England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Lapp Industries Ltd v 1st Formations Ltd [2025] EWHC 943 (TCC) (16 April 2025) URL: https://www.bailii.org/ew/cases/EWHC/TCC/2025/943.html Cite as: [2025] EWHC 943 (TCC) |
[New search] [Printable PDF version] [Help]
BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES
KING'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Fetter Lane, London, EC4A 1NL |
||
B e f o r e :
SITTING AS A DEPUTY JUDGE OF THE HIGH COURT
____________________
LAPP INDUSTRIES LTD |
Claimant |
|
- and – |
||
1ST FORMATIONS LIMITED |
Defendant |
____________________
Felicity Dynes (instructed by Bracher Rawlins LLP) for the Defendant
Hearing dates: 25 March 2025
____________________
Crown Copyright ©
Adrian Williamson KC:
i) They repeat the jurisdictional challenge summarised above;
ii) They say that the adjudicator acted in breach of the rules of natural justice by undertaking "a frolic of her own" and/or failing to consider two defences put forward by Formations.
a) Enforcement generally;
b) The jurisdiction argument;
c) The law relating to natural justice;
d) The "frolic" point;
e) The defences allegedly not dealt with;
f) Conclusions.
A. Enforcement
"The court may give summary judgment against a claimant or defendant on the whole of a claim or on an issue if—
(a) it considers that the party has no real prospect of succeeding on the claim, defence or issue; and
(b) there is no other compelling reason why the case or issue should be disposed of at a trial".
"If an applicant for summary judgment adduces credible evidence in support of the application, the respondent then comes under an evidential burden to prove some real prospect of success or other reason for having a trial: Sainsbury's Supermarkets Ltd v Condek Holdings Ltd (formerly Condek Ltd) [2014] EWHC 2016 (TCC) at [13]."
"85. The objective which underlies the Act and the statutory scheme requires the courts to respect and enforce the adjudicator's decision unless it is plain that the question which he has decided was not the question referred to him or the manner in which he has gone about his task is obviously unfair. It should be only in rare circumstances that the courts will interfere with the decision of an adjudicator. The courts should give no encouragement to the approach adopted by DML in the present case; which…may, indeed, aptly be described as "simply scrabbling around to find some argument, however tenuous, to resist payment"".
"it is not uncommon for an application under Pt 24 to give rise to a short point of law or construction and, if the court is satisfied that it has before it all the evidence necessary for the proper determination of the question and that the parties have had an adequate opportunity to address it in argument, it should grasp the nettle and decide it."
B. The jurisdiction argument
"6. At some point in late May 2022, I was contacted by Mr. John O'Donnell, who I understood to be acting on behalf of 1st Formations to look at some potential works to quote the Property.
7. I met him at the Property on 28 May 2022 where he asked me to first quote for some minor works, which I quoted for on 21 June 20221 and these were subsequently carried out on 29 June 2022. At that time, we did not enter into a written contract.
8. While I was carrying out the minor works referred to in paragraph 7 above, Mr. O'Donnell requested that I provide a quotation for demolition and enabling works at the Property. This ended up being the quotation of 17 July 2022. Prior to preparing the quotation, Mr. O'Donnell took me on a tour of the entire building, explaining that additional works throughout the Property would also require quotations once 1st Formations had determined
their specific requirements. Unfortunately, as I will elaborate further in this witness statement, 1st Formations never definitively finalised a specification for any part of the project. Even when a specification was agreed upon, it was frequently altered, either through written communication or verbal instructions.
9. The initial focus was on demolition on the second and third floors, referred to as the "Upper Floors" During this time, it was agreed that I would provide individual quotations for specific items of work. These quotations would then need approval from Mr. Graeme
Donnelly, the director of 1st Formations, before any work could begin. This process of submitting quotations for approval and awaiting confirmation became the basis of how we worked together throughout the project.
10. I submitted quotations for various elements of the works as agreed. These quotations were reviewed by Mr. O'Donnell and then passed on to Mr. Donnelly for final approval. Once each tranche of work was completed, I issued an invoice. It was understood between us that payment for these invoices would be made promptly, and this formed part of the working arrangement throughout the project."
"(1) Interpretation is the ascertainment of the meaning which the document would convey to a reasonable person having all the background knowledge which would reasonably have been available to the parties in the situation in which they were at the time of the contract.
