[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
High Court of Ireland Decisions |
||
You are here: BAILII >> Databases >> High Court of Ireland Decisions >> Irish Telephone Rentals v. Irish Civil Service Building Society Ltd. [1991] IEHC 1; [1991] ILRM 880 (8th February, 1991) URL: http://www.bailii.org/ie/cases/IEHC/1991/1.html Cite as: [1991] ILRM 880, [1991] IEHC 1 |
[New search] [Printable RTF version] [Help]
1. The
plaintiff’s main business, as its name indicates, is the letting on hire
of telephone installations and ancillary equipment. The defendant, as its name
proclaims, is a building society. For many years prior to 1982 the plaintiff
and the defendant had enjoyed a mutually beneficial ongoing business
relationship and when, in that year, a major extension of the defendant’s
head office in Molesworth Street was put in train and a new telephone system
required, the defendant naturally turned to the plaintiff to supply it. This it
did and the parties entered into a principal hiring agreement in April 1982
and, in subsequent years, seven supplementary agreements. The defendant also
hired from the plaintiff an internal broadcasting installation to supply an
internal paging system. The first broadcasting contract was dated 17 January
1985 and it was followed by a supplementary contract on 3 January 1986.
2. The
defendant terminated all their hiring contracts with the plaintiff in May 1988
claiming that the defects in both systems justified it in doing so. These
proceedings resulted. The plaintiff contends that the termination was wrongful
and amounted to a repudiation of the defendant’s contractual obligations.
Their claim is for £70,898.27 by way of liquidated or agreed damages
together with £3,607.33 in respect of arrears of rental. Alternatively
they claim damages for breach of contract The facts relating to the two main
contracts are different and I will deal firstly with the telephone contract.
3. The
development of the defendant’s head office was undertaken in two phases,
firstly, the offices on the Westmoreland Street side of the site and then the
offices on the D’Olier Street side. Mr. Evans, the defendant’s
engineer, showed the plans for the phased development to the plaintiff. From
these the plaintiff was able to ascertain the total office space contemplated
in the overall development, the probable number of staff when the development
was completed, and the position of the floor boxes from which internal
telephone connections could be made. No specification was prepared and the
choice of an appropriate telephone system was left entirely to the plaintiff.
The main telephone contract was dated 30 April 1982. Under it the defendant
agreed to hire a ‘Mitel’ SX 200 Switchboard, an operator’s
console, 20 exchange lines (that is, internal lines to staff ‘phones), 28
push button instruments, 2 ‘Kirk’ instruments. An annual rent of
£1,800 (payable quarterly) was provided for, and provision was made for an
annual review of this rent. The hiring was to last for 14 years. Clause 11
contained the clause on which the plaintiff’s claim for liquidated
damages is based and I will return to it later in this judgment. Between April
1982 and September 1987 seven supplementary contracts were entered into under
which the defendant hired additional extension lines and ‘phones bringing
the total number of ‘phones hired to 78. These new contracts involved the
payment of extra rentals. At the date of termination the annual rent in respect
of the main contract and supplementary contracts was £12,505.16.
4. At
the end of 1985 and on different occasions in 1986 complaints were made by the
defendant to the plaintiff about the manner in which this system was working.
In March of 1987 the defendant enquired what sum was payable under clause 11
should it wish to terminate the hiring and it was informed that the amount due
would be £87,178.03 plus the sum outstanding for current rent of
£4,823.14. Later in 1987 the defendant obtained the assistance of a
telephone systems consultant who wrote to the plaintiff on 11 February 1988
sending a detailed specification for a new telephone system and requesting a
quotation for the new system from the plaintiff. The plaintiff’s
quotation (which included a claim for £55,980 ‘by way of premature
cancellation of the existing telephone contract’) was not accepted and
the defendant purchased another system from a rival firm. By registered letter
to the plaintiff’s parent company of the 23 May 1988 the defendant
explained why the plaintiff’s quotation was not accepted and terminated
all the existing hiring contracts. The plaintiff replied on 17 June 1988
advancing the claims which are now incorporated in the present proceedings.
