![]() |
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | |
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Aedifice Partnership Ltd v Shah [2010] EWHC 2106 (TCC) (10 August 2010) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2010/2106.html Cite as: [2010] CILL 2905, [2010] EWHC 2106 (TCC), 132 Con LR 100 |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
AEDIFICE PARTNERSHIP LIMITED |
Claimant |
|
- and - |
||
MR ASHWIN SHAH |
Defendant |
____________________
Stephen Whitaker (instructed by Brindley Twist Tafft and James) for the Defendant
Hearing dates: 6 August 2010
____________________
Crown Copyright ©
Mr Justice Akenhead:
The Facts
"It was good to see the Hall on Monday. I am confident we can make this work. I had a conversation with the Architect yesterday and he is putting together some more information for me so we can set up a budget plan.
…We basically act as client's agent…we [act] more as Project Managers as you can see we input into all levels not just the basic traditional QS role of cost and contract…
As far as fees are concerned acting as Clients Agent/Contract Administrator from commencement to completion we charge 1.5% of the construction cost and usually act also as Planning Supervisor for which we charge 0.5% as above all subject to VAT. We expect there to be a competent Architect, Engineer and other specialist on the design front in place. We can guide them in terms of care home requirements but we do not expect to design for them.
All the guidance and development advice along with working with the funders etc is all included in the fee…
As I understand it you need the bank funding in place in order to fund the project and our fees [sic] we will therefore refrain from invoicing you until such time as some bank funding is available (hopefully to far in the future[sic]). Please note however we are not working at risk…"
"Care Home Development Project Coordination/Client's Agent-Seighford Hall Site, Staffordshire
Further to our discussions regarding care home development and our role, I set out below a broad outline of our role and fee proposal.
Our fee for project coordination from commencement to completion is 1.5% of the construction contract value which is fixed once a tender price is agreed with the contractor. This becomes a fixed lump sum and does not vary. This figure includes all our expenses, but excludes VAT.
Our project coordination/client's Agent services include the following:-
1. Pre-purchase feasibility on sites and advice at this stage…
10. Preparation of the contract documents…
The above is a general outline of our services in both pre-and post-contract stages…
I hope this provides you with an outline of our services and fees. These general proposals apply to any major nursing home construction or refurbishment project and if you have any further queries regarding this please do not hesitate to contact me."
Mr Shah says that he never received this letter. Mr Martin has said that he received an e-mail from Mr Shah accepting the contents of this letter but can not produce that e-mail because, he says, it was only on his laptop which has since been stolen. Mr Shah says that no such e-mail was sent.
The Adjudication
"For the avoidance of any doubt, I do not accept the terms of reference or the standard scale of charges and terms of engagement annexed to your letter dated 26th March 2010.
Please note, that I Ashwin Shah, have no dealings at all with Aedifice Partnership ("APL") whether in a personal capacity all on behalf of any corporate entity and had no liability to this company…
I note that your letter asks APL to forward to you the necessary contractual documentation. I am not aware of any such documentation.
With no disrespect to you, in all of the circumstances, I submit that you have no jurisdiction to deal with this matter and I decline to take any further part in this matter. If APL believes that I am in any way personally indebted to it, it has the option of court proceedings."
"2…(1) on 15 in August 1997… that Company was incorporated…(2) …On 12 May 1998 the Company was registered as proprietor of [Seighford Hall]…
3… (5) …After the site visit [of 31 July 2006] Mr Martin sent Ashwin Shah an e-mail [2 August 2006]…
5… (1) Neither Ashwin Shah nor the Company received a letter dated 20 September 2006… (3) The assertion that "this letter was accepted directly by e-mail" is denied…
7. It is further denied that the letter of 20 September 2006 is an accurate memorandum of the terms of an oral contract.
(1) …the letter is not an accurate memorandum in writing of what was agreed as it omitted an important term namely the event triggering remuneration…
9… (1) It is denied that the contracting party was Ashwin Shah (as opposed to the Company).
10. Accordingly, (a) it is denied that there is any contract between Aedifice and Ashwin Shah (b) it is denied that the letter is an accurate memorandum of the terms of the contract because it misstates an important term, namely the identity of one of the contracting parties…
31… Ashwin Shah invites the Adjudicator to decline jurisdiction, shortly stated for the following reasons:
(1) The issues of whether there was a contract, if so in what terms and between which parties are all live issues which should not be determined on and Adjudication. Disclosure of documents and cross-examination of witnesses would be necessary.
(2) There is a serious dispute whether s. 107 is complied with (i.e. whether the agreement was made or evidenced in writing). There are several elements to this issue. See Paragraphs 5, 7 and 10 (b) above. This dispute is not suitable for determination by the Adjudication procedures; disclosure of documents and cross-examination of witnesses would be necessary. Unless, contrary to these submissions, the Adjudicator is sure that there was a contract made in writing or evidenced in writing complying with s.107 there is no jurisdiction to adjudicate.
31. If the adjudicator does determine that he has jurisdiction he is respectfully requested to give full reasons for that decision and to rejecting the Respondent Party's submissions….
36. If the Adjudicator does accept jurisdiction the questions in Paragraph 107 are agreed as questions."
Aedifice served a Reply to which Mr Shah's solicitors served a Further Response, which apart from making a few specific points concluded by referring back to and repeating the Response.
"6.13 Whilst I do not have the power to determine my own jurisdiction, I am required to consider whether it is more likely than not that I have jurisdiction and if so proceed with the reference. In this instance I am of the view that there is a contract between the parties as contended by Aedifice. That Contract is a "construction contract" in the context of section 104 of the Act and it follows that any dispute may be referred to adjudication.