(2) The background was famously referred to by Lord Wilberforce as the 'matrix of fact', but this phrase is, if anything, an understated description of what the background may include. Subject to the requirement that it should have been reasonably available to the parties and to the exception to be mentioned next, it includes absolutely anything which would have affected the way in which the language of the document would have been understood by a reasonable man."
i) Any other analysis is contrived and unrealistic. These business people were not concerned with some artificial carving up of what was, for them, a single, ongoing engagement. The "more than one contract" point would not have occurred to them, and has arisen solely in the context of a very technical argument on jurisdiction, of the kind familiar to lawyers but not, generally, to those involved in commercial negotiations;
ii) All the work was performed at a single site, i.e. the premises;
iii) Both parties referred to the works as a "project". For example, Formations' agent Mr O'Donnell said "please find a spec of works … to kick start the refurb project at 71/75" in an email dated 24 July 2022 where the email attachment title was "New project phases for 71-75 Shelton." LAPP also referred to the works as a "project";
iv) Likewise, Formations' Mr Donnelly referred to a "final account" of the "Reception and Business Centre Re-fit Projects" in his email of 27 February 2023. This is consistent with an overarching contractual arrangement for the "project" as a whole, rather than a series of one-off engagements;
v) Formations made advance payments and/or paid a number of invoices in respect of numerous phases of works at the premises as set out in LAPP's Invoice Payment Summary up to 9 May 2023. These did not necessarily correspond to the individual quotations. Instead, some invoices were in respect of work carried out in different time periods, or advance payment for a proportion of the totality of the works;
vi) There were some fourteen quotations issued by LAPP. It would be surprising if there were at least fourteen separate contracts at a single site. It cannot have been the parties' intention, objectively construed, for there to have been fourteen separate contracts. A reasonable person would not have anticipated that LAPP would have to make numerous separate referrals to adjudication in respect of any payment issues arising across different quotations;
vii) The scenario here – an initial limited engagement, gradually expanded ad hoc – is not unfamiliar in the construction industry and makes far more commercial sense than the suggestion of many separate contracts.
i) The single contract case, based on the June 2022 quotation, is not pleaded by LAPP adequately or at all;
ii) The quotations differ as to their terms, e.g. as to payment, suggesting that these gave rise to fresh contracts;
iii) The workscope evolved in a manner inconsistent with a single overarching contract;
iv) Even if there appears prima facie to be a single contract, there may be matters of conduct, or conversations, which will emerge at trial and which will show matters in a different light.
i) The LAPP pleadings do not cogently advance any such case, but the task for me on these enforcement proceedings is to consider whether there is a real prospect of Formations showing that there were multiple contracts. For the reasons given above, I do not think there is such a prospect;
ii) The quotations do, on occasions, differ in minor respects as to terms, but this does not undermine the overall picture that I have described above;
iii) The workscope did indeed evolve in a somewhat untidy fashion, and grew far beyond the scope of the June 2022 quotation. But that is quite consistent with a single contract gradually being expanded, as required;
iv) This is pure "surmise and Micawberism". Formations do not identify any particular conduct or conversations which point away from the conclusions I have arrived at. On the contrary, this seems to me a suitable case for me "grasp the nettle and decide" the legal effect of largely undisputed facts.
"…Miss Cheng relied upon the decision of Akenhead J in the Air Design case to which I have already referred. In particular she referred me to paragraph 22 of
his decision in that case, where he said this:
"22. However, there are two further factors which effectively override considerations as to whether or not there were one, two, three or four contracts between the parties which establish that the Adjudicator was acting within his proper jurisdiction:(a) The substantive decision-making process upon which the Adjudicator had to embark in relation to the disputed claim put before him necessarily involved a consideration of whether there was more than one contract. It was thus within his
jurisdiction to decide in effect that there was one contract, albeit one that may have been varied by agreement.
(b) It was thus a part of his jurisdiction to decide whether or not and if so to what extent the Basebuild Contract had been varied by the CPA and BMS Arrangements and indeed whether there were yet further variations ordered to the Basebuild Contract. There may be cases, and this is clearly one, where substance and jurisdiction overlap so that it is within the Adjudicator's jurisdiction to decide as matters within his or her substantive jurisdiction whether there have been in
effect variations to the contract pursuant to which he or she has properly been appointed Adjudicator. It cannot then in those circumstances be a valid challenge to his or her jurisdiction that upon analysis he or she may be wrong as a matter of fact or law in determining that such variations were made to the originating contract as opposed to a series of later legally unconnected contracts.
(c) ...