5. The
system which the plaintiffs installed worked satisfactorily until about the
year 1985. From 1985 however problems in relation to it arose which became
progressively worse as the volume of the defendant’s business increased
causing greater demands on the telephone system. The complaints which the
defendants had with the system were two-fold, but inter-related. Firstly
incoming callers began to experience very long delays in having their calls
answered. They heard the ringing tone but the telephone operator failed to
respond to it. Secondly, calls transferred internally from members of the
defendant’s staff were subject to being cut off and reverting to the
switch. The delays which outside callers experienced were very extensive. The
defendant’s solicitor told me how he was required regularly to
‘phone his clients and how he experienced very excessive delays in
attempting to do so. On one occasion he decided to time the delay - it lasted
for 22 minutes during which time the ringing tone was heard but was left
unanswered. The manager of the defendant’s Dundrum branch described to me
how difficult he found it was to get through to head office. He was required to
‘phone on a daily basis and frequently. His estimate was that three out
of every ten calls involved a delay of about five minutes before the call was
answered. The consultant called in to advise the defendants gave up using the
defendant’s listed number because of the delay problem. Many complaints
about the delay were made by members of the public to the defendant’s
telephone operator and other members of the staff.
6. The
internal problem was related to the ‘cradle-tap’ or
‘cradle-flash’ system for transferring internal calls. Instead of a
hold-button on the internal ‘phone when a call had to be transferred (for
example, from a secretary to her principal or from one member of the staff to
another) the cradle of the telephone had to be tapped. The tap had to be exact.
It had to be held for at least a quarter of a second and not more than half a
second. If the tap was for less than a quarter of a second nothing would
happen. If it was for more than half a second the call would revert to the
switch. This produced the phenomenon referred to as ‘backing up’ by
which a great number of calls which were cut off by the cradle tapping system
would queue at the switch for the operator’s attention. Incoming callers
became part of the queue. The evidence satisfies me that a high proportion of
attempts to transfer calls resulted in the calls reverting to the switch. Staff
found the system frustrating and to avoid it a practice developed by which they
requested a colleague to ‘phone the operator to effect the transfer
rather than attempt to do so by the cradle-tapping method.
7. The
situation caused by the backing up of calls was aggravated by another feature
of the system. There were four hold-buttons on the operator’s console.
This number was not sufficient for the volume of calls but in fact only three
were operative in 1987 and 1988. This meant that on only three incoming lines
could the operator answer the caller and put the caller on hold. Thus the
delays suffered by callers were due to a combination of an inadequate number of
hold-buttons and the backing up of calls at the switch caused by the
cradle-tapping system.
8. Complaints
about the system were made verbally to the plaintiffs by Mr. Nolan the
defendant’s general manager. He complained about the system at a meeting
in December 1985 and at six meetings in 1986. A letter written in May 1987
requiring information about the amount payable under clause 11 should the
defendants terminate the contract was written because of dissatisfaction with
the system. This dissatisfaction deepened and towards the end of 1987 an expert
consultant was called in to advise the defendants. As a result specifications
for a new system were prepared and tenders sought. When the plaintiff’s
tender was not accepted the letter of 23 May 1988 was written terminating the
contract. I am satisfied that this decision did not result from a desire to
avoid contractual obligations which the defendants found to be onerous but
because of defects in the system which they found to be insupportable.
