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Placefirst Construction Ltd v Car Construction (North East) Ltd [2025] EWHC 100 (TCC) (24 January 2025) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2025/100.html Cite as: [2025] EWHC 100 (TCC) |
[New search] [Printable PDF version] [Help]
Claim No. HT-2024-MAN-000057 |
BUSINESS & PROPERTY COURTS IN MANCHESTER
TECHNOLOGY AND CONSTRUCTION COURT (KBD)
1 Bridge Street West, Manchester M60 9DJ |
||
B e f o r e :
SITTING AS A JUDGE OF THE HIGH COURT
____________________
PLACEFIRST CONSTRUCTION LIMITED |
Part 8 Claimant/ Part 7 Defendant |
|
- and - |
||
CAR CONSTRUCTION (NORTH EAST) LIMITED |
Part 8 Defendant / Part 7 Claimant |
____________________
Simon Arnold (instructed by Weightmans LLP, Liverpool) for CAR Construction
Hearing dates: 20 December 2024
Draft judgment circulated: 6 January 2025
____________________
Crown Copyright ©
Remote hand-down: This judgment was handed down remotely at 10am on Friday 24 January 2025 by circulation to the parties or their representatives by email and by release to The National Archives.
His Honour Judge Stephen Davies
HHJ Stephen Davies:
Introduction and summary of decision
a. Since the court was in a position to determine the Part 8 claim on 20 December 2024 without delaying the resolution of the enforcement proceedings, there was no reason in principle why it should not do so.
b. This was because, if Placefirst was correct in its analysis of the notices, and if it was indeed a short, crisp point requiring little, if any, factual evidence beyond the relevant terms of the contract and the notices in question, with no need for disclosure or witness evidence, it would be unconscionable to enforce the adjudicator's decision.
c. On a proper analysis, CAR had failed to articulate any defence in relation to the points maintained by Placefirst which required any evidence to be adduced above and beyond reference to the contract and to the notices in question and – if necessary - to some undisputed correspondence.
a. First, whether Placefirst did serve what was, on an objective analysis, intended and understood to be a payment notice in accordance with Part 2 of the Housing Grants, Construction and Regeneration Act 1996 (as amended) ("the Act") and the subcontract. This involves an application of established principles to the particular facts of this case.
b. Second, whether Placefirst's payless notice was invalid because it was served (on CAR's case) in advance of the date when it could properly have been served under the Act and the subcontract. This is a point on which I am told there is no authority.
The subcontract
The application and notices in question
"We write further to your application for payment email dated 24 July 2024. We provide our Pay less notice under paragraph 10 of Part II of the Scheme for Construction Contracts (England and Wales) Regulations 1998 (SI 1998/649) (as amended) and section 111 of the Housing Grants, Construction and Regeneration Act 1996 (as amended). We consider that the gross amount due on the date this notice is served to be £2,769,275.56 (excluding retention and VAT) in accordance with our assessment of the works reference Esh Winning - Car Construction - Valuation 30 which has been enclosed for your information."
The statutory provisions
"Payment notices: contractual requirements
110A.—
(1) A construction contract shall, in relation to every payment provided for by the contract—
(a) require the payer or a specified person to give a notice complying with subsection (2) to the payee not later than five days after the payment due date, or
(b) require the payee to give a notice complying with subsection (3) to the payer or a specified person not later than five days after the payment due date.
(2) A notice complies with this subsection if it specifies—
(a) in a case where the notice is given by the payer—
(i) the sum that the payer considers to be or to have been due at the payment due date in respect of the payment, and
(ii) the basis on which that sum is calculated;
(b) in a case where the notice is given by a specified person—
(i) the sum that the payer or the specified person considers to be or to have been due at the payment due date in respect of the payment, and
(ii) the basis on which that sum is calculated.
(3) A notice complies with this subsection if it specifies—
(a) the sum that the payee considers to be or to have been due at the payment due date in respect of the payment, and
(b) the basis on which that sum is calculated.
(4) For the purposes of this section, it is immaterial that the sum referred to in subsection (2)(a) or (b) or (3)(a) may be zero.
(5) If or to the extent that a contract does not comply with subsection (1), the relevant provisions of the Scheme for Construction Contracts apply.
(6) In this and the following sections, in relation to any payment provided for by a construction contract—
"payee" means the person to whom the payment is due;
"payer" means the person from whom the payment is due;
"payment due date" means the date provided for by the contract as the date on which the payment is due;
"specified person" means a person specified in or determined in accordance with the provisions of the contract.