I have therefore formed the view that the Adjudicator did have jurisdiction to rule on all the matters which he did decide in his Decision. Whether he was right or wrong to find or make the assumption that there was effectively one contract which was varied and whether he was wrong as a matter of fact or law in any other part of his decision is
immaterial. Any such errors do not mean that he does not have jurisdiction. Even if I was wrong about that conclusion, then my analysis that effectively the CPA and BMS Arrangements and the Supplementary Agreement were simply variations of the Basebuild Contract would apply." …
77. Akenhead J has revisited his decision in Air Design in two further decisions, the first being Camillin Denny Architects v Adelaide Jones & Co [2009] EWHC 2110 (TCC) and the second being Supablast v Story Rail [2010] EWHC 56 (TCC).
78. In the Camillin case he commented on Air Design in the following terms:
"30. That was a case in which there could be no doubt that the adjudicator was properly appointed under the first contract and there could be no argument that, in that capacity, he had jurisdiction to decide whether later "contracts" were simply variations of the first contract or stood on their own entirely separately as contracts in their own right. I am
not convinced that this case is authority for any proposition other than that there may be cases in which adjudicators properly appointed have jurisdiction to resolve jurisdictional issues if and to the extent coincidentally those issues are part of the substantive dispute
referred to adjudication."
79. In the Supablast case he referred both to Air Design and to Camillin and then said this:
"29. One must bear in mind that variations, that is additional, altered, substituted or omitted works, are very common and almost invariably feature in payment disputes between construction contract parties. Many of the adjudication decisions which come to be considered by the TCC involve rulings on whether particular work has been varied and
if so what price is to be put on it. Generally, an adjudicator properly appointed under the original contract between the parties to the adjudication will have jurisdiction to determine whether or not particular work was or was to be treated as a variation under
or pursuant to that original contract. Of course, it is open to either party to argue that, although the particular work was extra to the scope of works covered by the original contract, it was not a variation envisaged or permitted by that contract. That argument will or may in effect give rise both to a substantive defence under the original contract ("there is no entitlement to payment because there is no variation") as well as a jurisdictional challenge ("the adjudicator has no jurisdiction to decide because the extra work cannot have been ordered under the original contract which gives the adjudicator jurisdiction in the first place"). This is where there will often be an overlap between jurisdiction and substance."
C. The law relating to natural justice
"86. It is only too easy in a complex case for a party who is dissatisfied with the decision of an adjudicator to comb through the adjudicator's reasons and identify points upon which to present a challenge under the labels "excess of jurisdiction" or "breach of natural justice"…The task of the adjudicator is not to act as arbitrator or judge. The time constraints within which he is expected to operate are proof of that. The task of the adjudicator is to find an interim solution which meets the needs of the case.
87. In short, in the overwhelming majority of cases, the proper course for the party who is unsuccessful in an adjudication under the scheme must be to pay the amount that he has been ordered to pay by the adjudicator. If he does not accept the adjudicator's decision as correct (whether on the facts or in law), he can take legal or arbitration proceedings in order to establish the true position. To seek to challenge the adjudicator's decision on the ground that he has exceeded his jurisdiction or breached the rules of natural justice (save in the plainest cases) is likely to lead to a substantial waste of time and expense as,
we suspect, the costs incurred in the present case will demonstrate only too clearly."
(See also to similar effect: CG Group Ltd v Breyer Group Plc [2013] EWHC 2722 (TCC) at para 31(e)).
"22. It is also well understood that an adjudicator must observe the rules of natural justice. In this context, that means that he should not decide a point on a factual or legal basis that has not been argued or put forward in the submissions made to him: see Balfour Beatty Construction v London Borough of Lambeth [2002] BLR 288. However, this rule is often easier to state than to apply.
23. If an adjudicator has it in mind to determine a point wholly or partly on the basis of material that has not been put before him by the parties, he must give them an opportunity to make submissions on it. For example, he should not arrive at a rate for particular work using a pricing guide to which no reference had been made during the course of the referral without giving the parties an opportunity to comment on it.
24. By contrast, there is no rule that a judge, arbitrator or adjudicator must decide a case only by accepting the submissions of one party or the other. An adjudicator can reach a decision on a point of importance on the material before him on a basis for which neither party has contended, provided that the parties were aware of the relevant material and that the issues to which it gave rise had been fairly canvassed before the adjudicator."