9. In
reaching the conclusion that the problems which the defendants encountered were
caused by the defects which I have outlined I have not lost sight of other
possible causes. I have heard the evidence of the telephone operators who were
employed by the defendants at the relevant time. They were both experienced
telephonists and the delays were not caused by their inadequacies. There are
now two operators and a full-time receptionist employed by the defendant. But
this is because of the expansion in the defendant’s business which has
occurred since 1988. Prior to and at the time of the termination of the
contract the telephonist acted as a receptionist. But there is a record of the
level of daily calls received by the defendants at the date of termination and
these could have been adequately handled had the system not been defective. The
problems the defendants encountered were not the fault of the Telecom
Éireann lines or of an inadequate number of lines for incoming calls at
that time. I have had evidence that the Mitel System with cradle-tapping
internal ‘phones has been installed elsewhere and works well. There are,
however, several possible explanations as to why the system worked well
elsewhere but not on the defendant’s premises. For example, the
calibration on the cradle-tapping system in other premises might have been
different or the requirements for transferring internal calls might have been
on a lower level, so that the fact of the system working well elsewhere does
not vitiate the conclusions which, on the balance of probabilities, I have
arrived at on the evidence in this case.
10. That
evidence satisfies me that by 1988 the delays experienced by outside callers
were of a serious nature. As a result the installations hired by the defendants
did not provide a telephone communications system which would enable persons
wishing to communicate by telephone with the defendant to have their calls
answered within a time which would be acceptable to a reasonable caller. The
system, in my judgment, was by that time not fit for the purpose for which it
was being hired.
11. Clause
2 of the principal hiring contract (and in the supplementary hiring contracts)
provided that the agreed hiring rent was to be paid during the continuance of
the contract ‘for the hire of the installation and for maintenance of
same in good working order’. The defects which I have outlined seem to me
to be a breach of the plaintiff’s obligation under this clause as they
failed to provide installations during the continuance of the hiring in good
working order. The working order of the system by 1988 could not be described
as being ‘good’ and it seems to me that the plaintiffs were in
breach of an express term of their contracts.
12. The
defendants were also in breach of a term implied by the Sale of Goods and
Supply of Services Act 1980. By virtue of s. 39 of that Act in every contract
for ‘the supply of a service’, where the supplier is acting in the
course of a business and where goods are supplied under the contract there is a
term implied that the goods will be of ‘merchantable quality’. In
this case the contract which was entered into between the parties was for the
supply of a telecommunications service. The plaintiff entered into the contract
in the course of its business as suppliers of such a service. And goods,
namely, a switchboard, console and telephone sets, were supplied under it.
‘Merchantable quality’ has the same meaning in s. 39 as it has in
s. 14 (3) of the Sale of Goods Act 1893 (inserted by s. 10 of the 1980 Act).
Goods are of ‘merchantable quality’ if they are as fit for the
purpose for which goods of that kind are commonly bought and as durable as it
is reasonable to expect. The durability of the goods is not in question in this
case. What the defendants contend, and I think correctly contend, is that the
goods which they hired were not fit for the purpose of providing a reasonably
efficient telephone system. There was, in my judgment, a breach of the term
implied by s. 39 of the 1980 Act.
13. The
issue which arises now for consideration is one which arises in many cases. It
does not follow that because one party is guilty of a breach of contract that
the other may treat himself as discharged from obligation further to perform
the contract.
14. There
may be many cases in which the court, when presented with a problem of this
sort, may be required to consider whether the term which was broken was
‘a condition’ or a ‘warranty’ or, a ‘fundamental
term’ of the contract but, as the frequently cited case of
Hong
Kong Fir Shipping Co. Ltd v Kawasaki Kisen Kaisha Ltd
[1962] 1 QB 26 shows, this is by no means a necessary exercise to be undertaken
in every case. I think the approach suggested by the judgment of Diplock LJ at
pp.65 and 66 of the report is appropriate to this case. In answer to the
question ‘In what event will a party be relieved of his undertaking to do
that which he has agreed to do but has not yet done?’ he said:-
15. The
contract may itself expressly define some of these events, as in the
cancellation clause in a charter party; but, human prescience being limited, it
seldom does so exhaustively and often fails to do so at all. In some classes of
contracts such as sale of goods, marine insurance, contracts of affreightment,
evidenced by bills of lading and those between parties to bills of exchange,
parliament has defined by statute some of the events not provided for expressly
in individual contracts of that class; but where an event occurs the occurrence
of which neither the parties nor parliament have expressly stated will
discharge one of the parties from further performance of his undertakings, it
is for the court to determine whether the event has this effect or not.
