[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Dacy Building Services Ltd v IDM Properties LLP [2016] EWHC 3007 (TCC) (25 November 2016) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2016/3007.html Cite as: 170 Con LR 176, [2016] EWHC 3007 (TCC), [2017] BLR 114 |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
DACY BUILDING SERVICES LIMITED |
Claimant |
|
- and - |
||
IDM PROPERTIES LLP |
Defendant |
____________________
Mr Samuel Townend (instructed by Stepien Lake) for the Defendant
Hearing dates: 22nd October 2016
____________________
Crown Copyright ©
Insert Judge title and name here :
Introduction
The progress of the adjudication
The issues on this application
(i) The Claimant argued that the Defendant had agreed to or submitted to the adjudicator's jurisdiction.
(ii) The Claimant suggested, but did not seriously pursue, an argument that the adjudicator had jurisdiction to determine his own jurisdiction in any event.
(iii) The Claimant argued that the Defendant has no realistic prospect of establishing that there was no contract between the Claimant and the Defendant.
Reservation of the right to challenge the jurisdiction of the adjudicator
The adjudicator's jurisdiction to determine his own jurisdiction
"27. Finally … there is a wider point for consideration here which, although it has been the subject of some commentary, has not been the subject of any previous judicial observation. The point concerns the statutory amendments in respect of written contracts. Before the amendments to the 1996 Act, adjudication could only happen when there was a contract in writing. That was so as to ensure that the adjudicator did not have to deal with complex questions as to contract formation, appropriate terms and the like, in addition to addressing the underlying claims, all in 28 days. Of course, that certainty has now gone, and the adjudicator may have to do all those things within the 28 day period.
28. This case is, I think, a good example of the change. In my view, this would not have been a dispute that could have been referred to adjudication under the old law. However, following the change in the law, it was validly referred to Mr Gupta [the adjudicator] for decision in Adjudication 1. Thus, Mr Gupta had to deal with all of the issues (both contractual and financial) within the limited timetable allowed by adjudication. In my view, in such cases, the courts are going to have to give adjudicators some latitude as they grapple with these difficulties. In an ordinary case, and depending on the words of the notice, it may be unduly restrictive to conclude that an adjudicator could decide what the contract was not, but not what the contract was. Similarly, it may be unduly restrictive to say that any notice of adjudication which raised the existence of the contract and/or its precise terms (on the one hand), and the financial claims thereunder (on the other), somehow involved more than one dispute."
Contract or no contract?
December 2015 to February 2016
"Thanks for your time today and we now understand what are the procedures for that job. management, instructions, timesheets will be done by HOC. we will be invoicing HOC and once HOC are happy with the invoices and also with the works performed on site then they will send the invoice to IDM. IDM will pay Dacy on a monthly basis."
This e-mail was copied to Mr Cutmore and Mr Hewson. This is one of the e-mails which Dacy expressly relied on in the adjudication as evidencing the contract but, on its face, the e-mail is consistent with an arrangement under which Dacy was engaged by HOC (who give instructions for work, deal with timesheets and so on, are invoiced and consider the validity of the invoices) but payment is made by IDM, with the IDM company appearing to be IDM Construction London.
(i) A handful of e-mails was also exhibited from Mr Cutmore to Mr Keran requesting the supply of labour and/or materials. All of these are copied to Graham Hewson and some to Randol Taylor.
(ii) There are a number of e-mails from Mr Hewson requesting or instructing work. Although these are sent from Mr Hewson's IDM Construction London e-mail address, the standard signature at the bottom of the e-mails gives a link to the IDM Properties website and states "This is a communication from IDM Properties LLP".
(iii) These e-mails included the following: (a) From 13 December 2015 to 19 December 2016, e-mails from Mr Hewson to Mr Keran copied to Mr Taylor and Mr McLoughlin; (b) on 22 December 2016 an e-mail to Mr Keran (no ccs) requesting supply and installation of locks stating that "This instruction is on behalf of HOC for the Camberwell new Road Site"; (c) a further e-mail on the same date telling Mr Keran that the joinery contractor has pulled out, asking him to carry out works and saying "Please acknowledge your acceptance of this instruction of and on behalf of HOC".
(iv) I have seen further e-mails sent to Dacy by Mr Hewson in 2016. These were usually copied to Mr Cutmore and some were copied to Randol Taylor. In this early part of 2016, the mantra "For and on behalf of HOC" appears on one e-mail dated 12 January 2016 and on one Site Instruction which refers back to "HOC authorization" by e-mail dated 11 December 2015 (which I have not been able to identify).
(v) I have seen further e-mails from 25 February 2016 from Patrick Beglane to Dacy (no ccs) either instructing or confirming the instruction of work. Mr Beglane used an Outlook address and signed himself "Patrick IDM".
March 2016
"The purpose of the meeting was to identify and allocate the cost of works done by Dacy, to be supported by either HOC, IDM or to be deducted from other Subcontractors."
"Payment application 1 and 2 were paid in full by IDM whereas payment application 3 was paid on account only 50% of its value. As described by Randol before IDM will commit to pay Dacy's application No. 3 in full, HOC will have to agree as well to the cost of the works carried out by Dacy."
"Richard requested Dacy supply him with all applications and back-up claiming that he has never received anything and not agreeing to any payments until he is satisfied (as far as we are concerned we have been told from day one that HOC will manage and IDM will pay, hence we've invoiced IDM on a monthly basis). …."
It is worth noting that Dacy had not in fact invoiced IDM but had invoiced HOC.
"I realise that Brian has been called into the office and has not left any labour requirements for tomorrow or the weekend, after consulting with Dragos (Dacy) we believe the HOC Site requires the following ……………… "
"To clarify once again it is still a HOC project IDM are assisting financially and administratively, Brian was called to the office without leaving Dragos[Dacy] instructions for tomorrow, I have stepped in to assist."
Conclusion