[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Airwave Solutions Ltd v Secretary of State for the Home Department & Anor [2025] EWHC 108 (TCC) (23 January 2025) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2025/108.html Cite as: [2025] EWHC 108 (TCC) |
[New search] [Printable PDF version] [Help]
BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES
TECHNOLOGY & CONSTRUCTION COURT (KBD)
Fetter Lane, London, EC4A 1NL |
||
B e f o r e :
____________________
Airwave Solutions Limited |
Claimant |
|
- and - |
||
The Secretary of State for the Home Department & another |
Defendants |
____________________
Jason Coppel KC, Stephen Kosmin and Benjamin Tankel (instructed by TLT LLP) for the Defendants
Hearing date: 18 December 2024
____________________
Crown Copyright ©
Sir Vivian Ramsey:
Introduction
"15. The Defendants make various prejudicial and highly contentious allegations in relation to Motorola's conduct in performing and exiting the Lot 2 ESN Contract (paragraphs 2(3), 2(4), 2(9), 2(16), 2(18), 2(31), 20(8), 20(9), 27(4), 36). The allegations should be withdrawn. They are of no legal relevance to the Claim and they have been raised in breach of a settlement agreement relating to a dispute which is outside the scope of the Claim. For completeness and the avoidance of doubt, they are denied.
a. Clause 6.3 provides […]
b. Dispute is defined as: […]
c. Reserved Claims is defined as: […]
The Defendants' Submissions
21. The Defendants refer to the amendments in paragraph 27(4)(e) about Wave 7000 and in paragraph 27(4)(h) in relation to Kodiak. They say that the amendments to paragraphs 82(4) and 83(3) to (4) seek to clarify their case on reg.72(1) of the PCR 2015 which provides that modifications may be agreed "for additional works, services or supplies by the original contractor that have become necessary and were not included in the initial procurement …". They say that the amendments to paragraphs 83(3) and (4) relate to the first condition in reg.72(1)(c) of PCR 2015: "the need for modification has been brought about by circumstances which a diligent contracting authority could not have foreseen".
"(2) The negotiated procedure without prior publication may be used for public works contracts, public supply contracts and public service contracts in any of the following cases:
… (c) insofar as is strictly necessary where, for reasons of extreme urgency brought about by events unforeseeable by the contracting authority, the time limits for the open or restricted procedures or competitive procedures with negotiation cannot be complied with. …
(4) For the purposes of paragraph (2)(c), the circumstances invoked to justify extreme urgency must not in any event be attributable to the contracting authority."
The Claimant's submissions
Relevant Authorities
a. A party seeking a late amendment must demonstrate that they have "a real as opposed to fanciful prospect of success which is one that is more than merely arguable and carries some degree of conviction" (see Elite Property Holdings Ltd v Barclays Bank plc [2019] EWCA Civ 204 ("Elite") at [41]. The approach to be taken to a late amendment is therefore that adopted in relation to summary judgment: see CNM at [74]. Provided that a case would survive a summary judgment application, its apparent weakness cannot be taken into account on an application for a late amendment.
b. A claim does not have a real prospect of success where (i) it is possible to say with confidence that the factual basis for the amendment is fanciful because it is entirely without substance; (ii) the party seeking the amendment does not have material to support at least a prima facie case that the allegations are correct; and/or (iii) the amended statement of case has insufficient facts to entitle the court to draw the necessary inferences: see Elite at [41].
c. Where there are significant differences between the parties so far as factual issues are concerned, the Court is in no position to conduct a mini-trial: see ED&F Man Liquid Products Ltd v Patel [2003] CP Rep 51 at [10]. In CNM at §76, the Court of Appeal held: "… it may be necessary to consider, as Carr J [in Quah Su-Ling v Goldman Sachs International [2015] EWHC 759 (Comm)] suggested: "a review of the nature of the proposed amendment, the quality of the explanation for its timing, and a fair appreciation of the consequences in terms of work wasted and consequential work to be done." But even if it is necessary to adopt that approach when the amendment is on the cusp of being "late" and "very late", it will never be appropriate to attempt to conduct a mini-trial."
d. Permission to amend should be refused if it is apparent that a proposed claim would have no real prospect of success (CNM at [69]-[70]).
"Unless the particular circumstances make it obviously unnecessary, a formal application to amend is ordinarily required, with a written document setting out the proposed amendments; and, again in general, there is a merits test to overcome in obtaining permission to amend. The pleading must not only be coherent and properly particularised, it must plead allegations which if true would establish a claim that has a real prospect of success. This means that the claim must carry a degree of conviction; and the pleading must be supported by evidence which establishes a factual basis which meets the merits test."
"(a) The lateness by which an amendment is produced is a relative concept (Hague Plant). An amendment is late if it could have been advanced earlier, or involves the duplication of cost and effort, or if it requires the resisting party to revisit any of the significant steps in the litigation (such as disclosure or the provision of witness statements and expert's reports) which have been completed by the time of the amendment.
(b) An amendment can be regarded as 'very late' if permission to amend threatens the trial date (Swain-Mason), even if the application is made some months before the trial is due to start. Parties have a legitimate expectation that trial dates will be met and not adjourned without good reason (Brown).
