[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Venulum Property Investments Ltd v Space Architects Ltd & Ors [2013] EWHC 3948 (TCC) (17 December 2013) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2013/3948.html Cite as: [2013] EWHC 3948 (TCC) |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Rolls Building, 7 Rolls Buildings London EC4A 1NL |
||
B e f o r e :
____________________
Venulum Property Investments Ltd |
Claimant |
|
- and - |
||
Space Architects Ltd MRP Development Services Ltd Mark Kevin Willmott Richard Stewart Anderson Robin John Ungemuth Abbeyross Ltd |
Defendants |
____________________
Mark Sefton Esq
(instructed by Field Fisher Waterhouse LLP) for the 1st to 4th Defendants
Richard Harrison Esq,
(instructed by Wilkins Beaumont Suckling Ltd) for the 5th and 6th Defendants
Hearing dates: 15th and 22nd November 2013
____________________
Crown Copyright ©
Mr. Justice Edwards-Stuart:
Introduction
The background
The approach
"Both the application to strike out and the application for summary judgment are summary applications. The application for summary judgment is made by defendants against a claimant, which is less usual than an application by a claimant for judgment against a defendant. The authorities deal mainly with applications by claimants. The correct approach on applications by defendants is, in my judgment, as follows:
i) The court must consider whether the claimant has a 'realistic' as opposed to a 'fanciful' prospect of success: Swain v Hillman [2001] 2 All ER 91;
ii) A 'realistic' claim is one that carries some degree of conviction. This means a claim that is more than merely arguable: ED & F Man Liquid Products v Patel [2003] EWCA Civ 472 at [8]
iii) In reaching its conclusion the court must not conduct a 'mini-trial': Swain v Hillman
iv) This does not mean that the court must take at face value and without analysis everything that a claimant says in his statements before the court. In some cases it may be clear that there is no real substance in factual assertions made, particularly if contradicted by contemporaneous documents: ED & F Man Liquid Products v Patel at [10]
v) However, in reaching its conclusion the court must take into account not only the evidence actually placed before it on the application for summary judgment, but also the evidence that can reasonably be expected to be available at trial: Royal Brompton Hospital NHS Trust v Hammond (No 5) [2001] EWCA Civ 550;
vi) Although a case may turn out at trial not to be really complicated, it does not follow that it should be decided without the fuller investigation into the facts at trial than is possible or permissible on summary judgment. Thus the court should hesitate about making a final decision without a trial, even where there is no obvious conflict of fact at the time of the application, where reasonable grounds exist for believing that a fuller investigation into the facts of the case would add to or alter the evidence available to a trial judge and so affect the outcome of the case: Doncaster Pharmaceuticals Group Ltd v Bolton Pharmaceutical Co 100 Ltd [2007] FSR 63;
vii) The court should be especially cautious of striking out a claim in an area of developing jurisprudence, because in such areas decisions on novel points of law should be decided on real rather than assumed facts."
The applications to strike out on the basis that the claim discloses no reasonable cause of action or has no realistic prospect of success
"… it has not entered into this contract in reliance on any representation made by or on behalf of the Seller but not embodied in this contract except to the extent that the Buyer may be entitled to rely on any representation made by the Seller's Solicitors on behalf of the Seller in any written reply to any enquiry made by the buyer's Solicitors on behalf of the Buyer".
Mr. Sefton said that it is not asserted that there were any relevant written replies made in response to enquiries by the buyers' solicitors.
"… to be considered partners in a speculation for the planning and sale of the Enterprise Square scheme including the obtaining planning consent on the basis of plans and drawings which were feasible and could be used for a scheme which could in fact be constructed as illustrated."
In these circumstances, it is alleged that they all owed the alleged duty of care to the Claimant.
"[Mr Ungemuth] and [Mr Miller] acted in breach of an obligation of good faith owed to the Claimant in that they precipitated the Claimant in to making the Contract of Sale whereas if it had had more time the Claimant would have had the opportunity of discovering that the plans and drawings were not feasible and could not be used for a scheme which could in fact be constructed … [They] put their desire to earn commission above their duties to the Claimant."
The applications to strike out on the basis that the claims are statute-barred
"What is meant by actual damage? Counsel for the defendants says that it is any detriment, liability or a loss capable of assessment in money terms and it includes liabilities which may arise on a contingency, particularly a contingency over which the plaintiff has no control; things like loss of earning capacity, loss of a chance or bargain, loss of profits, losses incurred from onerous provisions or covenants in leases. They are all illustrations of a kind of loss which is meant by 'actual' damage. It was also suggested in argument … that 'actual' is rarely used in contrast to 'presumed' or 'assumed'. Whereas damage is presumed in trespass and libel, it is not presumed in negligence and has to be proved. There has to be some actual damage."
"In all those cases, however, the court was able to conclude that the transaction then and there caused the claimant loss, on the basis that if the injured party had been put in the position he would have occupied but for the breach of duty, the transaction in question would have provided greater rights, or imposed lesser liabilities or obligations than was the case; and that the difference between these two states of affairs could be quantified in money terms at the date of the transaction."
"Likewise, the principle that the incurring of a purely contingent liability is not itself damage does not apply where the claimant acquires a contingent liability as a part of a package of rights under a bilateral transaction and the value of that package has been diminished by the negligence of the defendant: see the Sephton case [2006] 2 AC 543, paras 30 and 45, per Lord Hoffmann and per Lord Walker respectively."