"48. A number of authorities have referred to the question of natural justice in the context of adjudications. I respectfully adopt and endorse the judgment of Coulson J in Pilon Limited v Breyer Group Ltd [2010] EWHC 837 where he reviewed relevant authorities from [17] and provided a summary of the relevant principles at 22. For present purposes it is sufficient to set out his summary, which was:
22 As a matter of principle, therefore, it seems to me that the law on this
topic can be summarised as follows.
22.1 The adjudicator must attempt to answer the question referred to him.
The question may consist of a number of separate sub-issues. If the
adjudicator has endeavoured generally to address those issues in order to
answer the question then, whether right or wrong, his decision is
enforceable: ….
22.2 If the adjudicator fails to address the question referred to him because
he has taken an erroneously restrictive view of his jurisdiction (and has, for
example, failed even to consider the defence to the claim or some
fundamental element of it), then that may make his decision unenforceable,
either on grounds of jurisdiction or natural justice: ….
22.3 However, for that result to obtain, the adjudicator's failure must be
deliberate. If there has simply been an inadvertent failure to consider one of
a number of issues embraced by the single dispute that the adjudicator has
to decide, then such a failure will not ordinarily render the decision
unenforceable: ….
22.4 It goes without saying that any such failure must also be material: ….
In other words, the error must be shown to have had a potentially
significant effect on the overall result of the adjudication: ….
22.5 A factor which may be relevant to the court's consideration of this
topic in any given case is whether or not the claiming party has brought
about the adjudicator's error by a misguided attempt to seek a tactical
advantage. … ."
49. It will be noted that an inadvertent failure to consider one of a number of issues will "ordinarily" not render the decision unenforceable. This qualification admits the possibility that an inadvertent failure may in an extraordinary case bring the principle into play. No clear guidance is available about when an inadvertent failure will render the decision unenforceable. Since the essence of the adjudication process is that the real dispute between the parties should be resolved, it seems to me that the touchstone should be whether the inadvertent failure means that the adjudicator has not effectively addressed the major issues raised on either side. Clearly, as [22.4] of Pilon makes clear, the failure must be material in the sense of having had a potentially significant effect on the overall result of the adjudication."
D. The "frolic" point.
"37. She went off on a frolic of her own in determining that the interim application was valid for reasons not raised by or argued by the parties and on which they were not given the opportunity to comment….
38. In the adjudication, the adjudicator decided that the purported application for payment was a valid application. One point that was central, in 1st Formations' submission, to that decision was her reliance on what she stated to be "the Parties' course of dealing" in respect of previous requests for advance payment (see paragraphs 38, 39, 42 and 43 of the Decision".
E. The defences allegedly not dealt with.
"42. The Adjudicator also failed to consider two of the defences put forward by 1st Formations and in doing so committed a material breach of natural justice because these defences were central to the defence advanced by 1st Formations and/or provide a complete defence to the claim: see paragraphs 35 to 47 of GWM2 [HB/(C.2)1/73-76].
43.Firstly, she failed to consider the defence that "the document relied on did not comply with the requirements of Part II of the [Scheme]" (Response, para 14(9) [HB/(E.3)4/210] and "the Referring Party is not entitled to any payment because: … (1) The documents relied upon as giving rise to an entitlement did not comply with the requirements of Part II of the [Scheme] and are incapable of amounting to a valid application for payment for the reasons set out above" (Response para 19(1) [HB/(E.3)4/213].
44.In the relevant section of her Decision on the issue of the validity of the application at paragraphs headed 'Discussion', no mention is made of this defence or a rejection of it.
45.Similarly, the Adjudicator fails to deal with the defence that the purported application was withdrawn and so cannot be relied on, because LAPP issued a further invoice dated 27 April 2023 which requested the sum of £426,854.52 expressly stated to include the sum of £100,000 plus VAT claimed on 14 April 2023: see paragraphs 19(2)-(4) of 1st Formations' Response."
"It is not necessary for a payment notice to be perfectly drafted. Whilst it must clearly set out the sum which is due and/or to be deducted and the basis on which the sum is calculated; beyond that, the question of whether a notice is a valid notice is a question of fact and degree. Taking a commonsense, practical view of the contents, I am of the view that the Application for Payment makes clear what is being held and why and therefore, I am reluctant to intervene to find reasons that would render the Application for Payment invalid or ineffective which I find to be a valid notice."
"I have considered all material that was submitted by both Parties. Any omission to refer to any material in this Decision should not be taken as a failure to have taken such material into account and given it all due and proper weight."
F. Conclusions