(c) The history of the amendment, together with an explanation for its lateness, is a matter for the amending party and is an important factor in the necessary balancing exercise (Brown; Wani). In essence, there must be a good reason for the delay (Brown).
(d) The particularity and/or clarity of the proposed amendment then has to be considered, because different considerations may well apply to amendments which are not tightly-drawn or focused (Swain Mason; Hague Plant; Wani).
(e) The prejudice to the resisting parties if the amendments are allowed will incorporate, at one end of the spectrum, the simple fact of being 'mucked around' (Worldwide), to the disruption of and additional pressure on their lawyers in the run-up to trial (Bourke), and the duplication of cost and effort (Hague Plant) at the other. If allowing the amendments would necessitate the adjournment of the trial, that may be an overwhelming reason to refuse the amendments (Swain Mason).
(f) Prejudice to the amending party if the amendments are not allowed will, obviously, include its inability to advance its amended case, but that is just one factor to be considered (Swain Mason). Moreover, if that prejudice has come about by the amending party's own conduct, then it is a much less important element of the balancing exercise (Archlane)."
a. At [38]:
"a) whether to allow an amendment is a matter for the discretion of the court. In exercising that discretion, the overriding objective is of the greatest importance. Applications always involve the court striking a balance between injustice to the applicant if the amendment is refused, and injustice to the opposing party and other litigants in general, if the amendment is permitted;
b) where a very late application to amend is made the correct approach is not that the amendments ought, in general, to be allowed so that the real dispute between the parties can be adjudicated upon. Rather, a heavy burden lies on a party seeking a very late amendment to show the strength of the new case and why justice to him, his opponent and other court users requires him to be able to pursue it. The risk to a trial date may mean that the lateness of the application to amend will of itself cause the balance to be loaded heavily against the grant of permission;
c) a very late amendment is one made when the trial date has been fixed and where permitting the amendments would cause the trial date to be lost. Parties and the court have a legitimate expectation that trial fixtures will be kept;
d) lateness is not an absolute, but a relative concept. It depends on a review of the nature of the proposed amendment, the quality of the explanation for its timing, and a fair appreciation of the consequences in terms of work wasted and consequential work to be done;
e) gone are the days when it was sufficient for the amending party to argue that no prejudice had been suffered, save as to costs. In the modern era it is more readily recognised that the payment of costs may not be adequate compensation;
f) it is incumbent on a party seeking the indulgence of the court to be allowed to raise a late claim to provide a good explanation for the delay;
g) a much stricter view is taken nowadays of non-compliance with the CPR and directions of the Court. The achievement of justice means something different now. Parties can no longer expect indulgence if they fail to comply with their procedural obligations because those obligations not only serve the purpose of ensuring that they conduct the litigation proportionately in order to ensure their own costs are kept within proportionate bounds but also the wider public interest of ensuring that other litigants can obtain justice efficiently and proportionately, and that the courts enable them to do so.""
b. And at [96]:
"Very late applications for permission to amend in circumstances where a) there is no good reason for the delay and b) amendment would result in real disruption or prejudice to the parties and/or the Court are unlikely to be allowed, irrespective of the merits of the proposed amendment."
"CPR 16.4(1)(a) requires that a particulars of claim must include "a concise statement of the facts on which the claimant relies". Thus, where the particulars of claim contain an allegation of breach of contract and/or negligence, it must be pleaded in such a way as to allow the defendant to know the case that it has to meet. The pleading needs to set out clearly what it is that the defendant failed to do that it should have done, and/or what the defendant did that it should not have done, what would have happened but for those acts or omissions, and the loss that eventuated. Those are 'the facts' relied on in support of the allegation, and are required in order that proper witness statements (and if necessary an expert's report) can be obtained by both sides which address the specific allegations made."
Discussion
a. Paragraph 2(9): "Subsequently, Motorola failed to discharge its obligations to deliver the Lot 2 ESN Contract, whether timeously or at all…".
b. Paragraph 2(16): "On 3 November 2022…, Motorola announced that it would seek to withdraw from the Lot 2 ESN Contract. … Motorola was subject to strong commercial incentives to seek to delay transition to the ESN for as long as possible…".
c. Paragraph 2(31): "The need to re-procure the public contract for the delivery of Lot 2 of the ESN, arising from Motorola's failure to meet its contractual obligations in respect of the Lot 2 ESN Contract and the subsequent termination of the Lot 2 ESN Contract, is a significant source of uncertainty in respect of the date on which transition to the ESN will complete."
d. Paragraphs 27(4)(d), (e) and (g): "there were (inter alia) significant on-going delays to the Lot 2 ESN Contract…
(d) The on-going failure to successfully progress the delivery and implementation of the ESN in line with the contract and delivery plan continued throughout 2017.
(e) On or around 28 August 2017, Motorola acquired Kodiak Networks ("Kodiak"), a company that had developed its own form of PTT communications technology as a potential alternative, and competitor, to the technological solution that Motorola had tendered, and undertaken to deliver, pursuant to the Lot 2 ESN Contract (CMA, §2.93).