16. The
test whether an event has this effect or not has been stated in a number of
metaphors all of which I think amount to the same thing: does the occurrence of
the event deprive the party who has further undertakings still to perform of
substantially the whole benefit which it was the intention of the parties as
expressed in the contract that he should obtain as the consideration for
performing those undertakings?
17. If
this question is posed in this case there can be only one answer to it. The
‘event’ which occurred in this case is the development of a
situation in which the installation which the defendants had hired
significantly failed to fulfil its purpose. This ‘event’ has
deprived the defendant of the whole of the benefit which it was intended the
defendant would obtain from the hiring agreements. The defendant was therefore,
in my opinion, discharged from further performing the hiring agreements and was
entitled to treat the contract as being at an end and request the plaintiff to
take back their installations. It follows therefore that the plaintiffs are not
entitled to rely on clause 11 of the contract and that their claim for damages
for breach of the hiring contracts relating to the telephone installations also
fails.
18. The
first of these contracts, designed to provide a paging system in the
defendant’s head office premises, was dated 17 January 1985, a
supplementary contract being dated 18 January 1989. Under these contracts the
plaintiff let on hire to the defendant a 60-watt amplifier, a microphone and a
number of loudspeakers for a period of 12 years, the terms of hiring being
similar to those in the telephone contracts. There was a rent review clause, by
the application of which the annual rent had increased to £1,438.16 when
the contracts were terminated. Using the formula contained in clause 11 on
agreed liquidated damages in the event of repudiation the plaintiff’s
claim the sum of £7,936.27 liquidated damages for the nine years remaining
of the hiring contract together with a quarter’s rent claimed to be due
for 1988.
19. The
circumstances of this part of the case are entirely separate from those
relating to the telephone contract. The complaint here is that the loudspeakers
were too loud and that they had no individual volume controls to enable the
sound to be reduced as a result of which some had to be disconnected. Three
were disconnected on Mr. Kelly’s floor and six others may have been. But
the evidence also establishes that this defect could have been easily remedied
by what has been referred to as ‘tapping’ the offending
loudspeakers. I do not think, therefore, that the defendant has established any
breach by the plaintiff of these contracts; it should have given an opportunity
to the plaintiff to rectify the complaint. Even if a breach of contract had
been established it was not one which would have entitled the plaintiff to
terminate the contract on the basis that the breach discharged its obligation
to continue the hiring.
20. What
falls therefore now for consideration is whether the plaintiff is entitled to
an award under clause 11 or whether this clause, as the defendants contend, is
a penalty clause and therefore unenforceable. If it is then I must assess
damages according to common law principles.
22. If
the subscriber that is, the defendant shall repudiate this contract and the
company that is, the plaintiff shall accept such repudiation so as to terminate
this contract the company may thereupon remove the installation and the
subscriber shall pay to the company all payments then accrued and also a sum
equal to the present value on a 5%
basis
of the remaining rentals that would have been payable under this contract if
not so terminated less an allowance of 25%
to
cover the estimated cost of maintenance and value of recovered material. The
said sums shall be payable as liquidated damages it being an agreed estimate of
the loss the company would suffer.
24. It
will be held to be a penalty if the sum stipulated for is extravagant and
unconscionable in amount in comparison with the greatest loss that could
conceivably be proved to have followed from the breach.
25. The
application of this principle is to be seen in the majority decision of the
Court of Appeal in England in
Robophone
Facilities Ltd v Blank
[1966]
1 WLR 1428 in which the court considered a contract for the hiring of a
telephone-answering machine for a seven year period which was repudiated before
the hiring began. The hiring agreement contained a clause which made provision
in the event of premature termination for the payment of agreed liquidated
damages equal to 50%
of
the total of the rentals due. In deciding that the sum of 50% was a genuine
pre-estimate of loss and not a penalty Lord Diplock examined what would be
recoverable by way of damages assessed on common law principles and concluded
that because 50%
of
the gross rent would not produce a figure which was ‘extravagantly
greater’ than those damages the clause was enforceable.