"62. Furthermore, in my judgment, it is correct to treat NIG as incurring loss and therefore as suffering damage for the purposes of the accrual of its causes of action in tort as soon as it issued ATE insurance even if [counsel] is correct to say that the measure of damage in this case is on a 'no transaction' basis. The measure of loss is then the difference between its financial position having issued the policies and its financial position if it had not issued them. The fact that it had incurred loss is relevant to the first part of that equation. The additional loss was the fact that the liabilities under those policies to policyholders were more burdensome, and a package of rights which they required under the policies was less valuable, than they should have been if the vetting breaches had not occurred. This was measurable loss additional to the incurring of purely contingent liabilities under the policies of insurance. The liabilities arose at the date of the issue of the policies and can be valued as at the date of the issue of the policies. The loss did not result from subsequent events, such as fluctuations in the value of the property, the event considered in the Nykredit (No 2) case [1997] 1 WLR 1627.
63. The judge inclined to the view that the measure of damage did not determine the question when loss was incurred which was a question of fact: see for example paragraph 59 of his judgment. In my judgment, there must be a correlation between the measure of damages and the incurring of loss for the purposes of the accrual of a cause of action. This is because loss must be recoverable loss if its incurring is to be relevant for accrual purposes: see per Lord Nicholls in the Nykredit (No 2) case [1997] 1 WLR 1627, 1630 F. I would however agree with the judge that damage can be incurred when a transaction is entered into even if damages fall to be assessed on the 'no transaction' basis. In this case, on the assumed facts, loss was incurred by NIG when it wrote the relevant policies."
"31. The judge accepted the argument of [counsel]. He held that the fact that clause 21(ii) could not be used before 31 August 1998 and could only be used if [the builder] failed to complete by that date did not mean that it did not have a value prior to 31 August 1998. In his judgment, although its value depended on a number of factors including the likelihood of the Watkins being able to exercise it after 31 August 1998, it had a value before 31 August 1998 and thus Sephton was distinguishable.
32. In my judgment, the judge was correct for the reasons he gave. When the Watkins entered into the building agreement they acquired a bundle of rights. That bundle of rights was of lesser value than they were on their case led to believe that it would be. Those rights were an asset capable of valuation. Thus, the Watkins suffered measurable loss when they acted on the allegedly negligent advice to enter into the later transaction. Accordingly, the claim is statute-barred."
"I am not persuaded that there is in the general principle that a party to a flawed transaction will only suffer a loss when and if the relevant transaction unconditionally binds that party. In the cases referred to in para 45 (sic) above, the contracts in question were in fact irrevocable, and so it could be said that loss had been suffered on the entry into the same. These cases did not, however, specifically consider the effect of entering into a flawed transaction that might be capable of being remedied by rescission."
"This to my mind explains why as a matter of logic that very entry into a flawed transaction should be seen to give rise to damage, even if capable of remedy. Firstly there is the practical inconvenience of having to rectify the position; secondly, there is the practical point that until the breach of duty was discovered (here the fact that false representations had been made, and that the solicitors had failed to ensure that the filed plan represented what were understood to be the physical boundaries) the flawed transaction would not be remedied, but rather the contract would be completed."
My conclusions on limitation
The application to amend the name of the Sixth Defendant
The disposal of this application
"The Claimant alleges that in about February 2007 it became aware that the supporting posts/pillars in the underground car park shown on the original plans were not of the size indicated on the amended plans and would not support the building. Further revisions resulted in the loss of about 30% of the parking spaces, with the consequence that the development could not be built in accordance with the planning permission. As a result, the Claimant alleges that the value of the property with the existing planning permission was worth far less than the sum that it had paid."
I note in passing that it is rather curious that Mr. Cadman is here referring to what is being alleged in the Particulars of Claim, as allegations, rather than confirming that those allegations are correct.
"51. The principals at the Claimant are commercial people and are not litigious by nature. Before issuing the Claim Form, every effort was being made to ameliorate the damage done by the Defendants. In fact, a planning application was in development that is now before Northamptonshire County Council. The alternative development will restore decent value to the property at Enterprise Square if planning permission is granted. This involves a proposal to construct student accommodation instead of flats. It is a step in mitigation taken at great expense both in terms of management time and money spent.
52. The Claimant initially sought permission to build 450 units. This went to a planning meeting in February 2012. Unfortunately, that application was rejected on the grounds of density. The proposal has now been scaled back to 300 units. I am told by the planning officers that permission would likely have been granted for the reduced proposal in 2012, had been made in those terms at that time. The court will appreciate that our obligation is to maximise any development return, so we had to make the application for the best realistically achievable planning permission. Obviously, this did not work out for the Claimant this time, but it does explain why the Claim Form was only issued shortly before limitation passed.
…
54. The Claimant was progressing the alternative development for most of the time before it issued the Claim Form. A decision is not expected from the planning committee on the scaled-down proposal until at least September 2013."
The Claimant's case in relation to the discovery of the defects in the drawings
i) There was insufficient headroom in the lower ground floor for the depth of the structure that would be required to provide support to the upper floors.ii) There was an absence of columns shown on the lower ground floor plan, with the result that the introduction of suitable columns might jeopardise the number of available car parking spaces or reduce their size to below the dimensions required by the Council.
iii) Various concerns and inconsistencies that he noted in relation to the approved floor plans.