(g) Following negotiations from May to August 2018, on 21 September 2018 the First Defendant agreed a contract variation (executed on 14 May 2019) that would permit Motorola to:
i. substitute the Kodiak technology for the technical solution that it had tendered and contractually committed to provide,…".
e. Paragraph 36: "…The re-procurement in respect of Lot 2 of the ESN, and the issue of the 2024 DNSDN, were necessary due to the fact that Motorola did not timeously or effectively achieve the outputs required under the Lot 2 ESN Contract, and the termination of the Lot 2 ESN Contract.".
f. Paragraph 41A(2)(i): "…In any event, it is averred that the position as at early 2022 concerned: (i) Motorola, and the then current position related to its failure to perform its contractual obligations in respect of the Lot 2 ESN Contract…".
g. Paragraph 82(4)(a): "The previous arrangements and extensions in respect of the relevant Blue Light Contracts which demonstrate that Defendants' conduct was reasonable, that there was no relevant "failure" on the part of the Defendants and that the cause (and/or principal and/or material cause) of the need for the previous arrangements and extensions following the original procurement of the ESN was (and is) the conduct, failures and defaults of the Claimant and/or Motorola (and the other appointed ESN providers).".
h. Paragraph 83(3): "It is denied that the relevant conduct of the Claimant and/or Motorola (namely the timing of their withdrawal and terms on which that withdrawal was effected) was reasonably foreseeable.".
i. Paragraph 86(7): "The 2024 DNSDN is necessary for reasons of extreme urgency…brought about by events unforeseeable by the contracting authority, namely the Claimant and/or Motorola's relevant conduct, failures and/or breaches of contract related to the Lot 2 ESN Contract, and….".
a. On the Claimant's formulation: "Whether the asserted need for extensions to the Blue Light Contracts is attributable to any failure by the Claimant rather than the Defendants. [The Defendants] rely upon the timing of MSUK's withdrawal from Lot 2 and the terms on which that withdrawal was effected.".
b. On the Defendants' formulation: "Whether the asserted need for extensions to the Blue Light Contracts is attributable to any conduct of the Claimant.".
a. By the Claimant: "The Claimant maintains its position on this issue, as set out in its 7 August 2024 letter. We suggest the matter be revisited in light of any amendments to the relevant sections of the Defendants' pleaded case (as set out in its Amended Defence).".
b. By the Defendants: "The Claimant's position has been to revert to its first proposals for the formulation of Issue 9 back on 17 July 2024, with some further wording added on 25 July 2024 which it has since insisted upon. The Defendants have amended the description of this issue to properly reflect the Defendants' pleaded case, and suggest that the following paragraph references of the Amended Defence are added to the LoIFD: [2(18)], [2(25)], and [36]. We also see no need for the second sentence in the description of this issue.".
"(4) At trial, the Defendants will refer to the CMA's Report, and facts and matters referred to therein, addressing (inter alia):
a. The previous arrangements and extensions in respect of the relevant Blue Light Contracts which demonstrate that Defendants' conduct was reasonable, that there was no relevant "failure" on the part of the Defendants and that the cause (and/or principal and/or material cause) of the need for the previous arrangements and extensions following the original procurement of the ESN was (and is) the conduct, failures and defaults of the Claimant and/or Motorola (and the other appointed ESN providers).
b. The economic and technical reasons why a change of contractor would, inter alia, result in incompatibility and/or disproportionate technical difficulties.
c. The reasons why a change of contractor would cause significant inconvenience and duplication of costs."
"Whether the asserted need for extensions to the Blue Light Contracts is attributable to any conduct of [the Claimant] rather than [the Defendants], including (i) the change of the technology to deliver the ESN Lot 2 Contract; (ii) representations by the Claimant to the Defendants as to the timeline of its delivery of the ESN Lot 2 Contract; and (iii) the limited utility of the technology used to deliver the ESN Lot 2 Contract following the Lot 2 Termination Agreement."
Conclusion
(1) permission is refused for the re-amendment to paragraph 27(4)(e)(i), (ii) and (iii);
(2) permission is granted for the re-amendment to paragraph 27(4)(h)(i) on the basis that the words "At trial, the Defendants will refer, amongst other things, to:" are deleted and that sub-paragraphs (i) to (vi) are re-phrased as "Particulars" and that sub-paragraph (iv) is drafted to include a concise summary of the particular allegation derived from "Motorola's 'Delivery Improvement' proposals related to security in June-July 2021";
(3) permission is granted for the re-amendment to paragraph 27(4)(h)(ii) on the basis that the words "At trial, the Defendants will refer, amongst other things, to:" are deleted, that sub-paragraphs (i) to (iv) are re-phrased as "Particulars" and that sub-paragraphs (i) to (iii) are drafted to include a concise summary of the particular allegations derived from (i) the Remedial Advisor 'Engagement Observations & Recommendations' report produced by Thought Works dated April 2021, (ii) the IBM Report dated 26 May 2021, (iii) Motorola's 'Delivery Improvement' proposals related to infrastructure, defect management and test automation in June-July 2021.