26. Before
considering in greater detail the operation in this case of clause 11, I should
give some more detail of how the plaintiff’s claim is made up.
27. The
plaintiff has calculated that there were nine full years of the agreement to
run from the date of termination. The annual rent at that time (which had been
increased over the years pursuant to the rent revision clause) was then
£1,438.16. This annual rent was discounted over a nine year period by 5%
giving
a discounted figure of £10,222.15. There was added to this one
quarter’s rent unpaid in 1988 (that is, £359.51)
giving
a total of £10,581.66. A figure of 25%
of
this sum was then calculated, that is a sum of £2,645.42. This was
deducted from the sum of £10,581.69 giving a figure of £7,936.27. It
is to be noted that the gross rent for the unexpired nine year period of the
hiring was £13,043.62 according to these calculations.
28. I
have come to the conclusion that the formula contained in clause 11 does not
produce a liquidated sum that can properly be regarded as a genuine
pre-estimate made at the date of the contract of the loss which the plaintiff
would suffer should the contract be prematurely determined and that it is in
reality a penalty and therefore unenforceable. My reasons are as follows:-
29. The
plaintiff has not produced its profit and loss account and so l do not know
what it shows. But I am entitled to apply the knowledge of financial affairs
which is available to every reader of the daily press from which
companies’ net profits as a percentage of their turnover is shown for an
extensive range of different classes of businesses. These, of course, vary
widely. In the retail trade a net profit of 10% of turnover is an average
figure. In some manufacturing companies it may be considerably less or
considerably more. A net profit of 71% of turnover would be a staggeringly
large one in any business and in the absence of proof that this is what the
plaintiff earned I am driven to the conclusion that the estimate of loss
contained in clause 11 is not a genuine pre-estimate but is a penalty.
30. I
cannot therefore allow the plaintiff’s claim based on clause 11 and must
assess damages based on the actual loss I think the plaintiff suffered.
31. The
plaintiff recovered back the equipment let under the contracts but was unable
to re-let or sell them. The plaintiff’s damages will therefore be an
estimate of the profit lost on the transaction, appropriately discounted for
accelerated payment. The gross rent which would have been received for the nine
year balance of the contract was £13,043.62 (assuming no increase, in the
rent, an assumption the plaintiff has made in its calculations). I have been
given no information as to what the plaintiff’s average net profit is,
but bearing in mind that the evidence establishes that the plaintiff’s
business is a competitive one (which would oblige them to keep their hiring
charges at a reasonable competitive level) and that the plaintiff is a long
established firm (which would give it the benefit of a considerable good-will)
I would consider it probable that a net profit of 20% of gross rents is what
the plaintiff would have earned on average. There is nothing to suggest that
there are any special circumstances which would justify an award for breach of
this particular contract on a basis higher than average net profit and so the
plaintiff’s loss of profit for the last nine years of this transaction is
£2,608.72 (20% of £13,043.62). I have very little evidence to help me
on how this sum should be discounted and I will, in the absence of evidence,
accept the 5%
figure
contained in clause 11. This means that there should be a deduction of
£130.47, giving an award for the loss the plaintiff has suffered for this
period of £2,478.29. To this to be added the loss in relation to one
quarter of the 1988 rent, namely, £359.51. 20% of this sum, discounted by
5% is £68.04. This gives a total figure for damages of £2,546.69. The
plaintiff is entitled to an award of this sum.
32. I
have assessed damages in the light of the facts established in this case. I do
not think I am required to assess them on the different basis which the facts
established in
In
the matter of Rank (Ireland) Ltd
[1988] ILRM 751 required.