Payment notices: payee's notice in default of payer's notice
110B.—(1) This section applies in a case where, in relation to any payment provided for by a construction contract—
(a) the contract requires the payer or a specified person to give the payee a notice complying with section 110A(2) not later than five days after the payment due date, but (b) notice is not given as so required.
(2) Subject to subsection (4), the payee may give to the payer a notice complying with section 110A(3) at any time after the date on which the notice referred to in subsection (1)(a) was required by the contract to be given.
(3) Where pursuant to subsection (2) the payee gives a notice complying with section 110A(3), the final date for payment of the sum specified in the notice shall for all purposes be regarded as postponed by the same number of days as the number of days after the date referred to in subsection (2) that the notice was given.
(4) If—
(a) the contract permits or requires the payee, before the date on which the notice referred to in subsection (1)(a) is required by the contract to be given, to notify the payer or a specified person of—
(i) the sum that the payee considers will become due on the payment due date in respect of the payment, and
(ii) the basis on which that sum is calculated, and
(b) the payee gives such notification in accordance with the contract, that notification is to be regarded as a notice complying with section 110A(3) given pursuant to subsection (2) (and the payee may not give another such notice pursuant to that subsection).
Requirement to pay notified sum
(1) Subject as follows, where a payment is provided for by a construction contract, the payer must pay the notified sum (to the extent not already paid) on or before the final date for payment.
(2) For the purposes of this section, the "notified sum" in relation to any payment provided for by a construction contract means—
(a) in a case where a notice complying with section 110A(2) has been given pursuant to and in accordance with a requirement of the contract, the amount specified in that notice;
(b) in a case where a notice complying with section 110A(3) has been given pursuant to and in accordance with a requirement of the contract, the amount specified in that notice;
(c) in a case where a notice complying with section 110A(3) has been given pursuant to and in accordance with section 110B(2), the amount specified in that notice.
(3) The payer or a specified person may in accordance with this section give to the payee a notice of the payer's intention to pay less than the notified sum.
(4) A notice under subsection (3) must specify—
(a) the sum that the payer considers to be due on the date the notice is served, and
(b) the basis on which that sum is calculated.
It is immaterial for the purposes of this subsection that the sum referred to in paragraph (a) or (b) may be zero.
(5) A notice under subsection (3)—
(a) must be given not later than the prescribed period before the final date for payment, and
(b) in a case referred to in subsection (2)(b) or (c), may not be given before the notice by reference to which the notified sum is determined.
(6) Where a notice is given under subsection (3), subsection (1) applies only in respect of the sum specified pursuant to subsection (4)(a).
(7) In subsection (5), "prescribed period" means—
(a) such period as the parties may agree, or
(b) in the absence of such agreement, the period provided by the Scheme for Construction Contracts.
(8) ..
(9) .."
"36. This regime depends on the issue of a series of notices whereby the payer becomes liable to pay "the notified sum". It is therefore necessary to identify the notice which, by trumping all others, contains "the notified sum" (section 111(2)). It is then possible to pay less than the notified sum (section 111(3)) subject to compliance with the requirements set out in the Act. The obligation to pay the notified sum (or a lesser amount stated in a pay less notice) does not preclude either party's subsequent ability to challenge the true value of the sum due, by means of adjudication or otherwise. But, in the meantime, the notified sum (or lesser amount stated in the pay less notice) is to be paid, with any dispute about true value following on behind.
"…to require an employer at periodic intervals to pay "the notified sum" by the final date for payment, irrespective of whether or not that sum in fact represents a correct valuation of the work to date. If an employer fails to give relevant notice, irrespective of whether this is by mistake, administrative oversight or any other reason, then a sum for which the contractor has applied becomes immediately contractually payable, even if it is wrong in valuation terms."
"46. I was taken during the hearing to a number of authorities in the context of the proper approach to be taken by the court to the interpretation of contractual notices, including Mannai Investment Co Ltd v Eagle Star Life Assurance Co Ltd [1997] AC 749 ("Mannai"), Thomas Vale Construction Plc v Brookside Syston Ltd [2006] EWHC 3637 (TCC) ("Thomas Vale"), Henia Investments Ltd v Beck Interiors Ltd [2015] BLR 704 ("Henia"), Jawaby, Surrey and Sussex Healthcare NHS Trust v Logan Construction (South East) Ltd [2017] BLR 189 ("Surrey and Sussex"), Grove Developments Ltd v S&T (UK) Ltd [2018] BLR 173 ("Grove Developments") and S&T (UK) Ltd v Grove Developments Ltd [2019] BLR 1 ("S&T") (in which the Court of Appeal upheld the reasoning of the Judge on this issue at [57]). There is no need to set these out at length; the principles that they establish and which I must apply in this case are uncontroversial.
