![]() |
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] [DONATE] | |
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Carrington v American International Group UK Ltd [2025] EWHC 1010 (TCC) (28 April 2025) URL: https://www.bailii.org/ew/cases/EWHC/TCC/2025/1010.html Cite as: [2025] EWHC 1010 (TCC) |
[New search] [Printable PDF version] [Help]
BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES
TECHNOLOGY AND CONSTRUCTION COURT (KBD)
Fetter Lane, London, EC4A 1NL |
||
B e f o r e :
sitting as a High Court Judge
____________________
MISS MICHELE CARRINGTON |
Claimant |
|
- and - |
||
AMERICAN INTERNATIONAL GROUP UK LIMITED |
Defendant |
____________________
Elizabeth Boon (instructed by Mills & Reeve, Manchester) for the Defendant
Hearing dates: 19 March 2025
Draft judgment sent 11 April 2025
____________________
HTML VERSION OF JUDGMENT APPROVED
Crown Copyright ©
Remote hand-down
This judgment was handed down remotely at 10:00am on 28 April 2025 by circulation to the parties or their representatives by email and by release to The National Archives.
HHJ Stephen Davies:
The relevant facts
i) Each allegation of breach must be fully and properly pleaded, explaining whether the breach is a breach of contract (if so specifying the relevant contractual term/s breached) and/or an allegation of negligence (if so specifying the particular obligation/s breached) and providing full details of each allegation.
ii) In respect of each such allegation the Claimant must set out a positive case as to why the allegation is not statute-barred, explaining when it is said the obligation / breach in question arose and when (over what period) the events alleged to constitute breach occurred. If it is said that it is a breach of a continuing obligation proper details must be given.
iii) In respect of each such allegation the Claimant must set out a positive case as to what the consequences were of such breach, whether alone or in combination with other alleged breaches, and bearing in mind that the consequences have to be judged in the light of the Claimant's case that the design works undertaken by the Defendant pre-construction stage (for which she cannot claim) were seriously defective and in the light of the Claimant's acceptance that the construction works had already commenced before 17 September 2012, so that the Claimant must clearly explain on what basis breaches occurring after that date made a material difference to the pre-existing position. The Claimant must set out a positive case as to whether or not she is saying that the consequences would have been that Ease would have properly performed the building contract to completion, explaining the basis on why she says so, and whether she says that would have been at the original contract cost or at some extra costs, which is nonetheless less than the cost she says she will now incur, again providing details (and again explaining how breaches which are not time-barred made a material difference to the existing position). If not, then the Claimant must set out a positive case as to what would have happened and how and why she would have been in a better position as a result.
iv) In respect of each such allegation the Claimant must set out a positive case as to what loss and damage she has suffered as a result of such breach and its consequences, again whether alone or in combination with other alleged breaches and again explaining how breaches which are not time-barred made a material difference to the existing position. Insofar as the claims are made on the basis of the Claimant's inability to fund completion works after the termination of the contract by Ease, including in particular any overall increase in construction costs and/or the costs of alternative accommodation, the Claimant must set out particulars of her case as to how – if at all – her financial position was made known to the Defendant pre-contract and/or pre-breach and why her financial position was such that she was unable to fund completion post termination by Ease and/or to fund sufficient works to enable her to continue living in the property but able to fund the costs of renting alternative accommodation.
The Claimant's current pleaded case
48. In paragraph 28AS the Claimant alleges that "throughout the currency of the Project, the Claimant informed the Companies of defects and potential defects". The Claimant continues in paragraph 28AS with a form of wording which, her advisers must have known from the previous hearing, was unacceptable, namely "In particular, but not limited to …", before pleading various notifications from (a) through to (h), which are not cross-referenced to the individual defects pleaded in paragraph 28AR, and include "the facts and matters set out above at paragraphs 28I, 28P and 28AF". In paragraph 28AT it is pleaded: "Each of the defective works identified above was commenced on or after 17 September 2012", which explains why the Claimant says that this claim is not statute-barred, but does not make clear whether these are the defects pleaded in paragraph 28R or 28AS.
The Defendant's strike out / summary judgment application
Breach of duty to review – no real prospect of success
Duty to review - causation – no real prospect of success
"Where a question arises as to what treatment would have been administered had the defendant not committed the breach of duty complained of, the claimant can discharge the burden of proof on causation in one of two ways. The claimant will succeed on causation if he satisfies the court that the defendant would, had he not committed the breach of duty complained of, have taken action which would have avoided the claimant's injuries. Alternatively, the claimant will succeed on causation if he establishes that the proper discharge of the defendant's duty towards him required that the defendant take such action (even if, in fact, the defendant would not have taken such action). In other words, a defendant cannot escape liability by saying that the damage would have occurred in any event because he would have committed some further or alternative breach of duty after or instead of the failure which in fact took place".
"First, although I entertained considerable doubts about the matter while the case was being argued, I have reached the clear conclusion that in principle a defendant should not be allowed to rely on a wrong perpetrated by himself in order (in whole or part) to break the chain of causation put forward by the claimant to establish and quantify the damage sustained by him by reason of the defendant's breach of contract or tort. This may be seen (as Waller LJ expresses it: paragraph 46) as an application of the general rule of the common law that a party may not rely on his own wrong to secure a benefit, and I agree that some support is to be found for that approach in the speech of Lord Browne-Wilkinson in Bolitho . But I think it is also consonant with modern ideas of causation now being developed in the cases. Authority supports the proposition that the resolution of causation issues, certainly in the law of tort, is by no means merely a fact-finding exercise; in many instances it is an evaluative judgment, concerned to establish the extent to which a defendant should justly be held responsible for what has befallen the claimant. This seems to me to be vouchsafed in particular by the opinions of Lord Bingham and Lord Hoffmann in Fairchild [2002] 3 WLR 89 at paragraphs 10–12 and 52–54 respectively; to which may be compared, in the context of damages for loss of a chance, the observations of Kirby J in the High Court of Australia in Chappel v Hart [1999] Lloyd's Law Reports: Med 223 at 245, 246, cited by Latham LJ in this court in Gregg v Scott [2002] EWCA Civ 1471."
Duty to Review - Consequences – No real prospect of success
"In tort, if there are competing causes of the claimant's loss and he is responsible for none of them, he will recover in full if he establishes that the cause for which the construction professional is responsible materially contributed to his loss. In contract, the position is less clear but there is authority for the following propositions:
1. If a breach of contract is one of two causes of a loss, both causes co-operating and of approximately equal efficacy, the claimant can recover his loss in full on the basis that the breach materially contributed to the loss;
2. If one cause of a loss is the defendant's breach of contract and another cause is the contractual responsibility of the claimant, the claimant will recover if he can establish that the cause for which the defendant is responsible is an effective cause of the loss."
Duty to Inspect - Causation – no real prospect of success
Issue 2 and Issue 3 – Amendment and strike-out for breach of unless order and relief from sanctions in respect of such breach