6.14 I therefore consider it more likely than not that I do have jurisdiction to deal with the dispute referred."
It is noteworthy that in his Conclusion in Paragraph 9 he does not include as part of his Decision or indeed Conclusion anything by way of declaration or otherwise about him having jurisdiction.
These Proceedings
The Law
"12. The law on this topic is clear. Jurisdictional issues often arise during the course of an adjudication, and it is usually sensible for the parties to ask the adjudicator to investigate the issue and state his conclusion. But, unless the parties have also agreed to be bound by the result of the adjudicator's investigation into his own jurisdiction, his ruling on that issue will not be determinative, and the challenger can defeat any subsequent enforcement proceedings by showing a respectable case that the adjudicator had reached an erroneous conclusion as to jurisdiction: see, in particular, paragraph 10 of the judgment of May LJ in Pegram Shopfitters Limited v Tally Weijl (Uk) Limited [2003] EWCA Civ 1750.
13.Accordingly, there needs to be either an express agreement between the parties that the adjudicator's decision on jurisdiction is to be binding or, at the very least, an implied agreement to the same effect, which may arise where the objecting party fails to reserve its position, or there has been a unilateral waiver of any jurisdictional objection. In both JW Hughes Building Contractors Limited v GB Metal Work Limited [2003] EWHC 2421 (TCC) and Nordot Engineering Limited v Siemens Plc [2001] CILL 1778, the court found an ad hoc agreement between the parties that they would be bound by the adjudicator's decision as to jurisdiction, but such cases are rare. Generally speaking, as Dyson LJ put it in Amec Projects Limited v Whitefriars City Estates Limited [2004] EWCA Civ 1418, "the 'decision' of an adjudicator as to his jurisdiction is of no legal effect and cannot affect the rights of the parties….""
"33. The position can I think be summarised in the following two propositions. (1) If a defendant to a Part 24(2) application has submitted to the adjudicator's jurisdiction in the full sense of having agreed not only that the adjudicator should rule on the issue of jurisdiction but also that he would then be bound by that ruling, then he is liable to enforcement in the short term, even if the adjudicator was plainly wrong on the issue. (2) Even if the defendant has not submitted to the adjudicator's jurisdiction in that sense, then he is still liable to a Part 24(2) summary judgment upon the award if the adjudicator's ruling on the jurisdictional issue was plainly right."
"In my view, the defendants' solicitor's letter of 9 March 1999 stated in the clearest terms that the defendants protested the adjudicator's jurisdiction, and that they would not recognise and comply with any decision to award money to the claimant. The letter also made it clear that, if the adjudication proceeded, they reserved their rights to participate, but without prejudice to their contention that there was no jurisdiction. I do not consider that there can be any reasonable doubt as to the meaning of that letter. The only real question is whether, by participating in the adjudication process, the defendants waived the jurisdiction point, and agreed to submit to abide by the decision of the adjudicator on that issue. The only material relied on by Ms Rawley [Counsel] is the content of the defendants' response…But, in their response, the defendants continued to assert that the adjudicator had no jurisdiction…It is a matter of fact whether a parties submit to the jurisdiction of the third person…"
"So far as jurisdiction challenge to an adjudicator is concerned, it is necessary for the party objecting to the adjudicator' jurisdiction to make a clear and full reservation"
The report of that case goes on to review whether an adequate reservation was made and considers, amongst other things, whether the adjudicator proceeded on the basis that there had been a reservation about jurisdiction. In that case, there had been an effective reservation but in the event the jurisdictional challenge was not a good one.
"Various cases such as Thomas Frederic's (Construction) Limited v Keith Wilson [2004] BLR 23 and The Project Consultancy Group v The Trustees of the Grey Trust [1999] BLR 377 make it clear that if there is to be an objection to jurisdiction of the arbitrator generally there should be a clear reservation of the objecting party's stance on jurisdiction. Such a reservation will usually be done effectively by clear words but it could also be done by unequivocal conduct."
(a) An express agreement to give an adjudicator jurisdiction to decide on a binding way whether he has jurisdiction will fall into the normal category of any agreement; it simply has to be shown that there was an express agreement.
(b) For there to be an implied agreement giving the adjudicator such jurisdiction, one needs to look at everything material that was done and said to determine whether one can say with conviction that the parties must be taken to have agreed that the adjudicator had such jurisdiction. It will have to be clear that some objection is being taken in relation to the adjudicator's jurisdiction because otherwise one could not imply that the adjudicator was being asked to decide a non-existent jurisdictional issue which neither party had mentioned.
(c) One principal way of determining that there was no such implied agreement is if at any material stage shortly before or, mainly, during the adjudication a clear reservation was made by the party objecting to the jurisdiction of the adjudicator.
(d) A clear reservation can, and usually will, be made by words expressed by or on behalf of the objecting party. Words such as "I fully reserve my position about your jurisdiction" or "I am only participating in the adjudication under protest" will usually suffice to make an effective reservation; these forms of words whilst desirable are not absolutely essential. One can however look at every relevant thing said and done during the course of the adjudication to see whether by words and conduct what was clearly intended was a reservation as to the jurisdiction of the adjudicator. It will be a matter of interpretation of what was said and done to determine whether an effective reservation was made. A legitimate question to ask is: was it or should it have been clear to all concerned that a reservation on jurisdiction was being made?
(e) A waiver can be said to arise where a party, who knows or should have known of grounds for a jurisdictional objection, participates in the adjudication without any reservation of any sort; its conduct will be such as to demonstrate that its non-objection on jurisdictional grounds and its active participation was intended to be and was relied upon by the other party (and indeed the adjudicator) in proceeding with the adjudication. It would be difficult to say that there was a waiver if the grounds for objection on a jurisdictional basis were not known of or capable of being discovered by that party.
Discussion
Decision