i) In considering the true construction of a contractual notice (including notices under the payment regime in the Act – see Grove Developments per Coulson J at [21]-[22] and S&T in the Court of Appeal at [58] per Sir Rupert Jackson), the question is not how its recipient in fact understood it. Instead "the construction of the notices must be approached objectively. The issue is how a reasonable recipient would have understood the notices", i.e. a reasonable recipient "circumstanced as the actual parties were" (see Mannai at 767 G-H and 768B-C per Lord Steyn).
ii) The notice must be construed taking into account the "relevant objective contextual scene", i.e. the court must consider "what meanings the language read against the contextual scene will let in" (see Mannai at 767H and 768A-B). This means that, amongst other things, the reasonable recipient will be credited with knowledge of the relevant contract (see Mannai at 768B-C).
iii) The purpose of the notice will be relevant to its construction and validity (Mannai at 768E).
iv) The court will be "unimpressed by nice points of textual analysis or arguments which seek to condemn the notice on an artificial or contrived basis" (Thomas Vale per HHJ Kirkham at [43]; Grove at [26]). Instead, as Sir Peter Coulson says in paragraph 3.36 of his book on Construction Adjudication (4th ed. 2018), focusing specifically on Pay Less Notices:
"The courts will take a commonsense, practical view of the contents of a payless notice and will not adopt an unnecessarily restrictive interpretation of such a notice…It is thought that, provided that the notice makes tolerably clear what is being held and why, the court will not strive to intervene or endeavour to find reasons that would render such a notice invalid or ineffective".
v) There is no principled reason for adopting a different approach to construction in respect of different kinds of payment notices (for example because some may give rise to more draconian consequences than others) as that would be contrary to the guidance in Mannai (see Grove at [27]).
However:
"the particularly adverse consequences for an employer that follow from, say, a contractor's unanswered application/payment notice are relevant to the test of the reasonable recipient".
vi) To qualify as a valid notice, any payment notice must comply with the statutory (and, if more restrictive, the contractual) requirements in substance and form (Henia per Akenhead J at [17]). Payment notices and Pay Less Notices must clearly set out the sum which is due and/or to be deducted and the basis on which the sum is calculated. Beyond that, the question of whether a notice is or is not a valid notice is "a question of fact and degree" (Grove at [29] and S&T at [53]).
vii) Over and above the question of whether a notice has achieved the required degree of specificity, will be the additional question of whether the document that is alleged to constitute a valid notice was in fact intended to be such and whether it is "free from ambiguity" (Henia at [17] and Grove at [42]). The sender's intention is a matter to be assessed objectively taking into account the context. (Jawaby at [43], [59] and [63]).
viii) Although in Grove, Coulson J observed that payment notices must make plain what they are, there is no requirement for a particular type of notice, such as a Pay Less Notice, to have that title or to make specific reference to the contractual clause in order to be valid: "[t]he question is whether, viewed objectively, it had the requisite intention to fulfil that function" (Surrey & Sussex at [65]).
ix) One way of testing the validity or otherwise of a Pay Less Notice will be to see whether it "provided an adequate agenda for an adjudication as to the true value of the Works…" (Henia at [32] and Grove at [26]).
Issue 1 – was the payless notice a valid payless notice
a. Under the amended form of subcontract CAR was required by clause 4.6 to submit an interim payment application which was to include "a statement of the sum that [CAR] considers to be due to him … at the date when the relevant interim payment shall be calculated and the basis on which that sum is calculated" (emphasis added). This was subtly different to clause 4.6.2 of the standard form which, where the subcontract particulars state that it applies, the sub-contractor is required to submit an application "stating the sum the sub-contractor considers will become due to him at the due date and the basis on which that sum is calculated" (emphasis also added).
b. The wording as amended complies with s.110A(3)(a), whereas the unamended wording does not, because it refers to a sum the sub-contractor considers will become due at a future date. In my judgment s.110A(3)(a) cannot properly be read as if it said "the sum that the payee considers to be or to have been due or that will become due at the payment due date" (underlining added).
c. It follows that the interim payment application given by CAR in compliance with the contract as amended met the requirements of a payment notice under s.110A(3), even though it would not have the effect of a payment notice unless and until Placefirst had failed to give a valid payer's payment notice.
d. It also follows that on the hypothesis identified in paragraph 40 above, i.e. that Placefirst did not serve a valid payment notice, then s.111(2)(b) applied, because the interim payment application was the relevant notice, and it thus follows that Placefirst's payless notice was not given "before the notice by reference to which the notified sum is determined".
Issue 2 - Did Placefirst give a payment notice on 31 July 2024?